PART 3E+WChanges before or during construction

Change control applications: consultationE+W

23.—(1) Before determining a change control application relating to a controlled change of a kind described in regulation 18(1)(a) (change control), the regulator must consult—

(a)the enforcing authority (within the meaning of article 25 of the Regulatory Reform (Fire Safety) Order 2005(1)) for the building or proposed building where Part B of Schedule 1 to the 2010 Regulations imposes requirements in relation to the work to which the controlled change relates, and

(b)the sewerage undertaker for the building or proposed building where paragraph H4 of Schedule 1 to the 2010 Regulations imposes requirements in relation to the work to which the controlled change relates.

(2) Where the regulator is required to consult a person under this regulation the regulator—

(a)must give the person sufficient plans to show whether the work would, if carried out in accordance with those plans, comply with—

(i)in the case of the enforcing authority, the applicable requirements of Part B (fire safety) of Schedule 1 to the 2010 Regulations, and

(ii)in the case of the sewerage undertaker, the requirements of paragraph H4 of Schedule 1 to the 2010 Regulations;

(b)must not determine the application until the expiry of a period of 10 working days beginning with the date the consultation starts or such longer period as the regulator and the person consulted agree in writing.

(3) In relation to the consultation under paragraph (1)(a) the plans given must include the fire and emergency file or, where the work to which the application relates is category B work, the fire safety compliance information.

(4) If all persons consulted express their views before the end of the period referred to in paragraph (2)(b) then the prohibition against determining the application ceases to apply on the day after the date on which their views are received by the regulator.

(5) The regulator is not required to consult under this regulation where it is satisfied following consideration of the application there are sufficient grounds to reject the application.

(6) In this regulation, “category B work” has the meaning given in regulation 12 (building control approval applications for work to existing HRB).

Commencement Information

I1Reg. 23 in force at 1.10.2023, see reg. 1(1)

(1)

S.I. 2005/1541 to which there are amendments not relevant to this provision.