Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
44.—(1) The regulator must approve a completion certificate application and issue a completion certificate, if it is satisfied, after taking all reasonable steps, that—
(a)HRB work, stage of HRB work or work to existing HRB is completed and complies with all applicable requirements of the building regulations;
(b)the documents and information listed in regulation 40(2)(a) to (d) (completion certificate applications) and submitted as part of the completion certificate application are complete and accurate;
(c)the information required to be provided to the relevant person in accordance with regulation 38 (handover of information on completion etc) is complete and has been provided.
(2) If the regulator is not satisfied in accordance with paragraph (1) it must reject the completion certificate application.
(3) The regulator must notify the applicant of the outcome of the application (and where the applicant is not the client, also give a copy of the notification to the client) within the period referred to in regulation 41 (completion certificate applications: validity and time limit).
(4) A notice that the application has been rejected must give the reasons for rejection.
(5) If the application is approved the regulator must issue a completion certificate for the higher-risk building at the same time as giving the notice of its decision under paragraph (3).
(6) If requested by the applicant or the relevant person, the regulator must provide a paper copy of the completion certificate.
(7) A certificate issued under this regulation is evidence (but not conclusive evidence) that all applicable requirements of the building regulations have been complied with in relation to the HRB work, the stage of HRB work or, as the case may be, the work to existing HRB.
(8) The certificate must include a statement describing its evidentiary effect, in terms substantially the same as paragraph (7).
(9) When the completion certificate application is approved the client must ensure the relevant person (as defined in regulation 38 (handover of information on completion etc)) is sent—
(a)a copy of the completion certificate application and each of the other documents which accompanied the application, and
(b)a copy of the completion certificate.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: