Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Building control approval applications for HRB work or stage of HRB work: consultationE+W

This section has no associated Explanatory Memorandum

6.—(1) Subject to paragraph (5), before determining a building control approval application for HRB work or a building control approval application for a stage of HRB work the regulator must consult—

(a)the enforcing authority (within the meaning of article 25 of the Regulatory Reform (Fire Safety) Order 2005(1)) for the proposed higher-risk building, and

(b)where paragraph H4 of Schedule 1 to the 2010 Regulations imposes requirements in relation to the work, the sewerage undertaker for the proposed higher-risk building.

(2) Where the regulator is required to consult a person under this regulation the regulator—

(a)must give the person sufficient plans to show whether the HRB work or the stage of HRB work would, if carried out in accordance with those plans, comply with—

(i)in the case of the enforcing authority, the applicable requirements of Part B (fire safety) of Schedule 1 to the 2010 Regulations, and

(ii)in the case of the sewerage undertaker, the requirements of paragraph H4 of Schedule 1 to the 2010 Regulations;

(b)must not determine the application until the expiry of a period of 15 working days beginning with the date the consultation starts or such longer period as the regulator and the person consulted agree in writing.

(3) In relation to the consultation under paragraph (1)(a) the plans given must include the fire and emergency file.

(4) If all persons consulted express their views before the end of the period referred to in paragraph (2)(b) then the prohibition against determining the application ceases to apply on the day after the date on which their views are received by the regulator.

(5) The regulator is not required to consult under this regulation where it is satisfied following consideration of the application there are sufficient grounds to reject the application.

Commencement Information

I1Reg. 6 in force at 1.10.2023, see reg. 1(1)

(1)

S.I. 2005/1541 to which there are amendments not relevant to this provision.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources