Search Legislation

The Building (Higher-Risk Buildings Procedures) (England) Regulations 2023

Status:

This is the original version (as it was originally made).

Contraventions by the regulator not to be subject to enforcement

This section has no associated Explanatory Memorandum

60.  The following provisions of these Regulations are prescribed for the purposes of sections 35(2) and 35B(7)(a) of the 1984 Act—

(a)regulation 5 (building control approval applications for HRB work or stage of HRB work: validity and time limit);

(b)regulation 6(1) and (2) (building control approval applications for HRB work or stage of HRB work: consultation);

(c)regulation 7(1), (4) to (7), (13) and (14) (building control approval applications for HRB work or stage of HRB work: decisions);

(d)regulation 9(4) (notice before starting work and further notice when work is “commenced”);

(e)regulation 13 (building control approval applications for work to existing HRB: validity and time limit);

(f)regulation 14(1) and (2) (building control approval applications for work to existing HRB: consultation);

(g)regulation 15(1), (4) to (7), (13) and (14) (building control approval applications for work to existing HRB: decisions);

(h)regulation 17(4) (notice before starting work and further notice when work is “commenced”);

(i)regulation 22 (change control applications: validity and time limit);

(j)regulation 23(1) and (2) (change control applications: consultation);

(k)regulation 24(1), (4) to (7) and (11)(b) and (d) (change control applications: decisions);

(l)regulation 30(4) and (6) to (8) (variation of a requirement imposed on a building control approval);

(m)regulation 41(1) and (2) (completion certificate applications: validity and time limit);

(n)regulation 42(1) (completion certificate applications: consultation);

(o)regulation 43 (completion certificate applications: inspection);

(p)regulation 44(1) to (6) and (8) (completion certificate applications: decisions);

(q)regulation 45(5), (6), (8), (10) to (15) and (17) (partial completion certificates) except that regulation 45(8) is not prescribed in relation to the regulator consulting a sewerage undertaker;

(r)regulation 47(6) (regularisation of unauthorised building work);

(s)regulation 48(5) to (8) (review of regulator’s decisions);

(t)regulation 53 (section 30A applications: determinations);

(u)regulation 54 (section 30A applications: appointed persons);

(v)regulation 59(2) and (4) (electronic submission and directions).

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources