SCHEDULE 3Transitional, supplementary and saving provisions
PART 1Transitional etc provisions
From April 2024: cases where work has sufficiently progressed but approved inspector is not a registered building control approverI110
1
This paragraph applies where—
a
paragraph 1 applies in relation to a particular building in respect of work for which an initial notice was in force on 6th April 2024 but the approved inspector which gave the notice was not a registered building control approver on that date, and
b
a notice under paragraph 1(4) (notice that work had sufficiently progressed) in relation to that work was received by a local authority before 6th April 2024.
2
Where this paragraph applies—
a
for the purposes of section 47(4)(b)(ii) of the 1984 Act the initial notice or, such part of the notice which relates to the higher-risk building, ceases to be in force with effect from 6th April 2024;
b
if a final certificate relating to the work (or any part of the work which relates to the higher-risk building) has been accepted before 6th April 2024 then with effect from the notice date the function of enforcing building regulations that is conferred on the regulator by section 91(3) of the 1984 Act is not exercisable in relation to that work;
c
if a plans certificate relating to the work (or any part of the work which relates to the higher-risk building) has been accepted before 6th April 2024 then with effect from the notice date the certificate ceases to have effect;
d
accordingly Parts 2 to 6 of these Regulations apply to the work from 6th April 2024 with the modifications provided for in paragraph 5(9) (as applied by paragraph (4));
e
subject to paragraph (f), the 2010 Regulations, to the extent they apply to higher-risk buildings, apply to any of the work from that date;
f
regulation 11(3) of the 2010 Regulations does not apply and accordingly the regulator may exercise the power in section 8(3A) of the 1984 Act to dispense with or relax any requirement of the 2010 Regulations.
3
Where this paragraph applies, with effect from 6th April 2024 the regulator, and not the local authority for the area, is the building control authority in relation to the higher-risk building and accordingly the duties and functions of the regulator under section 91 of the 1984 Act apply in relation to the work to the higher-risk building (but not in relation to any other work specified in the initial notice).
4
The provisions of paragraph 5(4) to (9) also apply but as if any reference to the cancellation date were a reference to 6th April 2024.