xmlns:atom="http://www.w3.org/2005/Atom"
Articles 12, 16, 24 and 41
1. In this Part of this Schedule—
“area of jurisdiction” means the area within the harbour limits, being the area in which the powers of the dock master may be exercised;
“authorised works” means any work, operation or activity that the undertaker is authorised by this Order to construct or carry out;
“environmental document” means—
the environment statement prepared for the purposes of the application for this Order together with any supplementary environmental information or other document so prepared by way of clarification or amplification of the environmental statement; and
any other document containing environmental information provided by the undertaker to the Secretary of State or the Statutory Conservancy and Navigation Authority or Trinity House for the purposes of any tidal works approval under article 37 (provision against danger to navigation), article 38 (lights on tidal works during construction) or article 39 (permanent lights on tidal works);
“plans” includes sections, drawings, specifications, calculations and method statements;
“the river” means the River Humber; and
“
” means for the purposes of this Protective Provision Associated British Ports in its capacity as statutory conservancy and navigation authority for the river Humber (as successor to the Conservancy Commissioners established under the Humber Conservancy Act 1868) and including in its role as competent harbour authority and local lighthouse authority for its statutory area.2.—(1) The provisions of this Part of this Schedule, unless otherwise agreed in writing between the undertaker and the Statutory Conservancy and Navigation Authority, have effect until the commencement of the operation of the authorised development for the protection of the Statutory Conservancy and Navigation Authority and the users of the river.
(2) For the purposes of this Part of this Schedule, the definition of “tidal work” is taken to include—
(a)any projection over the river outside the area of jurisdiction by booms, cranes and similar plant or machinery, whether or not situated within the area of jurisdiction; and
(b)any authorised work which affects the river or any functions of the Statutory Conservancy and Navigation Authority , whether or not that authorised work is within the limits of the Statutory Conservancy and Navigation Authority.
3.—(1) Prior to the commencement of the authorised development in the marine environment the undertaker must submit to the Statutory Conservancy and Navigation Authority plans and sections of the tidal works or operation and such further particulars as the Statutory Conservancy and Navigation Authority may, within 28 days from the day on which plans and sections are submitted under this sub-paragraph, reasonably require.
(2) Any approval of the Statutory Conservancy and Navigation Authority required under this paragraph shall be deemed to have been given if it is neither given nor refused (or is refused but without an indication of the grounds for refusal) within 28 days of the day on which the request for consent is submitted under sub-paragraph (1) must not be unreasonably withheld but may be given subject to such reasonable requirements as the Statutory Conservancy and Navigation Authority may make for the protection of—
(a)traffic in, or the flow or regime of, the river;
(b)the use of its operational land or the river for the purposes of performing its functions; or
(c)the performance of any of its functions connected with environmental protection.
(3) Requirements made under sub-paragraph (2) may include conditions as to—
(a)the relocation, provision and maintenance of works, moorings, apparatus and equipment necessitated by the tidal work; and
(b)the expiry of the approval if the undertaker does not commence construction of the tidal work approved within a prescribed period.
(4) Before making a decision on any such approval, the Statutory Conservancy and Navigation Authority must take into account any opinion on plans and sections provided to it by the Environment Agency.
(5) Whenever the undertaker provides the Secretary of State with an environmental document it must at the same time send a copy to the Statutory Conservancy and Navigation Authority.
4. Any operations for the construction of any tidal work approved in accordance with this Order, once commenced, must be carried out by the undertaker without unnecessary delay and to the reasonable satisfaction of the Statutory Conservancy and Navigation Authority so that river traffic, the flow or regime of the river and the exercise of the Statutory Conservancy and Navigation Authority’s functions do not suffer more interference than is reasonably practicable, and an authorised officer of the Statutory Conservancy and Navigation Authority is entitled at all reasonable times, on giving such notice as may be reasonable in the circumstances, to inspect and survey such operations.
5.—(1) The undertaker must not without the Consent of the Statutory Conservancy and Navigation Authority—
(a)deposit in or allow to fall or be washed into the river any gravel, soil or other material; or
(b)discharge or allow to escape either directly or indirectly into the river any offensive or injurious matter in suspension or otherwise.
(2) Any consent of the Statutory Conservancy and Navigation Authority under this paragraph must not be unreasonably withheld but may be given subject to such terms and conditions as the Statutory Conservancy and Navigation Authority may reasonably impose.
(3) Any such approval is deemed to have been given if it is neither given nor refused (or is refused but without an indication of the grounds for refusal) within 28 days of the day on which the request for consent is submitted under sub-paragraph (1).
(4) In its application to the discharge of water into the river, article 24 (discharge of water) has effect subject to the terms of any conditions attached to a consent given under this paragraph.
(5) The undertaker must not, in exercise of the powers conferred by article 24 (discharge of water), damage or interfere with the beds or banks of any watercourse forming part of the river unless such damage or interference is approved as a tidal work under this Order or is otherwise approved in writing by the Statutory Conservancy and Navigation Authority.
6. If any pile, stump or other obstruction to navigation becomes exposed in the course of constructing any tidal work (other than a pile, stump or other obstruction on the site of a structure comprised in any permanent work), the undertaker, as soon as reasonably practicable after the receipt of notice in writing from the Statutory Conservancy and Navigation Authority requiring such action, must remove it from the river or, if it is not reasonably practicable to remove it—
(a)cut the obstruction off at such level below the bed of the river as the Statutory Conservancy and Navigation Authority may reasonably direct; or
(b)take such other steps to make the obstruction safe as the Statutory Conservancy and Navigation Authority may reasonably require.
7. If—
(a)by reason of the construction of any tidal work it is reasonably necessary for the Statutory Conservancy and Navigation Authority to incur reasonable costs in temporarily or permanently altering, removing, re-siting, repositioning or reinstating existing moorings or aids to navigation (including navigation marks or lights) owned by the Statutory Conservancy and Navigation Authority, or laying down and removing substituted moorings or buoys, or carrying out dredging operations for any such purpose, not being costs which it would have incurred for any other reason; and
(b)the Statutory Conservancy and Navigation Authority gives to the undertaker not less than 28 days’ notice of its intention to incur such costs, and takes into account any representations which the undertaker may make in response to the notice within 14 days of the receipt of the notice,
the undertaker must pay the costs reasonably so incurred by the Statutory Conservancy and Navigation Authority.
8. In addition to any requirement imposed under this Order the undertaker, at or near every tidal work, and any other work of which the undertaker is in possession in exercise of any of the powers conferred by this Order (being in either case a work which is below mean high water level forming part of the River Humber), must exhibit such lights, lay down such buoys and take such other steps for preventing danger to navigation as the Statutory Conservancy and Navigation Authority may from time to time reasonably require.
9. On completion of the construction of any part of a permanent authorised work, the undertaker must as soon as practicable remove—
(a)any temporary tidal work carried out only for the purposes of that part of the permanent work; and
(b)any materials, plant and equipment used for such construction,
and must make good the site to the reasonable satisfaction of the Statutory Conservancy and Navigation Authority.
10.—(1) If any tidal work—
(a)is constructed otherwise than in accordance with the requirements of this Part of this Schedule or with any condition in an approval given pursuant to paragraph 3; or
(b)during construction gives rise to sedimentation, scouring, currents or wave action detrimental to traffic in, or the flow or regime of, the river,
then the Statutory Conservancy and Navigation Authority may by notice in writing require the undertaker at the undertaker’s own expense to comply with the remedial requirements specified in the notice.
(2) The requirements that may be specified in a notice given under sub-paragraph (1) are—
(a)in the case of a tidal work to which sub-paragraph (1)(a) applies, such requirements as may be specified in the notice for the purpose of giving effect to the requirements of—
(i)this Part of this Schedule; or
(ii)the condition that has been breached; or
(b)in any case within sub-paragraph (1)(b), such requirements as may be specified in the notice for the purpose of preventing, mitigating or making good the sedimentation, scouring, currents or wave action so far as required by the needs of traffic in, or the flow or regime of, the river.
(3) If the undertaker does not comply with a notice under sub-paragraph (1), or is unable to do so, the Statutory Conservancy and Navigation Authority may in writing require the undertaker to—
(a)remove, alter or pull down the tidal work, and where the tidal work is removed to restore the site of that work (to such extent as the Statutory Conservancy and Navigation Authority reasonably requires) to its former condition; or
(b)take such other action as the Statutory Conservancy and Navigation Authority may reasonably specify for the purpose of remedying the non-compliance to which the notice relates.
(4) If a tidal work gives rise to environmental impacts over and above those anticipated by any environmental document, the undertaker, in compliance with its duties under any enactment and, in particular, under section 48A of the Harbours Act 1964(1), must take such action as is necessary to prevent or mitigate those environmental impacts and in doing so must consult and seek to agree the necessary measures with the Statutory Conservancy and Navigation Authority.
(5) If the Statutory Conservancy and Navigation Authority becomes aware that any tidal work is causing an environmental impact over and above those anticipated by any environmental document, the Statutory Conservancy and Navigation Authority must notify the undertaker of that environmental impact, the reasons why the Statutory Conservancy and Navigation Authority believes that the environmental impact is being caused by the tidal work and of measures that the Statutory Conservancy and Navigation Authority reasonably believes are necessary to counter or mitigate that environmental impact.
(6) The undertaker must implement the measures that the Statutory Conservancy and Navigation Authority has notified to the undertaker or must implement such other measures as the undertaker believes are necessary to counter the environmental impact identified, giving reasons to the Statutory Conservancy and Navigation Authority as to why it has implemented such other measures.
11.—(1) If any tidal work or any other work of which the undertaker is in possession in exercise of any of the powers conferred by this Order (being in either case a work which is below mean high water level) is abandoned or falls into decay, the Statutory Conservancy and Navigation Authority may by notice in writing require the undertaker to take such reasonable steps as may be specified in the notice either to repair or restore the work, or any part of it, or to remove the work and (to such extent as the Statutory Conservancy and Navigation Authority reasonably requires) to restore the site to its former condition.
(2) If any tidal work is in such condition that it is, or is likely to become, a danger to or an interference with navigation in the river, the Statutory Conservancy and Navigation Authority may by notice in writing require the undertaker to take such reasonable steps as may be specified in the notice—
(a)to repair and restore the work or part of it; or
(b)if the undertaker so elects, to remove the tidal work and (to such extent as the Statutory Conservancy and Navigation Authority reasonably requires) to restore the site to its former condition.
(3) If after such reasonable period as may be specified in a notice under this paragraph the undertaker has failed to begin taking steps to comply with the requirements of the notice, or after beginning has failed to make reasonably expeditious progress towards their implementation, the Statutory Conservancy and Navigation Authority may carry out the works specified in the notice and any expenditure reasonably incurred by it in so doing is recoverable from the undertaker.
12.—(1) The undertaker must not in the exercise of the powers conferred by this Order interfere with any marks, lights or other navigational aids in the river without the agreement of the Statutory Conservancy and Navigation Authority and must ensure that access to such aids remains available during and following construction of any tidal works.
(2) The undertaker must provide at any tidal works, or must afford reasonable facilities at such works (including an electricity supply) for the Statutory Conservancy and Navigation Authority to provide at the undertaker’s cost, from time to time, such navigational lights, signals, radar or other apparatus for the benefit, control and direction of navigation of users of the river in general as the Statutory Conservancy and Navigation Authority may deem necessary by reason of the construction of any tidal works, and must ensure that access remains available to apparatus during and following construction of such works.
(3) The undertaker must comply with the directions of the Statutory Conservancy and Navigation Authority from time to time with regard to the lighting on the tidal works or within the harbour, or the screening of such lighting, so as to ensure safe navigation on the river.
13.—(1) This paragraph applies if any part of the river becomes subject to sedimentation, scouring, currents or wave action which—
(a)is, during the period beginning with the commencement of the construction of that tidal work and ending with the expiration of 10 years after the date on which all the tidal works constructed under this Order are completed, wholly or partly caused by a tidal work; and
(b)for the safety of navigation or for the protection of works in the river, should in the reasonable opinion of the Statutory Conservancy and Navigation Authority be removed or made good.
(2) The undertaker must either—
(a)pay to the Statutory Conservancy and Navigation Authority any additional expense to which the Statutory Conservancy and Navigation Authority may reasonably be put in dredging the river to remove the sedimentation or in making good the scouring so far as (in either case) it is attributable to the tidal work; or
(b)carry out the necessary dredging at its own expense and subject to the prior approval of the Statutory Conservancy and Navigation Authority, such prior approval not to be unreasonably withheld or delayed;
and the reasonable expenses payable by the undertaker under this paragraph include any additional expenses accrued or incurred by the Statutory Conservancy and Navigation Authority in carrying out surveys or studies in connection with the implementation of this paragraph.
14.—(1) The undertaker is responsible for and must make good to the Statutory Conservancy and Navigation Authority all reasonable financial costs or losses not otherwise provided for in this Part of this Schedule which may reasonably be incurred or suffered by the Authority by reason of—
(a)the construction or operation of the authorised works or the failure of the authorised works;
(b)anything done in relation to a mooring or buoy under paragraph 8; or
(c)any act or omission of the undertaker, its employees, contractors or agents or others whilst engaged upon the construction or operation of the authorised works or dealing with any failure of the authorised works,
and the undertaker must indemnify the Statutory Conservancy and Navigation Authority from and against all claims and demands arising out of or in connection with the authorised works or any such failure, act or omission.
(2) The fact that any act or thing may have been done—
(a)by the Statutory Conservancy and Navigation Authority on behalf of the undertaker; or
(b)by the undertaker, its employees, contractors or agents in accordance with plans or particulars submitted to or modifications or conditions specified by the Statutory Conservancy and Navigation Authority, or in a manner approved by the Statutory Conservancy and Navigation Authority, or under its supervision or the supervision of its duly authorised representative,
does not (if it was done or required without negligence on the part of the Statutory Conservancy and Navigation Authority or its duly authorised representative, employee, contractor or agent) excuse the undertaker from liability under the provisions of this paragraph.
(3) The Statutory Conservancy and Navigation Authority must give the undertaker reasonable notice of any such claim or demand as is referred to in sub-paragraph (1), and no settlement or compromise of any such claim or demand is to be made without the prior consent of the undertaker.
15.—(1) Subject to article 3 (disapplication and modification of legislative provisions) and this paragraph, any function of the undertaker or any officer of the undertaker, whether conferred by or under this Order or any other enactment, is subject to—
(a)any enactment relating to the Statutory Conservancy and Navigation Authority;
(b)any byelaw, direction or other requirement made by the Statutory Conservancy and Navigation Authority under any enactment; and
(c)any other exercise by the Statutory Conservancy and Navigation Authority of any function conferred by or under any enactment.
(2) The undertaker must not take any action in the river outside the area of jurisdiction under sections 57 and 65 of the 1847 Act as incorporated by article 4 (incorporation of the Act of 1847) except with the consent of the harbour master, which must not be unreasonably withheld.
(3) The dock master must not give or enforce any special direction to any vessel under section 52 of the 1847 Act, as incorporated by article 4 (incorporation of the 1847 Act), if to do so would conflict with a special direction given to the same vessel by the harbour master.
(4) The Statutory Conservancy and Navigation Authority must consult the undertaker before making any byelaw which directly applies to or which could directly affect the construction, operation or maintenance of the authorised development.
(5) The Statutory Conservancy and Navigation Authority must consult the undertaker before giving any general direction which directly affects the construction, operation or maintenance of the authorised development.
16.—(1) Before commencing marine commercial operations the undertaker must submit to the Statutory Conservancy and Navigation Authority for approval a written statement of proposed safe operating procedures for access to and egress from the authorised development.
(2) The undertaker must not submit the statement referred to in sub–paragraph (1) unless it has first consulted with the harbour master, the dock master for the Port of Immingham and the IOT Operators, as defined in Part 4 of this Schedule, and has had due regard to their representations.
(3) Prior to granting or refusing approval of the statement referred to in sub–paragraph (1), the Statutory Conservancy and Navigation Authority may carry out its own navigational risk assessment and may impose reasonable conditions on the approval for the purposes set out in paragraph 3(2)(a) to (c) of this Part of this Schedule.
(4) The undertaker must operate the authorised development only in accordance with such procedure as approved, including any approved alteration made from time to time.
17. The undertaker must consult the Statutory Conservancy and Navigation Authority before submitting any oil pollution emergency plan to the Maritime and Coastguard Agency and must ensure that any such plan is compatible with the Statutory Conservancy and Navigation Authority’s existing plan known as “Humber Clean” or such other plan as supersedes “Humber Clean”.
18.—(1) The following provisions shall apply for the protection of the Agency unless otherwise agreed in writing between the undertaker and the Agency.
(2) In this part of this Schedule—
“the Agency” means the Environment Agency;
“construction” includes execution, placing, altering, replacing, relaying and removal and excavation and “construct” and “constructed” shall be construed accordingly;
“flood management infrastructure” includes any bank, wall, embankment or other structure, or any appliance, constructed or used for land drainage, flood defence or tidal monitoring;
“plans” includes sections, drawings, specifications, calculations and method statements; and
“specified work” means any part of the authorised development that intersects with or sits over or above, touches or otherwise interferes with the flood management infrastructure, including the maintenance and inspection thereof.
19.—(1) Prior to the commencement of any specified work, the undertaker must submit to the Agency plans of the specified work and such further particulars available to it as the Agency may within 28 days of receipt of the plans reasonably request.
(2) Any such specified work must not be constructed except in accordance with such plans as may be approved in writing by the Agency, or determined under paragraph 23.
(3) Any approval of the Agency required under this paragraph—
(a)must not be unreasonably withheld or delayed;
(b)is deemed to have been refused if it is neither given nor refused within 2 months of the submission of the plans or receipt of further particulars if such particulars have been requested by the Agency for approval; and
(c)may be given subject to such reasonable requirements as the Agency may have for the protection of any flood management infrastructure or for the prevention of flooding or pollution or in the discharge of its environmental duties.
(4) The Agency must use its reasonable endeavours to respond to the submission of any plans before the expiration of the period mentioned in sub-paragraph (3)(b).
(5) In the case of a refusal, if requested to do so, the Agency must provide reasons for the grounds of refusal.
20. The undertaker must ensure—
(a)that the authorised development including the associated development does not touch any existing flood management infrastructure; and
(b)that the authorised development including the associated development does not impede the Agency’s access to the flood management infrastructure for maintenance and inspection purposes and where required the development is constructed to a sufficient height above the flood management infrastructure to facilitate the aforesaid access.
21. On completion of the works, all debris and surplus material must be removed from the land adjacent to the flood defence to avoid erosion, to the satisfaction of the Agency.
22. The undertaker must bring the conditions contained in paragraphs 19 to 21 to the attention of any agent or contractor responsible for carrying out the authorised development.
23. Any dispute arising between the undertaker and the Agency under this part of this Schedule shall, if the parties agree, be determined by arbitration under article 35 (arbitration), but shall otherwise be determined by the Secretary of State for Environment, Food and Rural Affairs or its successor and the Secretary of State for Transport or its successor acting jointly on a reference to them by the undertaker or the Agency, after notice in writing by one to the other.
24. For the protection of Exolum the following provisions, unless otherwise agreed in writing at any time between the undertaker and Exolum, have effect until the commencement of the operation of the authorised development.
25. In this Protective Provision—
“apparatus” means the pipe-line and storage system and ancillary apparatus owned, operated or maintained by Exolum and includes any structure in which apparatus is or is to be lodged or which gives or will give access to apparatus;
“Exolum” means Exolum Pipeline System Ltd and Exolum Immingham Limited and any successor in title;
“functions” includes powers and duties;
“in” in a context referring to apparatus in land, includes a reference to apparatus under, over or upon land;
“pipe-line” means the whole or any part of a pipe-line belonging to or maintained by Exolum and includes any ancillary works and apparatus; all protective wrappings, valves, sleeves and slabs, cathodic protection units, together with ancillary cables and markers; and such legal interest and benefit of property rights and covenants as are vested in Exolum in respect of those items;
“plan” includes all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe the works to be executed;
“premises” means land that Exolum owns, occupies or otherwise has rights to use including but not limited to storage facilities and jetties;
“specified work” means any work which will or may be situated on, over, under or within 15 metres measured in any direction of any apparatus, or (wherever situated) impose any load directly upon any apparatus or involve embankment works within 15 metres of any apparatus; and
“working day” means any day other than a Saturday, Sunday or English bank or public holiday.
26. Irrespective of any provision in this Order or anything shown on the land plans—
(a)the undertaker may not acquire any apparatus, premises or any right of Exolum in respect of any apparatus or any of Exolum’s interests in land;
(b)the undertaker must not obstruct or render less convenient the access to any apparatus or premises or interfere with or affect Exolum’s ability to operate the apparatus, otherwise than by agreement with Exolum, agreement not to be unreasonably delayed or withheld;
(c)any right of Exolum to maintain, repair, renew, adjust, alter or inspect any apparatus may not be extinguished by the undertaker until any necessary alternative apparatus which allows Exolum to fulfil its functions in a manner not less efficient than previously has been constructed and is in operation to the reasonable satisfaction of Exolum;
(d)the undertaker must not require that any apparatus is relocated or diverted or removed, otherwise than by agreement with Exolum; and
(e)where alternative apparatus is proposed or reasonably necessary in consequence of the exercise of any of the powers conferred by the Order, the undertaker must afford to Exolum the necessary facilities and rights for the construction of any alternative apparatus.
27.—(1) In this paragraph—
“relevant works” means any works forming any part of the authorised development as do, will or are likely to affect any apparatus or Exolum’s access to any apparatus including those which involve—
a physical connection or attachment to any apparatus;
works within 15 metres of any apparatus;
the crossing of any apparatus by other utilities;
the use of explosives within 400 metres of any apparatus; or
piling, undertaking of a 3D seismic survey or the sinking of boreholes within 30 metres of any apparatus.
(2) Unless a shorter period is otherwise agreed in writing between the undertaker and Exolum, not less than 35 days before commencing any relevant works, the undertaker must submit to Exolum the works details for the relevant works and such further particulars as Exolum may reasonably require and submit to the Undertaker within 28 days of receipt of the works details and no relevant works are to be commenced until Exolum, acting reasonably, has approved the works details.
(3) The relevant works must be executed only in accordance with the works details approved by Exolum under this sub-paragraph 3 including any reasonable requirements notified to the undertaker by Exolum and Exolum shall be entitled to observe and inspect the execution of those works.
(4) Nothing in this Schedule shall authorise the undertaker to execute the placing, installation, bedding, packing, removal, connection or disconnection of any apparatus, or execute any filling around the apparatus (where the apparatus is laid in a trench) within 3 metres of the apparatus unless that apparatus is redundant and disconnected from Exolum’s remaining system.
(5) If Exolum, in accordance with sub-paragraph 27(2), and in consequence of the works proposed by the undertaker, reasonably requires the removal of any Apparatus and gives written notice to the undertaker of that requirement, this deed applies as if the removal of the Apparatus had been required by the undertaker and agreed with Exolum pursuant to sub-paragraph 27(2).
(6) Nothing in this sub-paragraph (6) precludes the undertaker from submitting at any time or from time to time, but (unless otherwise agreed in writing between the undertaker and Exolum) in no case less than 28 days before commencing the execution of any relevant works, new works details, instead of the works details previously submitted, and having done so the provisions of this sub-paragraph 6 apply to and in respect of the new works details.
(7) In relation to works which will or may be situated on, over, under or within 15 metres measured in any direction of the apparatus, or (wherever situated) impose any load directly upon the apparatus or involve embankment works within 15 metres of the apparatus, the works details to be submitted to Exolum under sub-paragraph 27(2) shall be detailed including a method statement describing—
(a)the exact position of the works;
(b)the level at which the works are to be constructed or renewed;
(c)the manner of their construction or renewal;
(d)the position of the apparatus; and
(e)by way of detailed drawings, every alteration proposed to be made to the apparatus.
28.—(1) Subject to the following provisions of this paragraph, the undertaker must pay to Exolum the reasonable costs and expenses incurred by Exolum in, or in connection with—
(a)the inspection, removal, alteration or works for the protection of any apparatus;
(b)the observation and inspection of the execution of any specified work including relevant works;
(c)the imposition of reasonable requirements for the protection or alteration of apparatus; and
(d)the undertaking by Exolum of its obligations under this protective provision including the review and assessment of plans and works details.
which may reasonably be required in consequence of the execution of any such works as are required under this protective provision.
(2) The undertaker shall pay Exolum’s reasonable direct costs incurred in the management and handling of any expenses paid under this protective provision.
(3) There will be no deduction from any sum payable under this protective provision as a result of—
(a)the placing of apparatus of a better type, greater capacity or of greater dimensions, or at a greater depth than the existing apparatus; or
(b)the placing of apparatus in substitution of the existing apparatus that may defer the time for renewal of the existing apparatus in the ordinary course.
(4) Upon the submission of an invoice detailing the proper and reasonable costs and expenses incurred by Exolum, the undertaker shall pay Exolum within 30 days from the date on which the invoice is received.
29.—(1) Subject to the following provisions of this paragraph, the undertaker must pay to Exolum the reasonable costs and expenses incurred by Exolum in, or in connection with—
(a)pay Exolum for all loss, damage, liability, costs and expenses reasonably suffered or incurred by Exolum for which Exolum is legally liable as a result of legally sustainable claims brought against Exolum by any third party solely arising out of the carrying out of any works associated with the authorised development;
(b)pay the cost reasonably incurred by Exolum in making good any damage to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal or abandonment) arising from or caused by the carrying out of any works associated with the authorised development; and
(c)pay the cost reasonably incurred by Exolum in stopping, suspending and restoring the supply through its pipeline and make reasonable compensation to Exolum for any other expenses, losses, damages, penalty or costs incurred by Exolum by reason or in consequence of any such damage or interruption provided that the same arises in consequence of the carrying out of any works associated with the authorised development.
(2) Irrespective of anything to the contrary elsewhere in this protective provision—
(a)the undertaker and Exolum must at all times take reasonable steps to prevent and mitigate any loss, damage, liability, claim, cost or expense (whether indemnified or not) which either suffers as a result of the other’s negligence or breach of this protective provision; and
(b)neither the undertaker nor Exolum are liable for any loss, damage, liability, claim, cost or expense suffered or incurred by the other to the extent that the same are incurred as a result of or in connection with the sole, partial or complete breach of this protective provision or negligence arising out of an act, omission, default or works of the other, its officers, servants, contractors or agents.
(3) Exolum must give to the undertaker reasonable notice of any claim or demand to which this paragraph 30 applies. The undertaker may at its own expense conduct all negotiations for the settlement of the same and any litigation that may arise therefrom. Exolum must not compromise or settle any such claim or make any admission which might be prejudicial to the claim. Exolum must, at the request of the undertaker, afford all reasonable assistance for the purpose of contesting any such claim or action, and is entitled to be repaid all reasonable expenses incurred in so doing.
(4) The requirement to give reasonable notice of any claim or demand to the undertaker in sub-paragraph (3) above shall not apply in the event of an emergency or where the safety of the apparatus is at risk, in which case Exolum may take necessary action and notify the undertaker of its costs promptly afterwards.
30.—(1) Where in consequence of the proposed construction of any of the authorised development, Exolum requires the protection or alteration of apparatus under the terms of this protective provision, the undertaker must use its best endeavours to co–ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of Exolum’s undertaking.
(2) Exolum must use reasonable endeavours to cooperate with the undertaker for the purposes outlined in this paragraph 30.
(3) The undertaker and Exolum must act reasonably in respect of any given term of this protective provision and, in particular, (without prejudice to generality) where any consent or expression of satisfaction is required by this protective provision it must not be unreasonably withheld or delayed.
31. Nothing in this protective provision affects the provisions of any enactment or agreement regulating the relations between the undertaker and Exolum in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made provided that the terms of the relevant enactment or agreement are not inconsistent with the provisions of this Order. In the case of any inconsistency, in the context of the authorised development, the provisions of this Order prevail.
32. Any dispute arising between the Undertaker and Exolum under this Part of this Schedule is to be determined by arbitration in accordance with article 35 (arbitration).
33.—(1) The undertaker acknowledges that Exolum provides services to His Majesty’s Government, using its apparatus, which may affect any works to be carried under this Order.
(2) In the following circumstances, Exolum may on written notice to the undertaker immediately suspend all works that necessitate the stopping or suspending of the supply of product through any apparatus under this Order and Exolum shall not be in breach of its obligations to proceed—
(a)circumstances in which, in the determination of the Secretary of State, there subsists a material threat to national security, or a threat or state of hostility or war or other crisis or national emergency (whether or not involving hostility or war); or
(b)circumstances in which a request has been received, and a decision to act upon such request has been taken, by His Majesty’s Government for assistance in relation to the occurrence or anticipated occurrence of a major accident, crisis or natural disaster; or
(c)circumstances in which a request has been received from or on behalf of NATO, the EU, the UN, the International Energy Agency (or any successor agency thereof) or the government of any other state for support or assistance pursuant to the United Kingdom’s international obligations and a decision to act upon such request has been taken by His Majesty’s Government or the Secretary of State; or
(d)any circumstances identified by the COBRA committee of His Majesty’s Government (or any successor committee thereof); or
(e)any situation, including where the United Kingdom is engaged in any planned or unplanned military operations within the United Kingdom or overseas, in connection with which the Secretary of State requires fuel capacity.
(3) The parties agree to act in good faith and in all reasonableness to agree any revisions to any schedule, programme or costs estimate (which shall include costs of demobilising and remobilising any workforce, and any costs to protect Exolum’s apparatus “mid-works”) to account for the suspension.
(4) Exolum shall not be liable for any costs, expenses, losses or liabilities the undertaker incurs as a result of the suspension of any activities under this paragraph or delays caused by it.
34. The provisions of this Part of this Schedule shall apply for the protection of the IOT Operators, unless otherwise agreed in writing at any time between the undertaker and the IOT Operators.
35. In this Part of this protective provision—
“apparatus” means the pipe-line and storage system owned or maintained by the IOT Operators and includes any structure in which apparatus is or is to be lodged or which gives or will give access to apparatus;
“Associated Petroleum Terminals (Immingham) Ltd” means Associated Petroleum Terminals (Immingham) Limited, company number 00564394 registered at Queens Road, Immingham, Grimsby, N E Lincolnshire, DN40 2PN, and any successor in title;
“functions” includes powers and duties;
“Humber Oil Terminal Trustees Ltd” means Humber Oil Terminal Trustees Limited, company number 00874993 registered at Queens Road, Immingham, Grimsby, N E Lincolnshire, DN40 2PN, and any successor in title;
“in” in a context referring to apparatus in land, includes a reference to apparatus under, over or upon land;
“IOT Operators” means Associated Petroleum Terminals (Immingham) Ltd and Humber Oil Terminal Trustees Ltd;
“pipe-line” means the whole or any part of a pipe-line belonging to or maintained by IOT Operators and includes any ancillary works and apparatus; all protective wrappings, valves, sleeves and slabs, cathodic protection units, together with ancillary cables and markers; and such legal interest and benefit of property rights and covenants as are vested in IOT Operators in respect of those items;
“specified work” means any work which will or may be situated on, over, under or within 15 metres measured in any direction of any apparatus, or (wherever situated) impose any load directly upon any apparatus or involve embankment works within 15 metres of any apparatus; and
“working day” means any day other than a Saturday, Sunday or English bank or public holiday.
36. Irrespective of any provision in this Order or anything shown on the land plans—
(a)the undertaker may not acquire any apparatus or obstruct or render less convenient the access to any apparatus, otherwise than by agreement with the IOT Operators; and
(b)any right of the IOT Operators to maintain, repair, renew, adjust, alter or inspect any apparatus may not be extinguished by the undertaker until any necessary alternative apparatus has been constructed and is in operation to the reasonable satisfaction of the IOT Operators.
37. Subject to the following provisions of this paragraph, during the construction of the authorised development the undertaker must pay to IOT Operators the reasonable costs and expenses incurred by the IOT Operators in, or in connection with—
(a)the inspection, removal, alteration or protection of any apparatus; or
(b)the watching and inspecting the execution of any specified work; or
(c)the imposition of reasonable requirements for the protection or alteration of apparatus,
which may reasonably be required in consequence of the execution of any such works as are required under this Schedule.
38.—(1) Subject to the following provisions of this paragraph, the undertaker must—
(a)grant the IOT Operators, upon reasonable notice access to any apparatus during the carrying out of any relevant works reasonably required for the purposes of inspection, maintenance and repair of such apparatus and upon reasonable notice. For the purposes of this subparagraph (a), ‘apparatus’ includes any connection into pipelines or associated infrastructure operated by the IOT Operators and/or any successor pipeline system operator.
(b)pay the IOT Operators for all loss, damage, liability, costs and expenses reasonably suffered or incurred by the IOT Operators for which the IOT Operators is legally liable as a result of legally sustainable claims brought against the IOT Operators by any third party solely arising out of the carrying out of any relevant works;
(c)pay the cost reasonably incurred by the IOT Operators in making good any damage to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal or abandonment) arising from or caused by the carrying out of any relevant works; and
(d)pay the cost reasonably incurred by the IOT Operators in stopping, suspending and restoring the supply through its pipeline and make reasonable compensation to the IOT Operators for any other expenses, losses, damages, penalty or costs incurred by the IOT Operators by reason or in consequence of any such damage or interruption provided that the same arises in consequence of the carrying out of any relevant works.
(2) Irrespective of anything to the contrary elsewhere in this protective provision—
(a)the undertaker and the IOT Operators must at all times take reasonable steps to prevent and mitigate any loss, damage, liability, claim, cost or expense (whether indemnified or not) which either suffers as a result of the other’s negligence or breach of this Part of this Schedule; and
(b)neither the undertaker nor the IOT Operators are liable for any loss, damage, liability, claim, cost or expense suffered or incurred by the other to the extent that the same are incurred as a result of or in connection with the sole, partial or complete breach of this protective provision or negligence arising out of an act, omission, default or works of the other, its officers, servants, contractors or agents.
(3) The IOT Operators must give to the undertaker reasonable notice of any claim or demand to which this paragraph 38 applies. The undertaker may at its own expense conduct all negotiations for the settlement of the same and any litigation that may arise therefrom. The IOT Operators must not compromise or settle any such claim or make any admission which might be prejudicial to the claim. The IOT Operators must, at the request of the undertaker, afford all reasonable assistance for the purpose of contesting any such claim or action, and is entitled to be repaid all reasonable expenses incurred in so doing.
(4) In this paragraph—
“relevant works” means such of the authorised development as—
does, will or is likely to affect any apparatus; or
involves a physical connection or attachment to any apparatus.
39.—(1) Where as a consequence of the construction of any part of the authorised development, the undertaker requires the removal of apparatus or the IOT Operators, acting reasonably, requires the protection or alteration of apparatus, the undertaker must, if it agrees that such works are necessary, use its best endeavours to co–ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of the IOT Operators’ undertaking and the IOT Operators must use its best endeavours to cooperate with the undertaker for that purpose.
(2) the undertaker and the IOT Operators must act reasonably in compliance with the terms of this protective provision and, in particular, (without prejudice to generality) where any consent or expression of satisfaction is required it must not be unreasonably withheld or delayed.
40. Nothing in this protective provision affects the provisions of any enactment or agreement regulating the relations between the undertaker and the IOT Operators in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made provided that in connection with the construction of the authorised development, the terms of the relevant enactment or agreement are not inconsistent with the provisions of this Order, including this protective provision. In the case of any inconsistency in the context of the authorised development, the provisions of this Order, including this protective provision, prevail.
41.—(1) The undertaker acknowledges that the IOT Operators provides services to His Majesty’s Government, using its apparatus, which may affect any works to be carried under this Order.
(2) In the following circumstances, the IOT Operators may on written notice to the undertaker require the immediate suspension of works to construct the authorised development if such works necessitate the stopping or suspending of the supply of product through any apparatus and the IOT Operators shall not be in breach of its obligations under this protective provision in circumstances—
(a)in which, in the determination of the Secretary of State, there subsists a material threat to national security, or a threat or state of hostility or war or other crisis or national emergency (whether or not involving hostility or war); or
(b)in which a request has been received, and a decision to act upon such request has been taken, by His Majesty’s Government for assistance in relation to the occurrence or anticipated occurrence of a major accident, crisis or natural disaster; or
(c)in which a request has been received from or on behalf of NATO, the EU, the UN, the International Energy Agency (or any successor agency thereof) or the government of any other state for support or assistance pursuant to the United Kingdom’s international obligations and a decision to act upon such request has been taken by His Majesty’s Government or the Secretary of State; or
(d)identified by the COBRA committee of His Majesty’s Government (or any successor committee thereof) as identified as falling within any of the above sub-paragraphs of this paragraph; or
(e)where the United Kingdom is engaged in any planned or unplanned military operations within the United Kingdom or overseas, in connection with which the Secretary of State requires fuel capacity.
(3) The parties agree to act in good faith and in all reasonableness to agree any revisions to any schedule, programme or costs estimate (which shall include costs of demobilising and remobilising any workforce, and any costs to protect the IOT Operators’ apparatus “mid-works”) to account for the suspension.
(4) The IOT Operators shall not be liable for any costs, expenses, losses or liabilities the undertaker incurs as a result of the suspension of any activities under this paragraph or delays caused by it.
42. For the protection of Northern Powergrid the following provisions, unless otherwise agreed in writing between the undertaker and Northern Powergrid, have effect for the duration of the construction of the authorised works, including (for the avoidance of doubt)—
(a)where this Order is amended by way of supplementary order, then the following provisions have effect for the construction of the development authorised by such supplementary order; and
(b)where a diversion or replacement of Northern Powergrid’s apparatus is required during the construction phase of this Order or any supplementary order, the following provisions have effect for as long as it takes for the diversion or replacement to be completed.
43. In this Part of this Schedule—
“alternative apparatus” means alternative apparatus adequate to enable Northern Powergrid to fulfil its statutory functions in a manner not less efficient than previously;
“apparatus” means electric lines or electrical plant (as defined in the Electricity Act 1989(2)), belonging to or maintained by Northern Powergrid and includes any structure in which apparatus is or is to be lodged or which gives or will give access to apparatus;
“authorised works” means so much of the works authorised by this Order which affect existing Northern Powergrid’s apparatus within the Order limits;
“functions” includes powers and duties;
“in”, in a context referring to apparatus or alternative apparatus in land, includes a reference to apparatus or alternative apparatus under, over or upon land;
“Northern Powergrid” means Northern Powergrid (Yorkshire) PLC (Company Number 04112320) whose registered address is Lloyds Court, 78 Grey Street, Newcastle upon Tyne NE1 6AF;
“plan” includes all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe the works to be executed and shall include measures proposed by the undertaker to ensure the grant of sufficient land or rights in land necessary to mitigate the impacts of the works on Northern Powergrid’s undertaking;
“supplementary order” means any order that is made by the Secretary of State that supersedes or amends this Order, including for the avoidance of doubt a non-material change order or a new application for a development consent order in respect of the Immingham Eastern Ro-Ro Terminal development; and
“working day” means a day other than a Saturday or a Sunday or public holiday in England.
44. Regardless of any provision in this Order or anything shown on the land plans the undertaker must not acquire any apparatus or override any easement or other interest of Northern Powergrid otherwise than by agreement with Northern Powergrid, such agreement not to be unreasonably withheld or delayed.
45.—(1) If, in the exercise of the powers conferred by this Order, the undertaker requires that Northern Powergrid’s apparatus is relocated or diverted, that apparatus must not be removed under this Part of this Schedule, and any right of Northern Powergrid to maintain that apparatus in that land and gain access to it must not be extinguished, until alternative apparatus has been constructed and is in operation, and access to it has been provided pursuant to a completed easement for a tenure no less than exists to the apparatus being relocated or diverted or is authorised by written agreement from Northern Powergrid, all to the reasonable satisfaction of Northern Powergrid in accordance with sub-paragraphs (2) to (5).
(2) If, for the purpose of executing any works in, on or under any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, the undertaker must give to Northern Powergrid 42 days’ advance written notice of that requirement, together with a plan and section of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order the undertaker reasonably needs to remove any of its apparatus) the undertaker must, subject to sub-paragraph (3), afford to Northern Powergrid the necessary facilities and rights for the construction of alternative apparatus in other land of the undertaker and subsequently for the maintenance of that apparatus.
(3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2) in the land in which the alternative apparatus or part of such apparatus is to be constructed Northern Powergrid must, on receipt of a written notice to that effect from the undertaker, as soon as reasonably possible and at the cost of the undertaker (subject to prior approval by the undertaker of its estimate of costs of doing so) use reasonable endeavours to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed.
(4) Any alternative apparatus to be constructed in land of the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between Northern Powergrid and the undertaker or in default of agreement settled by arbitration in accordance with article 35 (arbitration).
(5) Northern Powergrid must, after the alternative apparatus to be provided or constructed has been agreed or settled by arbitration in accordance with article 35 (arbitration), and after the grant to Northern Powergrid of any such facilities and rights as are referred to in sub-paragraphs (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this Part of this Schedule.
46.—(1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to a utility undertaker facilities and rights for the construction and maintenance in land of the undertaker of alternative apparatus in substitution for apparatus to be removed, those facilities and rights are to be granted upon such terms and conditions as may be agreed between the undertaker and Northern Powergrid or in default of agreement settled by arbitration in accordance with article 35 (arbitration).
(2) If the facilities and rights to be afforded by the undertaker in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are in the opinion of the arbitrator less favourable on the whole to Northern Powergrid than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject, the arbitrator must make such provision for the payment of compensation by the undertaker to Northern Powergrid as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
47.—(1) Not less than 28 working days before starting the execution of any works in, on or under any land purchased, held, appropriated or used under this Order that are near to (including conducting any activities whether intentionally or unintentionally, through for example ground or machinery collapse, which may affect Northern Powergrid’s apparatus or encroach on safety distances to live equipment), or will or may affect, any apparatus the removal of which has not been required by the undertaker under paragraph 45, the undertaker must submit to Northern Powergrid a plan, section and description of the works to be executed.
(2) Those works must be executed only in accordance with the plan, section and description submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (3) by Northern Powergrid for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and Northern Powergrid is entitled to watch and inspect the execution of those works.
(3) Any requirements made by Northern Powergrid under sub-paragraph (2) must be made within a period of 24 working days beginning with the date on which a plan, section and description under sub-paragraph (1) is submitted to it.
(4) If Northern Powergrid in accordance with sub-paragraph (3) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, sub-paragraphs 1 to 3 and 5 and 6 apply as if the removal of the apparatus had been required by the undertaker under paragraph 45.
(5) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any works, a new plan, section and description instead of the plan, section and description previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan.
(6) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case it must give to Northern Powergrid notice as soon as is reasonably practicable and a plan, section and description of those works as soon as reasonably practicable subsequently and must comply with sub-paragraph (2) in so far as is reasonably practicable in the circumstances.
48.—(1) Subject to the following provisions of this paragraph, the undertaker must repay to Northern Powergrid within 50 days of receipt of a valid VAT invoice all reasonable and proper expenses costs or charges incurred by Northern Powergrid—
(a)in, or in connection with, the inspection, removal, alteration or protection of any apparatus or the construction of any new apparatus which may be required in consequence of the execution of any such works as are referred to in paragraph 45(2) including without limitation—
(i)any costs reasonably incurred or compensation properly paid in connection with the acquisition of rights or the exercise of statutory powers for such apparatus including without limitation in the event that it is agreed Northern Powergrid elects to use compulsory purchase powers to acquire any necessary rights under paragraph 45(3) all costs reasonably incurred as a result of such action;
(ii)in connection with the cost of the carrying out of any diversion work or the provision of any alternative apparatus;
(iii)the cutting off of any apparatus from any other apparatus or the making safe of redundant apparatus;
(iv)the approval of plans;
(v)the carrying out of protective works, plus a capitalised sum to cover the cost of maintaining and renewing permanent protective works;
(vi)the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to in this Part of this Schedule); and
(b)in assessing and preparing a design for its apparatus to address and accommodate the proposals of the undertaker whether or not the undertaker proceeds to implement those proposals or alternative or none at all provided that if it so prefers Northern Powergrid may abandon apparatus that the undertaker does not seek to remove in accordance with paragraph 46(1) having first decommissioned such apparatus;
(c)where any payment falls due pursuant to paragraph 48(1), Northern Powergrid shall—
(i)provide an itemised invoice or reasonable expenses claim to the undertaker; and
(ii)provide ‘reminder letters’ to the undertaker for payment to be made within the 50 days on the following days after the invoice or reasonable expenses claim to the undertaker:
(aa)15 days (‘reminder letter 1’);
(bb)29 days (‘reminder letter 2’);
(cc)43 days (‘reminder letter 3’); and
(iii)commence debt proceedings to recover any unpaid itemised invoice or reasonable expenses claim on the fiftieth day of receipt of the same where payment has not been made.
(2) There is to be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Part of this Schedule that value being calculated after removal and for the avoidance of doubt, if the apparatus removed under the provisions of this Part of this Schedule has nil value, no sum will be deducted from the amount payable under sub-paragraph (1) if in accordance with the provisions of this Part of this Schedule—
(a)apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
(b)apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was, and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 35 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to Northern Powergrid by virtue of sub-paragraph (1) must be reduced by the amount of that excess save where it is not possible on account of project time limits and/or supply issues to obtain the existing type of operations, capacity, dimensions or place at the existing depth in which case full costs shall be borne by the undertaker.
(3) For the purposes of sub-paragraph (2)—
(a)an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus where such an extension is required in consequence of the execution of any such works as are referred to in paragraph 45(2); and
(b)where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.
(4) The undertaker shall not be liable for any claim by Northern Powergrid for charges, costs or expenses under this paragraph 48 unless prior to Northern Powergrid undertaking the relevant works and/or incurring those charges, costs or expenses, the undertaker has—
(a)received an estimate of that charge, cost or expense along with all necessary supporting information required to evidence the amount and reasonableness of, and the reasonable steps taken to minimise, the charge, cost or expense and a timescale in which the undertaker will be required to make payment, and
(b)approved the estimate in writing (approval not to be unreasonably withheld or delayed),
and Northern Powergrid may not commence any work in relation to which an estimate is submitted until it has been agreed in writing by the undertaker.
(5) The undertaker will use reasonable endeavours to agree the amount of any estimates submitted to it under sub-paragraph (4) within 15 working days of receipt, and must acknowledge as part of its approval that any estimate is only an estimate and may be subject to change.
(6) Subject to Northern Powergrid updating the undertaker by way of submission of an updated estimate for approval under sub-paragraph (4) where any charges, costs or expenses are anticipated to exceed an approved estimate, the undertaker’s approval of an estimate shall in no way limit National Powergrid’s recovery under this paragraph 48, and the undertaker shall pay the actual costs incurred by Northern Powergrid and submitted for payment whether such costs are above or below the estimate provided and upon making payment under this paragraph, the undertaker may—
(a)confirm to Northern Powergrid that the charge, cost or expense is accepted; or
(b)confirm to Northern Powergrid that the charge, cost or expense if not accepted and the reasons why it considers this to be the case,
and Northern Powergrid must take in to account any representations made by the undertaker in accordance with sub-paragraph (b) and must following receipt of such representations confirm whether or not the requested refund, or any part thereof, is accepted or rejected, and the reasons why it considered this to be the case; and make payment of the requested refund, or part thereof which is not rejected, as applicable such confirmation or payment not to be unreasonably withheld or delayed.
(7) Either party may refer any difference or dispute arising out of sub-paragraph (6) above to arbitration in accordance with article 35 (arbitration) of the Order.
49.—(1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any of the works referred to in paragraph 45(2), or in consequence of the, maintenance or failure of any of the authorised works by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by it) in the course of carrying out such works, including without limitation works carried out by the undertaker under this Schedule any subsidence resulting from any of these works, any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of Northern Powergrid, or there is any interruption in any service provided by Northern Powergrid, or Northern Powergrid becomes liable to pay any amount to a third party as a consequence of any default, negligence or omission by the undertaker in carrying out the authorised works, the undertaker must—
(a)bear and pay the cost reasonably incurred by Northern Powergrid in making good such damage or restoring the supply; and
(b)indemnify Northern Powergrid for any other expenses, loss, damages, penalty, proceedings, claims or costs incurred by or recovered from Northern Powergrid,
by reason or in consequence of any such damage or interruption or Northern Powergrid becoming liable to any third party.
(2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of Northern Powergrid, its officers, employees, servants, contractors or agents.
(3) Northern Powergrid must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise is to be made without the consent of the undertaker which, if it withholds such consent, has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
(4) Northern Powergrid must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph 49 applies. If requested to do so by the undertaker, Northern Powergrid must provide an explanation of how the claim has been minimised or details to substantiate any cost or compensation claimed pursuant to sub-paragraph (1). The undertaker shall only be liable under this paragraph 49 for claims reasonably incurred by Northern Powergrid.
(5) Where Northern Powergrid is liable to pay any amount to a third party as described in sub-paragraph (1), the total liability of the undertaker to Northern Powergrid under sub-paragraph (1) in respect of each third party claim shall be limited to the extent that Northern Powergrid has properly paid expenses, losses, demands, damages, claims, penalties, costs, interest or any other liability arising from any proceedings to such third party pursuant to—
(a)any statutory compensation scheme, obligation pursuant to its transmission license, or any agreement regulated thereby; or
(b)an award of damages by a court or a settlement or compromise of a claim, demand or proceeding provided that Northern Powergrid will not admit liability or offer to settle with a third party without the undertaker’s consent (not to be unreasonably withheld or delayed).
50. Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and Northern Powergrid in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
51. Where in consequence of the proposed construction of any of the authorised development, the undertaker or Northern Powergrid requires the removal of apparatus under paragraph 45 or otherwise or Northern Powergrid makes requirements for the protection or alteration of apparatus under paragraph 48, the undertaker must use its reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and the need to ensure the safe and efficient operation of Northern Powergrid’s undertaking taking into account the undertaker’s desire for the efficient and economic execution of the authorised development and the undertaker and Northern Powergrid shall use all reasonable endeavours to co-operate with the undertaker for those purposes.
52. If in consequence of an agreement reached in accordance with paragraph 44 or the powers granted under this Order the access to any apparatus or alternative apparatus is materially obstructed, the undertaker shall provide such alternative means of access to such apparatus or alternative apparatus as will enable Northern Powergrid to maintain or use the said apparatus no less effectively than was possible before such obstruction.
53. The plans submitted to Northern Powergrid by the undertaker pursuant to this Part of the Schedule must be sent to Northern Powergrid at property@northernpowergrid.com or such other address as Northern Powergrid may from time to time appoint instead for that purpose and notify to the undertaker in writing.
54. Where practicable, the undertaker and Northern Powergrid will make reasonable efforts to liaise and co-operate in respect of information that is relevant to the safe and efficient construction of the authorised development. Such liaison shall be carried out where any works are:
(a)within 15m of any above ground apparatus; and/or
(b)are to a depth of between 0–4m below ground level.
55. For the protection of Anglian Water the following provisions have effect until the commencement of the operation of the authorised development, unless otherwise agreed in writing between the undertaker and Anglian Water.
56. In this Part of this Schedule—
“1991 Act” means the New Roads and Street Works Act 1991;
“alternative apparatus” means alternative apparatus adequate to enable Anglian Water to fulfil its statutory functions in a manner no less efficient than previously;
“Anglian Water” means Anglian Water Services Limited;
“apparatus” means:
works, mains, pipes or other apparatus belonging to or maintained by Anglian Water for the purposes of water supply and sewerage including for the avoidance of doubt any decommissioned works, mains, pipes or other apparatus;
any drain or works vested in Anglian Water under the Water Industry Act 1991(3);
any sewer which is so vested or is the subject of a notice of intention to adopt given under section 102(4) of that Act or an agreement to adopt made under section 104 of that Act;
any drainage system constructed for the purpose of reducing the volume of surface water entering any public sewer belonging to Anglian Water; and
includes a sludge main, disposal main or sewer outfall and any manholes, ventilating shafts, pumps or other accessories forming part of any such sewer, drain or works, and includes any structure in which apparatus is or is to be lodged or which gives or will give access to apparatus;
and for the purpose of this definition, where words are defined by section 219 of that Act, they shall be taken to have the same meaning;
“functions” includes powers and duties;
“in”, in a context referring to apparatus or alternative apparatus in land, includes a reference to apparatus or alternative apparatus under, over or upon land;
“plan” includes all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe the works to be executed.
57. The undertaker, in the case of the powers conferred by article 27 (protective work to buildings), must exercise those powers so as not to obstruct or render less convenient the access to any apparatus.
58. Regardless of any provision in this Order or anything shown on the land plans, the undertaker must not acquire any apparatus otherwise than by agreement.
59.—(1) If, in the exercise of the powers conferred by this Order, the undertaker acquires any interest in any land in which any apparatus is placed or requires that Anglian Water’s apparatus is relocated or diverted, that apparatus must not be removed under this Part of this Schedule, and any right of Anglian Water to maintain that apparatus in that land must not be extinguished, until—
(a)alternative apparatus has been constructed and is in operation to the reasonable satisfaction of Anglian Water in accordance with sub-paragraphs (2) to (8); and
(b)facilities and rights have been secured for that alternative apparatus in accordance with paragraph 60.
(2) If, for the purpose of executing any works in, on or under any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, the undertaker must give to Anglian Water 28 days’ written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order the undertaker reasonably needs to remove any of Anglian Water’s apparatus) the undertaker must, subject to sub-paragraph (3), afford to Anglian Water the necessary facilities and rights for the construction of alternative apparatus in other land of the undertaker and subsequently for the maintenance of that apparatus.
(3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2) in the land in which the alternative apparatus or part of such apparatus is to be constructed Anglian Water must, on receipt of a written notice to that effect from the undertaker, as soon as reasonably possible use its best endeavours to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed.
(4) Any alternative apparatus to be constructed in land of the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between Anglian Water and the undertaker or in default of agreement settled by arbitration in accordance with article 35 (arbitration).
(5) Anglian Water must, after the alternative apparatus to be provided or constructed has been agreed or settled by arbitration in accordance with article 35 (arbitration), and after the grant to Anglian Water of any such facilities and rights as are referred to in sub-paragraphs (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this Part of this Schedule.
(6) Regardless of anything in sub-paragraph (5), if Anglian Water gives notice in writing to the undertaker that it desires the undertaker to execute any work, or part of any work in connection with the construction or removal of apparatus in any land of the undertaker or to the extent that Anglian Water fails to proceed with that work in accordance with sub-paragraph (5) or the undertaker and Anglian Water otherwise agree, that work, instead of being executed by Anglian Water, must be executed by the undertaker without unnecessary delay under the superintendence, if given, and to the reasonable satisfaction of Anglian Water.
(7) If Anglian Water fails either reasonably to approve, or to provide reasons for its failure to approve along with an indication of what would be required to make acceptable, any proposed details relating to required removal works under sub-paragraph (2) within 28 days of receiving a notice of the required works from the undertaker, then such details are deemed to have been approved. For the avoidance of doubt, any such “deemed consent” does not extend to the actual undertaking of the removal works, which shall remain the sole responsibility of Anglian Water or its contractors.
(8) Whenever alternative apparatus is to be or is being substituted for existing apparatus, the undertaker shall, before taking or requiring any further step in such substitution works, use best endeavours to comply with Anglian Water’s reasonable requests for a reasonable period of time to enable Anglian Water to—
(a)make network contingency arrangements; or
(b)bring such matters as it may consider reasonably necessary to the attention of end users of the utility in question.
60.—(1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to Anglian Water facilities and rights for the construction and maintenance in land of the undertaker of alternative apparatus in substitution for apparatus to be removed, those facilities and rights are to be granted upon such terms and conditions as may be agreed between the undertaker and Anglian Water or in default of agreement settled by arbitration in accordance with article 35 (arbitration).
(2) If the facilities and rights to be afforded by the undertaker in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are in the opinion of the arbitrator less favourable on the whole to Anglian Water than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject, the arbitrator must make such provision for the payment of compensation by the undertaker to Anglian Water as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
(3) Such facilities and rights as are set out in this paragraph are deemed to include any statutory permits granted to the undertaker in respect of the apparatus in question, whether under the Environmental Permitting (England and Wales) Regulations 2016(4) or other legislation.
61.—(1) Not less than 28 days before starting the execution of any works in, on or under any land purchased, held, appropriated or used under this Order that are near to, or will or may affect, any apparatus (or any means of access to it) the removal of which has not been required by the undertaker under paragraph 59(2), the undertaker must submit to Anglian Water a plan of the works to be executed.
(2) Those works must be executed only in accordance with the plan submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (3) by Anglian Water for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and Anglian Water is entitled to watch and inspect the execution of those works.
(3) Any requirements made by Anglian Water under sub-paragraph (2) must be made within a period of 21 days beginning with the date on which a plan under sub-paragraph (1) is submitted to it.
(4) If Anglian Water in accordance with sub-paragraph (3) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, sub-paragraphs 1 to 3 and 6 to 8 apply as if the removal of the apparatus had been required by the undertaker under paragraph 59(2).
(5) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any works, a new plan instead of the plan previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan.
(6) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case must give to Anglian Water notice as soon as is reasonably practicable and a plan of those works as soon as reasonably practicable subsequently and must comply with sub-paragraph (3) in so far as is reasonably practicable in the circumstances, using its best endeavours to keep the impact of those emergency works on Anglian Water’s apparatus, on the operation of its water and sewerage network and on end-users of the services Anglian Water provides to a minimum.
(7) For the purposes of sub-paragraph (1) and without prejudice to the generality of the principles set out in that sub-paragraph, works are deemed to be in land near Anglian Water’s apparatus (where it is a pipe) if those works fall within the following distances measured from the medial line of such apparatus—
(a)4 metres where the diameter of the pipe is less than 250 millimetres;
(b)5 metres where the diameter of the pipe is between 250 and 400 millimetres; and
(c)6 metres where the diameter of the pipe exceeds 400 millimetres.
62.—(1) Subject to the following provisions of this paragraph, the undertaker must repay to Anglian Water all expenses reasonably incurred by Anglian Water in, or in connection with, the inspection, removal, alteration or protection of any apparatus or the construction of any new apparatus which may be required in consequence of the execution of any such works as are referred to in this Part of this Schedule.
(2) There must be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Part of this Schedule that value being calculated after removal.
(3) If in accordance with the provisions of this Part of this Schedule—
(a)apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
(b)apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated, and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 35 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to Anglian Water by virtue of sub-paragraph (1) must be reduced by the amount of that excess.
(4) For the purposes of sub-paragraph (3)—
(a)an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
(b)where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.
63.—(1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any such works referred to in paragraphs 59 or 61(2), or by reason of any subsidence resulting from such development or works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of Anglian Water, or there is any interruption in any service provided, or in the supply of any goods, by Anglian Water, the undertaker must—
(a)bear and pay the cost reasonably incurred by Anglian Water in making good such damage or restoring the supply; and
(b)make reasonable compensation to Anglian Water for any other expenses, loss, damages, penalty or costs incurred by the undertaker,
by reason or in consequence of any such damage or interruption.
(2) The fact that any act or thing may have been done by Anglian Water on behalf of the undertaker or in accordance with a plan approved by Anglian Water or in accordance with any requirement of Anglian Water or under its supervision does not, subject to sub-paragraph (3), excuse the undertaker from liability under the provisions of sub-paragraph (1) unless Anglian Water fails to carry out and execute the works properly with due care and attention and in a skilful and professional like manner or in a manner that does not accord with the approved plan.
(3) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the unlawful or unreasonable act, neglect or default of Anglian Water, its officers, servants, contractors or agents.
(4) Anglian Water must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise is to be made, without the consent of the undertaker (such consent not to be unreasonably withheld or delayed) who, if withholding such consent, has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
64. Where in consequence of the proposed construction of any of the authorised development, the undertaker or Anglian Water requires the removal of apparatus under paragraph 59(2) or Anglian Water makes requirements for the protection or alteration of apparatus under paragraph 59(4), the undertaker must use all reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of Anglian Water’s undertaking, using existing processes where requested by Anglian Water, provided it is appropriate to do so, and Anglian Water must use all reasonable endeavours to co-operate with the undertaker for that purpose.
65. Where the undertaker identifies any apparatus which may belong to or be maintainable by Anglian Water but which does not appear on any statutory map kept for the purpose by Anglian Water, it shall inform Anglian Water of the existence and location of the apparatus as soon as reasonably practicable.
66. Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and Anglian Water in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
67. The undertaker and Anglian Water may by written agreement substitute any period of time for those periods set out in this Part of this Schedule.
68. The following provisions of this Part of this Schedule have effect, unless otherwise agreed in writing between the undertaker and Network Rail and, in the case of paragraph 81, any other person on whom rights or obligations are conferred by that paragraph.
69. In this Part of this Schedule—
“asset protection agreement” means an agreement, should such be required, to regulate the construction and maintenance of the specified work in a form to be agreed from time to time between the undertaker and Network Rail;
“construction” includes execution, placing, alteration and reconstruction and “construct” and “constructed” have corresponding meanings;
“the engineer” means an engineer appointed by Network Rail for the purposes of this Order;
“network licence” means the network licence, as the same is amended from time to time, granted to Network Rail by the Secretary of State in exercise of their powers under section 8 of the Railways Act 1993;
“Network Rail” means Network Rail Infrastructure Limited company number 02904587, registered at Waterloo General Office, London SE1 8SW, and any associated company of Network Rail Infrastructure Limited which holds property for railway purposes, and for the purpose of this definition “associated company” means any company which is (within the meaning of section 1159 of the Companies Act 2006) the holding company of Network Rail Infrastructure Limited, a subsidiary of Network Rail Infrastructure Limited or another subsidiary of the holding company of Network Rail Infrastructure Limited, and any successor to Network Rail Infrastructure Limited’s railway undertaking;
“plans” includes sections, designs, design data, software, drawings, specifications, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals, programmes and details of the extent, timing and duration of any proposed occupation of railway property;
“protective works” means any works specified by the engineer under paragraph 72(4);
“railway operational procedures” means procedures specified under any access agreement (as defined in the Railways Act 1993) or station lease;
“railway property” means any railway belonging to Network Rail and—
any station, land, works, apparatus and equipment belonging to Network Rail or a tenant or licensee of Network Rail or connected with any such railway; and
any easement or other property interest held or used by Network Rail or a tenant or licensee of Network Rail for the purposes of such railway or works, apparatus or equipment; and
“regulatory consents” means any consent or approval required under:
the Railways Act 1993;
the network licence; and/or
any other relevant statutory or regulatory provisions;
by either the Office of Rail and Road or the Secretary of State for Transport or any other competent body including change procedures and any other consents, approvals of any access or beneficiary that may be required in relation to the authorised development;
“specified work” means so much of any of the authorised development as is or is to be situated upon, across, under, over or within 15 metres of, or may in any way adversely affect, railway property and, for the avoidance of doubt, includes the maintenance of such works under the powers conferred by article 6 (maintenance of authorised development) in respect of such works.
70.—(1) Where under this Part of this Schedule Network Rail is required to give its consent or approval in respect of any matter, that consent or approval is subject to the condition that Network Rail complies with any relevant railway operational procedures and any obligations under its network licence or under statute.
(2) In so far as any specified work or the acquisition or use of railway property or rights over railway property is or may be subject to railway operational procedures, Network Rail must—
(a)co-operate with the undertaker with a view to avoiding undue delay and securing conformity as between any plans approved by the engineer and requirements emanating from those procedures; and
(b)use its reasonable endeavours to avoid any conflict arising between the application of those procedures and the proper implementation of the authorised development pursuant to this Order.
71.—(1) The undertaker must not exercise the powers conferred by—
(a)article 5 (development consent granted by the Order);
(b)article 6 (maintenance of the authorised development);
(c)article 13 (power to override easements and other rights);
(d)article 16 (statutory undertakers and operator of the electronic communications code network);
(e)article 26 (authority to survey and investigate the land);
(f)the powers conferred by section 203 (power to override easements and rights) of the Housing and Planning Act 2016;
(g)the powers conferred by section 172 (right to enter and survey land) of the Housing and Planning Act 2016;
(h)any powers in respect of the temporary possession of land under the Neighbourhood Planning Act 2017,
in respect of any railway property unless the exercise of such powers is with the consent of Network Rail.
(2) The undertaker must not in the exercise of the powers conferred by this Order prevent pedestrian or vehicular access to any railway property, unless preventing such access is with the consent of Network Rail.
(3) The undertaker must not exercise the powers conferred by sections 271 (extinguishment of rights of statutory undertakers: preliminary notices) or 272 (extinguishment of rights of electronic communications code network operators: preliminary notices) of the 1990 Act or article 16 (statutory undertakers and operator of the electronic communications code network) or article 13 (power to override easements and other rights or private rights of way) in relation to any right of access of Network Rail to railway property, but such right of access may be extinguished or diverted with the consent of Network Rail.
(4) No powers of compulsory acquisition are being sought in relation to railway property.
(5) The undertaker must not under the powers of this Order acquire or use or acquire new rights over or seek to impose any restrictive covenants over, any railway property, or extinguish any existing rights of Network Rail in respect of any third party property except with the consent of Network Rail.
(6) The undertaker must not under the powers of this Order do anything which would result in railway property being incapable of being used or maintained or which would affect the safe running of trains on the railway.
(7) Where Network Rail is asked to give its consent under this paragraph, such consent must not be unreasonably withheld but may be given subject to reasonable conditions but it shall never be unreasonable to withhold consent for reasons of operational or railway safety (such matters to be in Network Rail’s absolute discretion). The undertaker must enter into an asset protection agreement prior to the carrying out of any specified work.
72.—(1) The undertaker must, before commencing construction of any specified work, supply to Network Rail proper and sufficient plans of that work for the reasonable approval of the engineer and the specified work must not be commenced except in accordance with such plans as have been approved in writing by the engineer or settled by arbitration under article 35 (arbitration).
(2) The approval of the engineer under sub-paragraph (1) must not be unreasonably withheld, and if by the end of the period of 28 days beginning with the date on which such plans have been supplied to Network Rail the engineer has not communicated disapproval of those plans and the grounds of disapproval the undertaker may serve upon the engineer written notice requiring the engineer to communicate approval or disapproval within a further period of 28 days beginning with the date upon which the engineer receives written notice from the undertaker. If by the expiry of the further 28 days the engineer has not communicated approval or disapproval, the engineer is deemed to have approved the plans as submitted.
(3) If by the end of the period of 28 days beginning with the date on which written notice was served upon the engineer under sub-paragraph (2), Network Rail gives notice to the undertaker that Network Rail desires itself to construct any part of a specified work which in the opinion of the engineer will or may affect the stability of railway property or the safe operation of traffic on the railways of Network Rail then, if the undertaker desires such part of the specified work to be constructed, Network Rail must construct it without unnecessary delay on behalf of and to the reasonable satisfaction of the undertaker in accordance with the plans approved or deemed to be approved or settled under this paragraph, and under the supervision (where appropriate and if given) of the undertaker.
(4) When signifying approval of the plans the engineer may specify any protective works (whether temporary or permanent) which in the engineer’s reasonable opinion should be carried out before the commencement of the construction of a specified work to ensure the safety or stability of railway property or the continuation of safe and efficient operation of the railways of Network Rail or the services of operators using the same (including any relocation decommissioning and removal of works, apparatus and equipment necessitated by a specified work and the comfort and safety of passengers who may be affected by the specified works), and such protective works as may be reasonably necessary for those purposes must be constructed by Network Rail or by the undertaker, if Network Rail so desires, and such protective works must be carried out at the expense of the undertaker in either case without unnecessary delay and the undertaker must not commence the construction of the specified works in question until the engineer has notified the undertaker that the protective works have been completed to the engineer’s reasonable satisfaction.
73.—(1) Any specified work and any protective works to be constructed by virtue of paragraph 72 must, when commenced, be constructed—
(a)without unnecessary delay in accordance with the plans approved or deemed to have been approved or settled under paragraph 72;
(b)under the supervision (where appropriate) and to the reasonable satisfaction of the engineer;
(c)in such manner as to cause as little damage as is possible to railway property; and
(d)so far as is reasonably practicable, so as not to interfere with or obstruct the free, uninterrupted and safe use of any railway of Network Rail or the traffic on it and the use by passengers of railway property.
(2) If any damage to railway property or any such interference or obstruction is caused by the carrying out of, or in consequence of the construction of a specified work or a protective work, the undertaker must, regardless of any such approval, make good such damage and must pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation for any loss which it may sustain by reason of any such damage, interference or obstruction.
(3) Nothing in this Part of this Schedule imposes any liability on the undertaker with respect to any damage, costs, expenses or loss attributable to the negligence of Network Rail or its employees, contractors or agents or any liability on Network Rail with respect to any damage, costs, expenses or loss attributable to the negligence of the undertaker or its employees, contractors or agents.
74. The undertaker must—
(a)at all times afford reasonable facilities to the engineer for access to a specified work or a protective work during its construction; and
(b)supply the engineer with all such information as the engineer may reasonably require with regard to a specified work or a protective work or the method of constructing it.
75. Network Rail must at all times afford reasonable facilities to the undertaker and its employees, contractors or agents for access to any works carried out by Network Rail under this Part of this Schedule during their construction and must supply the undertaker with such information as it may reasonably require with regard to such works or the method of constructing them.
76.—(1) If any permanent or temporary alterations or additions to railway property are reasonably necessary in consequence of the construction of a specified work or a protective work, or during a period of 24 months after the completion of that work in order to ensure the safety of railway property or the continued safe operation of the railway of Network Rail, such alterations or additions may be carried out by Network Rail and if Network Rail gives to the undertaker 56 days’ notice (or in the event of an emergency or safety critical issue such notice as is reasonable in the circumstances of its intention to carry out such alterations or additions (which must be specified in the notice), the undertaker must pay to Network Rail the reasonable cost of those alterations or additions including, in respect of any such alterations or additions as are to be permanent, a capitalised sum representing the increase of the costs which may be expected to be reasonably incurred by Network Rail in maintaining, working and, when necessary, renewing any such alterations or additions.
(2) If during the construction of a specified work or a protective work by the undertaker, Network Rail gives notice to the undertaker that Network Rail desires itself to construct that part of the specified work or the protective work because which in the opinion of the engineer it is endangering the stability of railway property or the safe operation of traffic on the railways of Network Rail then, if the undertaker decides that part of the specified work or the protective work is to be constructed, Network Rail must assume construction of that part of the specified work or protective work and the undertaker must, regardless of any approval of the specified work or protective work in question under paragraph 72(3), pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation for any loss which it may suffer by reason of the execution by Network Rail of that specified work or protective work.
(3) The engineer must, in respect of the capitalised sums referred to in this paragraph and paragraph 77(a), provide such details of the formula or method of calculation by which those sums have been calculated as the undertaker may reasonably require.
(4) If the cost of maintaining, working or renewing railway property is reduced in consequence of any such alterations or additions, a capitalised sum representing such saving must be set off against any sum payable by the undertaker to Network Rail under this paragraph.
77. The undertaker must repay to Network Rail all reasonable fees, costs, charges and expenses reasonably incurred by Network Rail—
(a)in constructing any part of a specified work on behalf of the undertaker as provided by paragraph 72(3) or in constructing any protective works under the provisions of paragraph 72(4) including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works;
(b)in respect of the approval by the engineer of plans submitted by the undertaker and the supervision by the engineer of the construction of a specified work or a protective work;
(c)in respect of the employment or procurement of the services of any inspectors, signallers, watchkeepers and other persons whom it is reasonably necessary to appoint for inspecting, signalling, watching and lighting railway property and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or accident arising from the construction or failure of a specified work or a protective work;
(d)in respect of any special traffic working resulting from any speed restrictions which may in the reasonable opinion of the engineer be required to be imposed by reason or in consequence of the construction or failure of a specified work or a protective work or from the substitution or diversion of services which may be reasonably necessary for the same reason; and
(e)in respect of any additional temporary lighting of railway property in the vicinity of the specified works, being lighting made reasonably necessary by reason or in consequence of the construction or failure of a specified work or a protective work.
78. If at any time after the completion of a specified work or a protective work, not being a work vested in Network Rail, Network Rail gives notice to the undertaker informing it that the state of maintenance of any part of the specified work or the protective work appears to be such as adversely affects the operation of railway property, the undertaker must, on receipt of such notice, take such steps as may be reasonably necessary to put that specified work or protective work in such state of maintenance as not adversely to affect railway property.
79. The undertaker must not provide any illumination or illuminated sign or signal on or in connection with a specified work or a protective work in the vicinity of any railway belonging to Network Rail unless it has first consulted Network Rail and it must comply with Network Rail’s reasonable requirements for preventing confusion between such illumination or illuminated sign or signal and any railway signal or other light used for controlling, directing or securing the safety of traffic on the railway.
80. Any additional expenses which Network Rail may reasonably incur in altering, reconstructing or maintaining railway property under any powers existing at the making of this Order by reason of the existence of a specified work or protective work must, provided that 56 days’ previous notice of the commencement of such alteration, reconstruction or maintenance has been given to the undertaker, be repaid by the undertaker to Network Rail.
81.—(1) The undertaker must pay to Network Rail all reasonable costs, charges, damages and expenses not otherwise provided for in this Part of this Schedule which may be occasioned to or reasonably incurred by Network Rail—
(a)by reason of the construction or maintenance or operation of a specified work or a protective work or the failure of it;
(b)by reason of any act or omission of the undertaker or of any person in its employ or of its contractors or others whilst engaged upon a specified work or a protective work,
(c)by reason of any act or omission of the undertaker or any person in its employ or of its contractors or others whilst accessing to or egressing from the authorised development—
(i)in respect of any damage caused to, or additional maintenance required to, railway property or any such interference or obstruction or delay to the operation of the railway as a result of access to or egress from the authorised development by the undertaker or any person in its employ or of its contractors or others;
(ii)in respect of costs incurred by Network Rail in complying with any railway operational procedures or obtaining any regulatory consents which procedures are required to be followed or consents obtained to facilitate the carrying out or operation of the authorised development,
and the undertaker indemnify and keep indemnified Network Rail in respect of such costs, from and against all claims and demands arising out of or in connection with a specified work or protective work or any such failure, act or omission and the fact that any act or thing may have been done by Network Rail on behalf of the undertaker or in accordance with plans approved by the engineer or in accordance with any requirement of the engineer or under the engineer’s supervision will not (if it was done without negligence on the part of Network Rail or its employees, contractors or agents) excuse the undertaker from any liability under the provisions of this sub-paragraph.
(2) Network Rail must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise of such a claim or demand is to be made without the prior written consent of the undertaker.
(3) The sums payable by the undertaker under sub-paragraph (1) shall if relevant include a sum equivalent to the relevant costs.
(4) Subject to the terms of any agreement between Network Rail and a train operator regarding the timing or method of payment of the relevant costs in respect of that train operator, Network Rail must promptly pay to each train operator the amount of any sums which Network Rail receives under sub-paragraph (3) which relates to the relevant costs of that train operator.
(5) The obligation under sub-paragraph (3) to pay Network Rail the relevant costs is, in the event of default, enforceable directly by any train operator concerned to the extent that such sums would be payable to that operator pursuant to sub-paragraph (4).
(6) In this paragraph—
“the relevant costs” means the costs, direct losses and expenses (including loss of revenue) reasonably incurred by each train operator as a consequence of any specified work including but not limited to any restriction of the use of Network Rail’s railway network as a result of the construction, maintenance or failure of a specified work or a protective work or any such act or omission as mentioned in sub-paragraph (1); and
“train operator” means any person who is authorised to act as the operator of a train by a licence under section 8 of the Railways Act 1993.
82. Network Rail must, on receipt of a request from the undertaker, from time to time provide the undertaker free of charge with written estimates of the costs, charges, expenses and other liabilities for which the undertaker is or will become liable pursuant to this Part of this Schedule (including the amount of the relevant costs mentioned in paragraph 81(3) and with such information as may reasonably enable the undertaker to assess the reasonableness of any such estimate or claim made or to be made pursuant to this Part of this Schedule (including any claim relating to those relevant costs).
83. In the assessment of any sums payable to Network Rail under this Part of this Schedule there must not be taken into account any increase in the sums claimed that is attributable to any action taken by or any agreement entered into by Network Rail if that action or agreement was not reasonably necessary and was taken or entered into with a view to obtaining the payment of those sums by the undertaker under this Part of this Schedule or increasing the sums so payable.
84. Nothing in this Order, or in any enactment incorporated with or applied by this Order, prejudices or affects the operation of Part 1 of the Railways Act 1993.
85. The undertaker must give written notice to Network Rail where any application is proposed to be made by the undertaker for the Secretary of State’s consent under article 9 (transfer of benefit of Order, etc.) and any such notice must be given no later than 28 days before any such application is made and must describe or give (as appropriate)—
(a)the nature of the application to be made;
(b)the extent of the geographical area to which the application relates; and
(c)the name and address of the person acting for the Secretary of State to whom the application is to be made.
86. The undertaker must no later than 28 days from the date that the plans and documents referred to in article 33 (certification of plans and documents etc.) are certified by the Secretary of State provide a set of those plans and documents to Network Rail.
87. Any dispute arising between the undertaker and Network Rail under this Part of this Schedule is to be determined by arbitration in accordance with article 35 (arbitration).
88. The provisions of this Part of this Schedule apply until the commencement of the operation of the authorised development for the protection of North East Lincolnshire Council (as lead local flood authority within the meaning of the Flood and Water Management Act 2010) unless otherwise agreed between the undertaker and North East Lincolnshire Council.
89. In this Part of this Schedule—
“authorised officer” means an officer authorised to by North East Lincolnshire Council;
“construction” includes execution, placing, altering, replacing, relaying and removal and “construct” and “constructed” are construed accordingly;
“drainage work” means any ordinary watercourse and includes any land which is expected to provide flood storage capacity for an ordinary watercourse and any bank, wall, embankment or other structure, or any appliance, constructed or used for land drainage or flood defence in connection with an ordinary watercourse;
“ordinary watercourse” has the meaning as given in section 72 (interpretation) of the Land Drainage Act 1991;
“plans” includes sections, drawings, specifications and method statements; and
“specified work” means any works carried out in relation to or which may affect any ordinary watercourse, drain or culvert in a manner that would be likely to affect the flow of the watercourse.
90.—(1) Before beginning to construct any specified work, the undertaker must submit to North East Lincolnshire Council plans of the specified work and such further particulars available to it as North East Lincolnshire Council may within 28 days of the receipt of the plans reasonably require.
(2) Any such specified work must not be constructed except in accordance with such plans as may be approved in writing by North East Lincolnshire Council, or determined under sub-paragraph (3).
(3) Any approval of North East Lincolnshire Council required under sub-paragraph (2)—
(a)must not be unreasonably withheld or delayed;
(b)is deemed to have been given if it is neither given nor refused within 28 days of the receipt of the plans for approval or where further particulars are submitted under sub-paragraph (1) within 28 days of the submission of those particulars, or where further particulars are received under sub-paragraph (1), within 28 days of the receipt of those particulars, and, in the case of a refusal, accompanied by a statement of the grounds of refusal; and
(c)may be given subject to such reasonable requirements as it may make for the protection of any drainage work or for the prevention of flooding and
(d)North East Lincolnshire Council must use its reasonable endeavours to respond to the submission of any plans before the expiration of the period mentioned in sub-paragraph (3)(b).
91. Without limitation on the scope of paragraph 90 the requirements which North East Lincolnshire Council may make include conditions requiring the undertaker at its own expense to construct such protective works, whether temporary or permanent, before or during the construction of the specified works (including any new works as well as alterations to existing works) as are reasonably necessary—
(a)to safeguard any drainage work against damage; or
(b)to secure that the efficiency of any ordinary watercourse for flood defence or land drainage purposes is not impaired and that the risk of flooding is not otherwise increased,
by reason of the specified work.
92.—(1) Subject to sub-paragraph (2), any specified work, and all protective works required by North East Lincolnshire Council under paragraph 90 be constructed—
(a)without unnecessary delay in accordance with the plans approved or settled under this Part of this Schedule; and
(b)to the reasonable satisfaction of North East Lincolnshire Council,
and an authorised officer of North East Lincolnshire Council is entitled to watch and inspect the construction of such works.
(2) The undertaker must give to North East Lincolnshire Council not less than 14 days’ notice in writing of its intention to commence construction of any specified work and notice in writing of its completion not later than 7 days after the date on which it is completed.
(3) If any part of a specified work or any protective work required by North East Lincolnshire Council over or under any ordinary watercourse is constructed otherwise than in accordance with the requirements of this Part of Schedule, North East Lincolnshire Council may by notice in writing require the undertaker at the undertaker’s own expense to comply with the requirements of this Part of this Schedule or (if the undertaker so elects and North East Lincolnshire Council in writing consents, such consent not to be unreasonably withheld or delayed) to remove, alter or pull down the work and, where removal is required, to restore the site to its former condition to such extent and within such limits as North East Lincolnshire Council reasonably requires.
(4) Subject to sub-paragraph 5 and paragraph 90, if within a reasonable period, being not less than 28 days from the date when a notice under sub-paragraph (3) is served upon the undertaker, it has failed to begin taking steps to comply with the requirements of the notice and subsequently to make reasonably expeditious progress towards their implementation, North East Lincolnshire Council may execute the works specified in the notice and any reasonable expenditure incurred by it in so doing is recoverable from the undertaker.
(5) In the event of any dispute as to whether sub-paragraph (3) is properly applicable to any work in respect of which notice has been served under that sub-paragraph, or as to the reasonableness of any requirement of such a notice, North East Lincolnshire Council must not except in an emergency exercise the powers conferred by sub-paragraph (4) until the dispute has been finally determined.
93.—(1) Subject to sub-paragraph 2 the undertaker must from the commencement of the construction of the specified works maintain in good repair and condition and free from obstruction any drainage work which is situated within the limits of deviation and on land held by the undertaker for the purposes of or in connection with the specified works, whether or not the drainage work is constructed under the powers conferred by this Order or is already in existence.
(2) If any such drainage work which the undertaker is liable to maintain is not maintained to the reasonable satisfaction of North East Lincolnshire Council it may by notice in writing require the undertaker to repair and restore the work, or any part of such work, or (if the undertaker so elects and North East Lincolnshire Council in writing consents, such consent not to be unreasonably withheld or delayed), to remove the work and restore the site to its former condition, to such extent and within such limits as North East Lincolnshire Council reasonably requires.
(3) Subject to sub-paragraph 4 and paragraph 90, if, within a reasonable period being not less than 28 days beginning with the date on which a notice in respect of any drainage work is served under sub-paragraph (2) on the undertaker, the undertaker has failed to begin taking steps to comply with the reasonable requirements of the notice and has not subsequently made reasonably expeditious progress towards their implementation, North East Lincolnshire Council may do what is necessary for such compliance and may recover any expenditure reasonably incurred by it in so doing from the undertaker.
(4) In the event of any dispute as to the reasonableness of any requirement of a notice served under sub-paragraph 2, North East Lincolnshire Council must not, except in a case of an emergency, exercise the powers conferred by sub-paragraph 3 until the dispute has been finally determined.
(5) This paragraph does not apply to—
(a)drainage works which are vested in North East Lincolnshire Council, or which North East Lincolnshire Council or another person is liable to maintain and is not precluded by the powers of the Order from doing so; and
(b)any obstruction of a drainage work for the purpose of a work or operation authorised by this Order and carried out in accordance with the provisions of this Part of this Schedule.
94. Subject to paragraph 93, if by reason of the construction of any specified work or of the failure of any such work the efficiency of any ordinary watercourse for flood defence or land drainage purposes is impaired, or that watercourse is otherwise damaged, so as to require remedial action, such impairment or damage must be made good by the undertaker to the reasonable satisfaction of North East Lincolnshire Council and if the undertaker fails to do so, North East Lincolnshire Council may make good the same and recover from the undertaker the expense reasonably incurred by it in so doing.
95.—(1) The undertaker must indemnify North East Lincolnshire Council in respect of all costs, charges and expenses which North East Lincolnshire Council may reasonably incur or have to pay or which it may sustain—
(a)in the examination or approval of plans under this Part of this Schedule; and
(b)in the inspection of the construction of the specified work in respect of an ordinary watercourse or any protective works required by North East Lincolnshire Council under this Part of this Schedule.
(2) The maximum amount payable to North East Lincolnshire Council under paragraph 92 or 94 is to be the same as would have been payable to North East Lincolnshire Council in accordance with the scale of charges for pre-application advice and land drainage consent applications published by North East Lincolnshire Council from time to time.
96.—(1) Without affecting the other provisions of this Part of this Schedule, the undertaker must indemnify North East Lincolnshire Council from all claims, demands, proceedings, costs, charges, penalties, damages, expenses and losses, which may be made or taken against, recovered from, or incurred by, North East Lincolnshire Council by reason of—
(a)any damage to any drainage work so as to impair its efficiency for flood defence or land drainage purposes;
(b)any raising or lowering of the water table in land adjoining or affected by a specified work or adjoining any sewers, drains and watercourses;
(c)any flooding, increased flooding or impaired drainage of any such lands as are mentioned in paragraph 93;
(d)any claim in respect of pollution under the Control of Pollution Act 1974(5);
(e)damage to property including property owned by third parties; or
(f)injury to or death of any person,
which is caused by the construction of any of the specified works or any act or omission of the undertaker, its contractors, agents or employees whilst engaged upon the work.
(2) North East Lincolnshire Council must give to the undertaker reasonable notice of any such claim or demand and no settlement or compromise may be made without the agreement of the undertaker which agreement must not be unreasonably withheld or delayed.
97. The fact that any work or thing has been executed or done by the undertaker in accordance with plans approved by North East Lincolnshire Council, or to its satisfaction, or in accordance with any directions or award of an arbitrator, does not (in the absence of negligence on the part of North East Lincolnshire Council, its officers, contractors or agents) relieve the undertaker from any liability under the provisions of this Part of this Schedule.
98. Any dispute arising between the undertaker and North East Lincolnshire Council under this Part of this Schedule is to be determined by arbitration in accordance with article 35 (arbitration).
99. The provisions of this Part of this Schedule shall apply for the protection of Cadent, unless otherwise agreed in writing between the undertaker and Cadent.
100. In this Part of this Schedule—
“alternative apparatus” means appropriate alternative apparatus to the satisfaction of Cadent to enable Cadent to fulfil its statutory functions in a manner no less efficient than previously;
“apparatus” means any gas mains, pipes, pressure governors, ventilators, cathodic protections, cables or other apparatus belonging to or maintained by Cadent for the purposes of gas supply together with any replacement apparatus and such other apparatus constructed pursuant to the Order that becomes operational apparatus of Cadent for the purposes of transmission, distribution and/or supply and includes any structure in which apparatus is or will be lodged or which gives or will give access to apparatus;
“authorised works” means Work No. 6 as defined in Schedule 1 to this Order and includes any ancillary works (as defined in Schedule 1 to this Order) associated with Work No. 6;
“Cadent” means Cadent Gas Limited (Company Number 10080864) whose registered office is situated at Cadent, Pilot Way, Ansty, Coventry, England, CV7 9JU) and/or its successors in title and/or any successor as a gas transporter within the meaning of Part 1 of the Gas Act 1986;
“commence” has the same meaning as in article 2 of this Order and commencement shall be construed to have the same meaning save that for the purposes of this Part of the Schedule the terms commence and commencement include operations for the purposes of archaeological or ecological investigations and investigations of the existing condition of the ground or of structures;
“decommissioned apparatus” means any disused no longer maintained by Cadent as a consequence of the authorised development and for which rights have been surrendered and references to “decommission” and “decommissioned” shall be construed accordingly;
“deed of consent” means a deed of consent, crossing agreement, deed of variation or new deed of grant agreed between the parties acting reasonably in order to vary and/or replace existing easements, agreements, enactments and other such interests so as to secure land rights and interests as are necessary to carry out, maintain, operate and use the apparatus in a manner consistent with the terms of this Part of this Schedule and references to “deeds of consent” shall be construed accordingly;
“functions” includes powers and duties;
“ground mitigation scheme” means a scheme approved by Cadent (such approval not to be unreasonably withheld or delayed) setting out the necessary measures (if any) for a ground subsidence event;
“ground monitoring scheme” means a scheme for monitoring ground subsidence which sets out the apparatus which is to be subject to such monitoring, the extent of land to be monitored, the manner in which ground levels are to be monitored, the timescales of any monitoring activities and the extent of ground subsidence which, if exceeded, shall require the undertaker to submit for Cadent’s approval a ground mitigation scheme;
“ground subsidence event” means any ground subsidence identified by the monitoring activities set out in the ground monitoring scheme that has exceeded the level described in the ground monitoring scheme as requiring a ground mitigation scheme;
“in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over, across, along or upon such land;
“plan” or “plans” include all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe and assess the works to be executed;
“rights” shall include rights and restrictive covenants, and in relation to decommissioned apparatus the surrender of rights, release of liabilities and transfer of decommissioned apparatus;
“specified works” means any of the authorised works or activities undertaken in association with the authorised works which—
will or may be situated over, or within 15 metres measured in any direction of any apparatus the removal of which has not been required by the undertaker under sub-paragraph 103(2) or otherwise;
may in any way adversely affect any apparatus the removal of which has not been required by the undertaker under sub-paragraph 103(2) or otherwise; and/or
include any of the activities that are referred to in CD/SP/SSW/22 (Cadent’s policies for safe working in the vicinity of Cadent’s Assets); and
“undertaker” means the undertaker as defined in article 2 of this Order.
101.—(1) The undertaker, in the case of the powers conferred by article 27 (protective work to buildings), must exercise those powers so as not to obstruct or render less convenient the access to any apparatus without the written consent of Cadent and, if by reason of the exercise of those powers any damage to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal or abandonment) or property of Cadent or any interruption in the supply of gas by Cadent, as the case may be, is caused, the undertaker must bear and pay on demand the cost reasonably incurred by Cadent in making good such damage or restoring the supply; and, subject to sub-paragraph (2), shall—
(a)pay compensation to Cadent for any loss sustained by it; and
(b)indemnify Cadent against all claims, demands, proceedings, costs, damages and expenses which may be made or taken against or recovered from or incurred by Cadent, by reason of any such damage or interruption.
(2) Nothing in this paragraph imposes any liability on the undertaker with respect to any damage or interruption to the extent that such damage or interruption is attributable to the act, neglect or default of Cadent or its contractors or workmen; and Cadent will give to the undertaker reasonable notice of any claim or demand as aforesaid and no settlement or compromise thereof shall be made by Cadent, save in respect of any payment required under a statutory compensation scheme, without first consulting the undertaker and giving the undertaker an opportunity to make representations as to the claim or demand.
102.—(1) Regardless of any provision in this Order or anything shown on the land plans or contained in the book of reference to the Order, the undertaker may not appropriate or acquire any land interest or appropriate, acquire, extinguish, interfere with or override any easement, other interest or right and/or apparatus of Cadent otherwise than by agreement.
(2) As a condition of agreement between the parties in sub-paragraph 104(1), prior to the carrying out of any part of the authorised works (or in such other timeframe as may be agreed between Cadent and the undertaker) that are subject to the requirements of this Part of this Schedule that will cause any conflict with or breach the terms of any easement and/or other legal or land interest of Cadent and/or affects the provisions of any enactment or agreement regulating the relations between Cadent and the undertaker in respect of any apparatus laid or erected in land belonging to or secured by the undertaker, the undertaker must as Cadent reasonably requires enter into such deeds of consent and variations upon such terms and conditions as may be agreed between Cadent and the undertaker acting reasonably and which must be no less favourable on the whole to Cadent unless otherwise agreed by Cadent, and it will be the responsibility of the undertaker to procure and/or secure the consent and entering into of such deeds and variations by all other third parties with an interest in the land at that time who are affected by such authorised works.
(3) The undertaker and Cadent agree that where there is any inconsistency or duplication between the provisions set out in this Part of this Schedule relating to the relocation and/or removal of apparatus/including but not limited to the payment of costs and expenses relating to such relocation and/or removal of apparatus and the provisions of any existing easement, rights, agreements and licences granted, used, enjoyed or exercised by Cadent and/or other enactments relied upon by Cadent as of right or other use in relation to the apparatus, then the provisions in this Schedule shall prevail subject to the proviso in paragraph 99 above.
(4) Any agreement or consent granted by Cadent under paragraph 105 or any other paragraph of this Part of this Schedule, shall not be taken to constitute agreement under sub-paragraph 104(1).
(5) As a condition of an agreement between the parties in sub-paragraph 104(1) that involves de-commissioned apparatus being left in situ the undertaker must accept a surrender of any existing easement and/or other interest of Cadent in such decommissioned apparatus subject to the satisfaction of the undertaker and consequently acquire title to such decommissioned apparatus and release Cadent from all liabilities in respect of such de-commissioned apparatus from the date of such surrender.
103.—(1) If, for the purpose of executing any works in, on, under or over any land held or used under this Order, the undertaker requires the removal of any apparatus placed in that land, it must give to Cadent advance written notice of that requirement, together with a plan and section of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order Cadent reasonably needs to move or remove any of its apparatus) the undertaker must afford to Cadent to its satisfaction (taking into account sub-paragraph 104(1) below) the necessary facilities and rights—
(a)for the construction of alternative apparatus (including appropriate working areas required to reasonably and safely undertake necessary works by Cadent in respect of the apparatus);
(b)subsequently for the maintenance of that apparatus (including appropriate working areas required to reasonably and safely undertake necessary works by Cadent in respect of the apparatus); and
(c)to allow access to that apparatus (including appropriate working areas required to reasonably and safely undertake necessary works by Cadent in respect of the apparatus).
(2) If the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (1), in the land in which the alternative apparatus or part of such apparatus is to be constructed, Cadent may, on receipt of a written notice to that effect from the undertaker, take such steps as are reasonable in the circumstances in an endeavour to assist the undertaker in obtaining the necessary facilities and rights in the land in which the alternative apparatus is to be constructed save that this obligation shall not extend to the requirement for Cadent to use its compulsory purchase powers to this end unless it (in its absolute discretion) elects to so do.
(3) Any alternative apparatus to be constructed in land of the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between Cadent and the undertaker.
(4) Cadent must, after the alternative apparatus to be provided or constructed has been agreed, and subject to the prior grant to Cadent of such facilities and rights as are referred to in sub-paragraph (2) or (3) have been afforded to Cadent to its satisfaction, then proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to decommission or remove any apparatus required by the undertaker to be decommissioned or removed under the provisions of this Part of this Schedule.
(5) Where apparatus is to be decommissioned pursuant to sub–paragraph (4) such apparatus shall be filled with concrete save where Cadent determines (in its absolute discretion) that this method of decommissioning would not be appropriate and in such circumstances the undertaker shall be able to require the removal of such apparatus at the undertaker’s expense unless such removal is not practicable in which case Cadent shall decommission the apparatus as it sees fit.
104.—(1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to or secures for Cadent facilities and rights in land for the access to, construction and maintenance alternative apparatus in substitution for apparatus to be decommissioned or removed, those facilities and rights must be granted upon such terms and conditions as may be agreed between the undertaker and Cadent and must be no less favourable on the whole to Cadent than the facilities and rights enjoyed by it in respect of the apparatus to be decommissioned or removed unless otherwise agreed by Cadent.
(2) If the facilities and rights to be afforded by the undertaker and agreed with Cadent under sub-paragraph (1) above in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are less favourable on the whole to Cadent than the facilities and rights enjoyed by it in respect of the apparatus to be decommissioned or removed (in Cadent’s opinion) then the terms and conditions to which those facilities and rights are subject in the matter will be referred to arbitration in accordance with paragraph 112 (arbitration) of this protective provision and the arbitrator shall make such provision for the payment of compensation by the undertaker to Cadent as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
105.—(1) Not less than 56 days before the commencement of any specified works the undertaker must submit to Cadent a plan and, if reasonably required by Cadent, a ground monitoring scheme in respect of those works.
(2) The plan to be submitted to Cadent under sub-paragraph (1) must include a method statement and describe—
(a)the exact position of the works;
(b)the level at which these are proposed to be constructed or renewed;
(c)the manner of their construction or renewal including details of excavation, positioning of plant etc.;
(d)the position of all apparatus;
(e)by way of detailed drawings, every alteration proposed to be made to or close to any such apparatus; and
(f)any intended maintenance regimes.
(3) The undertaker must not commence any works to which sub-paragraphs (1) and (2) apply until Cadent has given written approval of the plan so submitted.
(4) Any approval of Cadent required under sub-paragraph (3)—
(a)may be given subject to reasonable conditions for any purpose mentioned in sub-paragraphs (5) or (7); and
(b)must not be unreasonably withheld.
(5) In relation to any work to which sub-paragraphs (1) and/or (2) apply, Cadent may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing apparatus against interference or risk of damage or for the purpose of providing or securing proper and convenient means of access to any apparatus.
(6) Works to which this paragraph applies must only be executed in accordance with the plan, submitted under sub-paragraph (1) and (2) or as relevant sub-paragraph (4), as approved or as amended from time to time by agreement between the undertaker and Cadent and in accordance with all conditions imposed under sub-paragraph (4)(a), and Cadent will be entitled to watch and inspect the execution of those works.
(7) Where Cadent requires any protective works to be carried out by itself or by the undertaker (whether of a temporary or permanent nature) such protective works, inclusive of any measures or schemes required and approved as part of the plan approved pursuant to this paragraph, must be carried out to Cadent’s satisfaction prior to the commencement of any authorised works (or any relevant part thereof) for which protective works are required prior to commencement.
(8) If Cadent, in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraphs 1 to 3 and 6 to 8 apply as if the removal of the apparatus had been required by the undertaker under sub-paragraph 103(2).
(9) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of the authorised works, a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph will apply to and in respect of the new plan.
(10) The undertaker will not be required to comply with sub-paragraph (1) where it needs to carry out emergency works as defined in the 1991 Act but in that case it must give to Cadent notice as soon as is reasonably practicable and a plan of those works and must comply with—
(a)the conditions imposed under sub-paragraph (4)(a) insofar as is reasonably practicable in the circumstances; and
(b)sub-paragraph (11) at all times.
(11) At all times when carrying out any works authorised under the Order the undertaker must comply with the Cadent’s policies for safe working in the vicinity of Cadent’s Assets CD/SP /SSW22 and HSE’s “HS(~G)47 Avoiding Danger from underground services”.
(12) As soon as reasonably practicable after any ground subsidence event attributable to the authorised development the undertaker shall implement an appropriate ground mitigation scheme save that Cadent retains the right to carry out any further necessary protective works for the safeguarding of its apparatus and can recover any such costs in line with paragraph 106.
106.—(1) Subject to the following provisions of this paragraph, the undertaker must pay to Cadent on demand all charges, costs and expenses reasonably anticipated or incurred by Cadent in, or in connection with, the inspection, removal, relaying or replacing, alteration or protection of any apparatus or the construction of any new or alternative apparatus which may be required in consequence of the execution of any authorised works as are referred to in this Part of this Schedule including without limitation—
(a)any costs reasonably incurred by or paid by Cadent in connection with the negotiation of rights or the exercise of statutory powers for such apparatus including without limitation all costs (including professional fees) incurred by Cadent in connection with the cost of the carrying out of any diversion work or the provision of any alternative apparatus;
(b)the cutting off of any apparatus from any other apparatus or the making safe of redundant apparatus;
(c)the approval of plans;
(d)the carrying out of protective works, plus a capitalised sum to cover the cost of maintaining and renewing permanent protective works;
(e)the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to in this Part of this Schedule; and
(f)any watching brief pursuant to sub-paragraph 105(6).
(2) There will be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Part of this Schedule and which is not re-used as part of the alternative apparatus, that value being calculated after removal.
(3) If in accordance with the provisions of this Part of this Schedule—
(a)apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
(b)apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 35 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to Cadent by virtue of sub-paragraph (1) will be reduced by the amount of that excess save where it is not possible or appropriate in the circumstances (including due to statutory or regulatory changes) to obtain the existing type of apparatus at the same capacity and dimensions or place at the existing depth in which case full costs will be borne by the undertaker.
(4) For the purposes of sub-paragraph (3)—
(a)an extension of apparatus to a length greater than the length of existing apparatus will not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
(b)where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole will be treated as if it also had been agreed or had been so determined.
(5) An amount which apart from this sub-paragraph would be payable to Cadent in respect of works by virtue of sub-paragraph (1) will, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on Cadent any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.
107.—(1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any works authorised by this Part of this Schedule (including without limitation relocation, diversion, decommissioning, construction and maintenance of apparatus or alternative apparatus) or in consequence of the construction, use, maintenance or failure of any of the authorised works by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by him) in the course of carrying out such works, including without limitation works carried out by the undertaker under this Part of this Schedule or any subsidence resulting from any of these works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of the authorised works) or property of Cadent, or there is any interruption in any service provided, or in the supply of any goods, by Cadent, or Cadent becomes liable to pay any amount to any third party, the undertaker will—
(a)bear and pay on demand the cost reasonably incurred by Cadent in making good such damage or restoring the supply; and
(b)indemnify Cadent for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from Cadent, by reason or in consequence of any such damage or interruption or Cadent becoming liable to any third party as aforesaid other than arising from any default of Cadent.
(2) The fact that any act or thing may have been done by Cadent on behalf of the undertaker or in accordance with a plan approved by Cadent or in accordance with any requirement of Cadent or under its supervision including under any watching brief will not (unless sub-paragraph (3) applies) excuse the undertaker from liability under the provisions of this sub-paragraph (1) unless Cadent fails to carry out and execute the works properly with due care and attention and in a skilful and workman like manner or in a manner that does not accord with the approved plan.
(3) Nothing in sub-paragraph (1) shall impose any liability on the undertaker in respect of—
(a)any damage or interruption to the extent that it is attributable to the neglect or default of Cadent, its officers, servants, contractors or agents; and
(b)any authorised works and/or any other works authorised by this Part of this Schedule carried out by Cadent as an assignee, transferee or lessee of the undertaker with the benefit of the Order pursuant to section 156 of the Planning Act 2008 or article 9 (transfer benefit of Order, etc.) subject to the proviso that once such works become apparatus (“new apparatus”), any authorised works yet to be executed and not falling within this sub-section 3(b) will be subject to the full terms of this Part of this Schedule including this paragraph 107.
(4) Cadent must give the undertaker reasonable notice of any such third party claim or demand and no settlement or compromise must, unless payment is required in connection with a statutory compensation scheme, be made without first consulting the promoter and considering their representations.
108. Save to the extent provided for to the contrary elsewhere in this Part of this Schedule or by agreement in writing between Cadent and the undertaker, nothing in this Part of this Schedule shall affect the provisions of any enactment or agreement regulating the relations between the undertaker and Cadent in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made and which will continue to have effect.
109. Where in consequence of the proposed construction of any of the authorised works, the undertaker or Cadent requires the removal of apparatus under sub-paragraph 103(2) or Cadent makes requirements for the protection or alteration of apparatus under paragraph 105, the undertaker shall use its best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of Cadent’s undertaking and Cadent shall use its best endeavours to co-operate with the undertaker for that purpose.
110. For the avoidance of doubt whenever Cadent’s consent, agreement or approval is required in relation to plans, documents or other information submitted by Cadent or the taking of action by Cadent, it must not be unreasonably withheld or delayed.
111. If in consequence of the agreement reached in accordance with sub-paragraph 104(1) or the powers granted under this Order the access to any apparatus (including appropriate working areas required to reasonably and safely undertake necessary works by Cadent in respect of the apparatus) is materially obstructed, the undertaker must provide such alternative rights and means of access to such apparatus as will enable Cadent to maintain or use the apparatus no less effectively than was possible before such obstruction.
112. Save for differences or disputes arising under sub-paragraphs 103(2), 103(4), 105(1), and paragraph 106 any difference or dispute arising between the undertaker and Cadent under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and Cadent, be determined by arbitration in accordance with article 35 (arbitration) to be referred to and settled by a single arbitrator to be agreed between the parties, or failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) to the President of the Institute of Civil Engineers and in settling any difference or dispute, the arbitrator must have regard to the requirements of Cadent for ensuring the safety, economic and efficient operation of Cadent’s apparatus.
113. The plans submitted to Cadent by the undertaker pursuant to sub-paragraph 105(1) must be sent to Cadent Gas Limited Plant Protection by e-mail to plantprotection@cadentgas.com copied by e-mail to landservices@cadentgas.com and sent to the General Counsel Department at Cadent’s registered office or such other address as Cadent may from time to time appoint instead for that purpose and notify to the undertaker.
114. For the protection of any operator, referred to in this Part of this Schedule, the following provisions have effect until the commencement of the operation of the authorised development, unless otherwise agreed in writing between the undertaker and the operator.
115. In this Part of this Schedule—
“the 2003 Act” means the Communications Act 2003;
“the code rights” has the same meaning as in the Paragraph 3 of the electronic communications code;
“electronic communications apparatus” has the same meaning as in electronic communications code;
“the electronic communications code” has the same meaning as in Chapter 1 of Part 2 of the 2003 Act;
“the electronic communications code network” means—
so much of an electronic communications network or infrastructure system provided by an electronic communications code operator as is not excluded from the application of the electronic communications code by a direction under section 106 of the 2003 Act; and
an electronic communications network which the undertaker is providing or proposing to provide;
“electronic communications code operator” means a person in whose case the electronic communications code is applied by a direction under section 106 of the 2003 Act;
“infrastructure system” has the same meaning as in the electronic communications code and references to providing an infrastructure system are to be construed in accordance with paragraph 7(2) of that code; and
“operator” means the operator of an electronic communications code network.
116. The exercise of the powers of article 16 (statutory undertakers and operator of the electronic communications code network) is subject to Part 10 (undertaker’s works affecting electronic communications apparatus) of the electronic code.
117.—(1) Subject to sub-paragraphs (2) to (4), if as the result of the authorised development or its construction, or of any subsidence resulting from any of the authorised development—
(a)any damage is caused to any electronic communications apparatus belonging to an operator (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of the authorised development), or other property of an operator; or
(b)there is any interruption in the supply of the service provided by an operator, the undertaker must bear and pay the cost reasonably incurred by the operator in making good such damage or restoring the supply and make reasonable compensation to that operator for any other expenses, loss, damages, penalty or costs incurred by it, by reason, or in consequence of, any such damage or interruption.
(2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of an operator, its officers, servants, contractors or agents.
(3) The operator must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise of the claim or demand is to be made without the consent of the undertaker and if such consent, is withheld, the undertaker has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
(4) Any difference arising between the undertaker and the operator under this Part of this Schedule must be referred to and settled by arbitration under article 35 (arbitration).
118. This Part of this Schedule does not apply to—
(a)any apparatus in respect of which the relations between the undertaker and an operator are regulated by the provisions of Part 3 (street works in England and Wales) of the 1991 Act; or
(b)any damage, or any interruption, caused by electro-magnetic interference arising from the construction or use of the authorised development.
119. Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and an operator in respect of any apparatus in land belonging to the undertaker on the date on which this Order is made.
120. The provisions of this Part of this Schedule shall apply for the protection of DFDS, unless otherwise agreed in writing at any time between the undertaker and DFDS.
121. In this Part of this Schedule—
“authorised work” means any work specified in Schedule 1;
“DFDS” means DFDS Seaways plc, company number 01554521 registered at Nordic House, Western Access Road, Immingham Dock, Immingham, DN40 2LZ; and
“environmental document” means the environmental statement prepared for the purposes of the application for this Order together with any supplementary environmental information or other document so prepared by way of clarification or amplification of the environmental statement.
122. The undertaker must, at least 28 days before the undertaker commences the construction of any authorised work, or any phase of any authorised work, that has been assessed in any environmental document as being likely to interfere with DFDS’ use of the Port of Immingham or the surrounding road network, inform DFDS in writing stating what is proposed and have regard to any response received from DFDS.
123.—(1) The undertaker is responsible for and must make good to DFDS all reasonable financial costs or losses not otherwise provided for in this Part of this Schedule which may reasonably be incurred or suffered by DFDS by reason of—
(a)the construction of the authorised works; or
(b)any act or omission of the undertaker, its employees, contractors or agents or others whilst engaged in the construction of the authorised works.
(2) DFDS must give the undertaker no less than 28 days’ notice in writing, providing a detailed explanation and justification for any such claim, as is referred to in sub-paragraph (1), and no settlement or compromise of any such claim or demand is to be made without the prior consent of the undertaker.
(3) Nothing in sub-paragraph (1) imposes any liability on the Undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of DFDS, its officers, servants, contractors or agents.
124. Before commencing any marine commercial operations the undertaker must provide DFDS with a copy of the Statutory Conservancy and Navigation Authority’s approval of the written statement of proposed safe operating procedures for access to and egress from the authorised development, including any approved alteration made from time to time.
125. Any dispute arising between the undertaker and DFDS under this Part of this Schedule is to be determined by arbitration as provided in article 35 (arbitration).
126. The provisions of this Part of this Schedule have effect, unless otherwise agreed in writing between the undertaker and CLdN, for the protection of CLdN until the commencement of operation of the authorised development.
127.—(1) Where the terms defined in article 2 (interpretation) of this Order are inconsistent with sub-paragraph (2), the latter prevail.
(2) In this part of this Schedule—
“CLdN” means CLdN Ports Killingholme Limited, company number 00278815, whose principal office is at 130 Shaftesbury Avenue, 2nd Floor, London, W1D 5EU as statutory harbour authority for and operator of the Port and any successor in title or function to the Port;
“the CLdN disposal site” means Humber 3A/Clay Huts (HU060) disposal site situated adjacent to Clay Huts and Holme Ridge in the river Humber;
“environmental document” means environmental statement prepared for the purposes of the application for this Order together with any supplementary environmental information or other document so prepared by way of clarification or amplification of the environmental statement;
“the Port” means any land (including land covered by water) at Killingholme for the time being owned or used by CLdN for the purposes of its statutory undertaking, together with any quays, jetties, docks, river walls or works held in connection with that undertaking;
“specified work” means any work, activity or operation authorised by this Order, by the Town and Country Planning Act (General Permitted Development) Order 2015 or by any planning permission given under the Town and Country Planning Act 1990, and any vessel movements, which has been assessed in any environmental document as being likely to interfere with—
the Port or access (including over water) to and from the Port; or
CLdN’s ability to carry out disposal activities at the CLdN disposal site; or
the functions of CLdN as the statutory harbour authority for the Port.
128. The undertaker and CLdN must each act in good faith and use reasonable endeavours to co-operate with, and provide assistance to, each other as may be required to give effect to the provisions of this Part of this Schedule.
129. The undertaker must inform CLdN in writing of the intended start date and the likely duration of the carrying out of any specified work at least 20 days prior to the commencement of the specified work.
130. Any operations for the construction of any specified work, once commenced, must be carried out by the undertaker so that CLdN does not suffer more interference than is reasonably necessary.
131.—(1) During the construction of the authorised development, the Undertaker must indemnify CLdN against all financial losses, costs, charges, damages, expenses, claims and demands which may reasonably be incurred or occasioned to CLdN by reason or arising in connection with—
(a)any obstruction which prevents or materially hinders access into or out of the Port, which is caused by or attributable to the undertaker or its agents or contractors in exercising the power of this Order, save for where such an obstruction is as a result of the lawful actions or direction of the Statutory Conservancy and Navigation Authority;
(b)the undertaking by CLdN of works or measures to prevent or remedy a danger or impediment to navigation or access to or from the Port arising from the exercise by the undertaker of its powers under this Order; or
(c)any additional costs of disposal of dredging arisings from the Port incurred by CLdN as a result of the undertaker’s use of the CLdN disposal site.
(2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of CLdN, its officers, servants, contractors or agents.
(3) Without limiting the generality of sub-paragraph (1), the undertaker must indemnify CLdN from and against all claims and demands arising out of, or in connection with, such construction, maintenance or failure or act or omission as is mentioned in that sub-paragraph until the commencement of the operation of the authorised development.
132. Unless otherwise agreed in writing, any dispute arising between the undertaker and CLdN under this Part of this Schedule is to be determined by arbitration as provided in article 35 (arbitration).
133. The provisions of this Part of this Schedule have effect for the protection of the Board unless otherwise agreed in writing between the undertaker and the Board.
134. In this part of this Schedule—
“construction” includes execution, placing, altering, replacing, relaying and removal; and “construct” and “constructed” must be construed accordingly;
“drainage work” means any ordinary watercourse and includes any land that provides or is expected to provide flood storage capacity for any ordinary watercourse and any bank, wall, embankment or other structure, or any appliance, constructed or used for land drainage or flood defence;
“evidence” includes hydraulic modelling, infiltration test results and geotechnical evaluations;
“ordinary watercourse” has the meaning given in section 72 (Interpretation) of the Land Drainage Act 1991(6);
“plans” includes sections, drawings, specifications and method statements;
“specified work” means—
the making of any opening into or connections with any watercourse or drain in connection with the authorised development; and/or
so much of any work or operation of the authorised development as is in, on, under, over or within 9 metres of a drainage work for which the Board has responsibility or is otherwise likely to—
affect any drainage work;
affect the total volume or volumetric rate of flow of water in or flowing to or from any drainage work;
affect the flow of water in any drainage work; or
affect the conservation, distribution or use of water resources.
135. The undertaker must not make any opening into or connections with any watercourse or drain in connection with the authorised development or carry out any specified work except—
(a)in accordance with plans approved by the Board in accordance with this Part of this Schedule; and
(b)where the Board has been given the opportunity to supervise the making of the opening or connection,
and no discharge of water under article 24 (discharge of water) shall be made until details of the location and rate of discharge have been submitted to and approved in writing by the Board.
(2) Before beginning to construct any specified work, the undertaker must submit to the Board plans of the specified work, evidence to support said plans and any such further particulars available to it as the Board may within 28 days of the submission of the plans reasonably require (or submission of further particulars if required by the Board).
(3) Any such specified work must not be constructed except in accordance with such plans as may be approved in writing by the Board or determined under paragraph 143.
(4) Any approval of the Board required under this paragraph—
(a)must not be unreasonably withheld or delayed;
(b)is deemed to have been given if it is neither given nor refused within 2 months of the submission of the plans for approval (or the submission of further particulars if applicable) or, in the case of a refusal, if it is not accompanied by a statement of the grounds of refusal; and
(c)may be given subject to such reasonable requirements and conditions as the Board may consider appropriate.
(5) The Board must use its reasonable endeavours to respond to the submission of any plans before the expiration of the period mentioned in sub-paragraph (4).
(6) Where under this Part of this Schedule the Board is required to give its consent or approval in respect of any matter, that consent or approval is subject to the condition that the Board complies with its obligations to consult other appropriate agencies, to have regard to any guidance issued by any appropriate supervisory body and has regard to its obligations under statute.
136. Without limiting paragraph 135, the requirements which the Board may make under that paragraph include conditions requiring the undertaker at its own expense to construct such protective works, whether temporary or permanent, during the construction of the specified work (including the provision of flood banks, walls or embankments or other new works and the strengthening, repair or renewal of existing banks, walls or embankments) as are reasonably necessary—
(a)to safeguard any drainage work against damage; or
(b)to secure that its efficiency for flood defence purposes is not impaired and that the risk of flooding is not otherwise increased,
by reason of any specified work or the authorised development.
137.—(1) Subject to sub–-paragraph (2), any specified work, and all protective works required by the Board under paragraph 136, must be constructed—
(a)without unreasonable delay in accordance with the plans approved or deemed to have been approved or settled under this Part; and
(b)to the reasonable satisfaction of the Board, and an officer of the Board is entitled to give such notice as may be reasonably required in the circumstances to watch and inspect the construction of such works.
(2) The undertaker must give to the Board—
(a)not less than 14 days’ notice in writing of its intention to commence construction of any specified work; and
(b)notice in writing of its completion not later than 7 days after the date on which it or the authorised development is brought into use.
(3) If the Board reasonably requires, the undertaker must construct all or part of the protective works so that they are in place before the construction of the specified work.
(4) If any part of a specified work or any protective work required by the Board is constructed otherwise than in accordance with the requirements of this Part of this Schedule, the Board may by notice in writing require the undertaker at the undertaker’s expense to comply with the requirements of this Part of this Schedule or (if the undertaker so elects and the Board in writing consents, such consent not to be unreasonably withheld or delayed) to remove, alter or pull down the work and, where removal is required, to restore the site to its former condition to such extent and within such limits as the Board reasonably requires.
(5) Subject to sub-paragraph (6), if within a reasonable period, being not less than 28 days from the date when a notice under sub-paragraph (4) is served on the undertaker, the undertaker has failed to begin taking steps to comply with the requirements of the notice and subsequently to make reasonably expeditious progress towards their implementation, the Board may execute the works specified in the notice, and any expenditure reasonably incurred by it in so doing is recoverable from the undertaker
(6) In the event of any dispute as to whether sub-paragraph (4) is properly applicable to any work in respect of which notice has been served under that sub-paragraph, or as to the reasonableness of any requirement of such a notice, the Board must not except in emergency exercise the powers conferred by sub-paragraph (4) until the dispute has been finally resolved by agreement or determined under paragraph 143.
138. If by reason of the construction of the authorised development or any specified work or of the failure of any such work the efficiency of any drainage work for flood defence purposes is impaired, or the drainage work is otherwise damaged, the impairment or damage must be made good by the undertaker to the reasonable satisfaction of the Board and, if the undertaker fails to do so, the Board may make good the impairment or damage and recover from the undertaker the expense reasonably incurred by it in doing so.
139. If the Board considers that, as a direct result of the construction and/or operation of the authorised development the outfall of the Habrough Drain has been obstructed or impaired and either—
(a)the obstruction has the potential to impede or affect the flow of water from the Habrough Drain into the River Humber; or
(b)the efficiency of any ordinary watercourse for flood defence or land drainage purposes is impaired, or that watercourse is otherwise damaged, so as to require remedial action,
such obstruction, impairment or damage must be made good by the undertaker to the reasonable satisfaction of the Board and if the Undertaker fails to do so, the Board may make good the same and recover from the undertaker the expense reasonably incurred by it in so doing.
140. The undertaker must compensate the Board in respect of all costs, charges and expenses that the Board may reasonably incur, have to pay or may sustain—
(a)in the examination or approval of plans and evidence under this Part of this Schedule;
(b)in inspecting the proposed site for and construction of any specified work or any protective works required by the Board under this Part of this Schedule; and
(c)in carrying out of any surveys or tests by the Board that are reasonably required in connection with the authorised development and/or construction of the specified work.
141. Without limiting the other provisions of this Part of this Schedule, the undertaker must compensate the Board in respect of all claims, demands, proceedings, costs, damages, expenses or loss that may be made or taken against, reasonably recovered from or reasonably incurred by the Board by reason of—
(a)any damage to any drainage work so as to impair its efficiency for the purposes of flood defence; and
(b)any flooding or increased flooding of any such land which is caused by, or results from, the authorised development, the construction of the specified work or any act or omission of the undertaker, its contractors, agents or employees whilst engaged upon the work.
142. The fact that any work or thing has been executed or done by the undertaker in accordance with a plan approved or deemed to be approved by the Board, or to its satisfaction, or in accordance with any directions or award of an arbitrator, does not relieve the undertaker from any liability under this Part of this Schedule.
143. Any dispute between the undertaker and the Board under this Part of this Schedule, unless otherwise agreed, must be determined by arbitration under article 35 (arbitration).