37. Subject to the following provisions of this paragraph, during the construction of the authorised development the undertaker must pay to IOT Operators the reasonable costs and expenses incurred by the IOT Operators in, or in connection with—
(a)the inspection, removal, alteration or protection of any apparatus; or
(b)the watching and inspecting the execution of any specified work; or
(c)the imposition of reasonable requirements for the protection or alteration of apparatus,
which may reasonably be required in consequence of the execution of any such works as are required under this Schedule.