Removal of temporary works
9. On completion of the construction of any part of a permanent authorised work, the undertaker must as soon as practicable remove—
(a)any temporary tidal work carried out only for the purposes of that part of the permanent work; and
(b)any materials, plant and equipment used for such construction,
and must make good the site to the reasonable satisfaction of the Statutory Conservancy and Navigation Authority.