PART 5Transfer of projects to another approver

Section 53(7): prescribed provisionI224

For the purposes of section 53(7)(a) of the 1984 Act, section 52(1)(a) of the 1984 Act is prescribed.

Annotations:
Commencement Information
I2

Reg. 24 in force at 6.4.2024, see reg. 1(3)

Information to be included in transfer certificatesI325

For the purposes of section 53B(5) of the 1984 Act, a transfer certificate must contain the following information—

a

a statement describing the original work and the unfinished work21;

b

a statement describing all the steps the approver has taken to determine, in accordance with section 53B(2) of the 1984 Act, whether the unfinished work contravenes any provision of the building regulations, in particular listing—

i

each inspection or laying open of the work undertaken;

ii

each report of any inspection or laying open of work produced;

iii

any other assessment of the work which was considered;

c

a statement setting out the name and address of the registered building inspector from whom advice was obtained under section 54B(3) of the 1984 Act before giving the transfer certificate;

d

a declaration, signed and dated by the approver, confirming—

i

the approver has inspected the unfinished work;

ii

the approver has determined that, as at the date of the transfer certificate, the unfinished work does not contravene any provision of the building regulations;

iii

each report or assessment referred to the statement under paragraph (b) has been included in the transfer report given under section 53B of the 1984 Act;

iv

the approver has obtained advice from a registered building inspector under section 54B(3) of the 1984 Act before giving the transfer certificate, and

v

the approver has received the agreement of the person carrying out or intending to carry out the work to submit the transfer certificate and transfer report.

Annotations:
Commencement Information
I3

Reg. 25 in force at 6.4.2024, see reg. 1(3)

Grounds for rejecting a transfer certificate and transfer reportI426

The grounds on which a local authority may reject a transfer certificate and transfer report are those prescribed in Schedule 5.

Annotations:
Commencement Information
I4

Reg. 26 in force at 6.4.2024, see reg. 1(3)

Cases where a further initial notice may be given after cancellation of an initial notice under section 53DI127

1

For the purposes of section 53D(5) of the 1984 Act, the following circumstances are prescribed—

a

the approver has cancelled the initial notice under section 52(1)(a) of the 1984 Act;

b

the person carrying out or intending to carry out the work has cancelled the initial notice under section 53D(3) of the 1984 Act because they were satisfied the approver was unable to carry out (or continue to carry out) their functions with respect to any of the work to which the initial notice relates;

c

the approver is given a specified disciplinary order during the relevant period (as defined in section 53B(7) of the 1984 Act).

2

In this regulation a “specified disciplinary order” means—

a

any disciplinary order under section 58U(2)(b) of the 1984 Act (variation of registration) such that the approver is no longer able to carry out their functions with respect to any of the work to which the initial notice F1relates;

b

any disciplinary order under section 58U(2)(c) of the 1984 Act (suspension of registration) excluding any suspension which is as a consequence of functions in relation to the unfinished work or work for the person carrying out the work;

c

any disciplinary order under section 58U(2)(d) of the 1984 Act (cancellation of registration) excluding any cancellation which is as a consequence of functions in relation to the unfinished work or work for the person carrying out the work;

d

an order under section 58V of the 1984 Act (interim suspension for suspected serious contravention) excluding any interim suspension which is as a consequence of functions in relation to the unfinished work or work for the person carrying out the work.