The Hornsea Four Offshore Wind Farm (Correction) Order 2024

This Statutory Instrument has been published in substitution of S.I. 2024/113 to correct the omission of that instrument not being printed.

Statutory Instruments

2024 No. 117

Infrastructure Planning

The Hornsea Four Offshore Wind Farm (Correction) Order 2024

Made

30th January 2024

Coming into force

31st January 2024

The Hornsea Four Offshore Wind Farm Order 2023(1), which granted development consent within the meaning of the Planning Act 2008 (“the Act”)(2), contains correctable errors within the meaning of paragraph 1 of Schedule 4 to the Act.

In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, before the end of the relevant period (as defined in paragraph 1(6)(a) of Schedule 4 to the Act), the Secretary of State received a written request from the applicant(3) for the correction of errors in the Hornsea Four Offshore Wind Farm Order 2023 under paragraph 1(5)(a) of Schedule 4 to the Act.

In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State has informed East Riding of Yorkshire Council as the relevant local planning authority(4), that the request has been received.

The Secretary of State, in exercise of the powers conferred by section 119, and paragraphs 1(4) and 1(8) of Schedule 4 to the Act, makes the following Order—

(2)

2008 c. 29. Paragraph 1 of Schedule 4 was amended by paragraph 70 of Schedule 13, and Part 20 of Schedule 25, to the Localism Act 2011 (c. 20) and by paragraph 4 of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23). There are other amendments to the Act which are not relevant to this Order.

(3)

As defined in paragraph 4 of Schedule 4 to the Act.

(4)

As defined in paragraph 4 of Schedule 4 to the Act.