SCHEDULES

SCHEDULE 12PROTECTIVE PROVISIONS

PART 20FOR THE PROTECTION OF SOUTH TEES DEVELOPMENT CORPORATION

Provision for diversion works279

If the undertaker issues notice to the Teesworks entity under paragraph 272(b) confirming that it does not agree to the diversion notice, the Teesworks entity may submit a further diversion notice to the undertaker to address the undertaker’s reasons for refusal under paragraph 275, provided that the undertaker is not obliged to consider any further diversion notice that is received by the undertaker—

a

more than 30 days after the date of the notice issued by the undertaker under paragraph 272(b); or

b

in any case 150 days from the date of the undertaker’s works notice under paragraph 268(b) or if relevant 150 days from the date of any further works notice issued by the undertaker under paragraph 269.