Apparatus of National Gas in streets subject to temporary stopping up

35.  Notwithstanding the temporary stopping up or diversion of any street under the powers of article 13 (temporary stopping up of streets, public rights of way and access land), National Gas will be at liberty at all times to take all necessary access across any such stopped up street and/or to execute and do all such works and things in, upon or under any such street as may be reasonably necessary or desirable to enable it to maintain any apparatus which at the time of the stopping up or diversion was in that street.