Article 2

SCHEDULE 1AUTHORISED DEVELOPMENT

Authorised Development

1.  In the County of Cambridgeshire and the County of Norfolk a nationally significant infrastructure project as defined in section 14(1)(a) (nationally significant infrastructure projects: general) and section 15 (generating stations) of the 2008 Act and associated development within the meaning of section 115(2) (development for which development consent may be granted) of the 2008 Act comprising all or part of—

In the County of Cambridgeshire

Work No. 1 – an electricity generating station with a gross installed generating capacity of up to 60 MW and capacity to process up to 625,600 tonnes of residual waste per annum, including—

(a)fuel reception and storage facilities consisting of tipping hall, tipping bays, tipping bunker, main waste bunker, shredder, waste chutes, cranes, cabin and handling and maintenance equipment;

(b)a combustion system including boiler house, air cooled moving grates, boilers and water tanks;

(c)air pollution control plant and monitoring systems including silos, reactors, filter houses, fans, cabins and loading and storage areas;

(d)a steam turbine and generator including turbine hall and cooling system;

(e)a bottom ash handling system, including ash storage bunker, conveyors, collection bays, cranes and handling and maintenance equipment;

(f)air cooled condenser;

(g)compressed air system;

(h)tank(s) for the storage of urea;

(i)switch gear building;

(j)control room; and

(k)water treatment and storage plant.

Work No. 1A – two chimneys and associated continuous emissions monitoring systems and platform.

Work No. 1B – administration building, including—

(a)roof–mounted photovoltaic solar panels to supplement energy use within the administration building, generating approximately 50kW (0.05MW) of electricity;

(b)brown roof and green walls;

(c)natural cooling apparatus including brise soleil to eastern elevation;

(d)bat and bird boxes; and

(e)rainwater harvesting apparatus.

Work No. 2 – in connection with and in addition to Work Nos 1, 1A and 1B—

Work No. 2A

(a)fire water tank and fire water pump cabin;

(b)diesel generator and diesel storage tanks;

(c)132kV switching compound, transformers, switch gear, cabling, kiosk and associated telemetry;

(d)workshop and stores; and

(e)gatehouse and weighbridges; and

Work No. 2B

(a)vehicle layby and queuing areas;

(b)laydown and maintenance areas;

(c)internal access roads and pedestrian walkways;

(d)parking areas and electrical vehicle charging points;

(e)pipes, cables, telecommunications and other services and associated infrastructure;

(f)site drainage, including works to drains and culverts, potable and wastewater services and associated infrastructure;

(g)hard and soft landscaping; and

(h)biodiversity enhancement measures and environmental mitigation measures.

Work No. 3 – associated development comprising combined heat and power equipment including heat exchangers, pipework, valving, pumps, pressurisation, water treatment systems and associated instrumentation and telemetry.

Work No. 3A – associated development comprising combined heat and power equipment including steam and condensate pipes, pipe racks, supports, pipe runs, valving, electrical supply cables and associated instrumentation and telemetry, vertical expansion loops and pipe bridges.

Work No. 3B – associated development comprising combined heat and power equipment including steam and condensate pipes, pipe racks, supports, pipe runs, valving, electrical supply cables and associated instrumentation and telemetry, bellows expansion connections, vertical expansion loops and pipe bridges.

Work No. 4A – associated development comprising a new site access and access improvements on New Bridge Lane including carriageway and footway widening, highway alteration works, junction improvements including signalisation and pedestrian crossing, culverts, drains, street lighting, services and utilities connections and compact substation.

Work No. 4B – associated development comprising a new site access and access improvements on Algores Way including carriageway and footway widening, highway alteration work, culverts, drains, services and utilities connections and street lighting.

Work No. 5 – associated development being a temporary construction compound and laydown area including—

(a)hard standings;

(b)materials storage and laydown areas;

(c)construction fabrication areas;

(d)generators;

(e)vehicle parking areas;

(f)wheel washing facilities;

(g)accommodation, office and welfare buildings;

(h)new or alteration to accesses;

(i)internal haul roads; and

(j)temporary pedestrian bridges.

Work No. 6A – comprising associated development for the potable water connection—

(a)water pipe(s) and associated instrumentation and telemetry;

(b)cable trenches, ducting, protection plates and jointing bays; and

(c)horizontal directional drilling compound.

Work No. 6B – comprising associated development for the foul water connection—

(a)water pipe(s) and associated instrumentation and telemetry; and

(b)cable trenches, ducting, protection plates and jointing bays.

Work No. 7 – comprising associated development—

(a)132kV electrical underground cables and associated instrumentation and telemetry;

(b)cable trenches, ducting, protection plates and jointing bays; and

(c)temporary storage compounds in laybys on the A47.

In the County of Norfolk

Work No. 8 – comprising associated development—

(a)132kV electrical underground cables and associated instrumentation and telemetry;

(b)cable trenches, ducting, protection plates and jointing bays; and

(c)temporary storage compounds in laybys on the A47.

Work No. 9 – comprising associated development—

(a)electrical substation and compound including clean air switchgear, control room kiosks and monitoring kiosk;

(b)cables and associated instrumentation and telemetry;

(c)cable trenches, ducting, protection plates and jointing bays; and

(d)new or alteration to accesses, internal pedestrian and vehicular access road and parking area.

In the County of Cambridgeshire

Work No. 10 – comprising associated development, being an acoustic fence.

In connection with and in addition to Work Nos 1, 1A, 1B, 2A, 2B, 3, 3A, 3B, 4A, 4B, 5, 6A, 6B, 7, 8, 9 and 10 and, to the extent that it does not otherwise form part of those Work Nos, further associated development comprising such other works or operations as may be necessary or expedient for the purposes of or in connection with the authorised development, and which are within the Order limits and fall within the scope of the work assessed by the environmental statement including—

(a)external lighting infrastructure, including lighting columns;

(b)fencing, boundary treatment and other means of enclosure;

(c)demolition of existing buildings and structures;

(d)signage;

(e)CCTV and other security measures;

(f)surface and foul water drainage facilities;

(g)potable water supply;

(h)new telecommunications and utilities apparatus and connections;

(i)hard and soft landscaping;

(j)biodiversity enhancement measures and environmental mitigation measures;

(k)works permanently to alter the position of existing telecommunications and utilities apparatus and connections;

(l)works for the protection of buildings and land;

(m)establishment of temporary construction compounds, including vehicle parking areas, hard standing, materials storage and laydown areas, construction fabrication areas, construction related buildings, accommodation buildings, temporary offices, structures, plant and machinery, lighting and fencing, internal haul routes and wheel wash facilities; and

(n)site establishment and preparation works, including site clearance (including temporary fencing and vegetation removal), earthworks (including soil stripping and storage and site levelling) and excavations, the creation of temporary construction access points and the temporary alteration of the position of services and utilities apparatus and connections.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources