Notice of start of commissioning and notice of date of final commissioningE+W+S

20.—(1) Notice of the commencement of commissioning of Work No. 1 must be given to the relevant planning authority within 7 days of the date on which commissioning is commenced.

(2) Notice of the completion of commissioning of Work No. 1 must be given to the relevant planning authority within 7 days of the date on which commissioning is completed.

Commencement Information

I1Sch. 2 para. 20 in force at 13.3.2024, see art. 1