25.—(1) Prior to the date of final commissioning, the undertaker must demonstrate to the relevant planning authority that it has constructed Work No. 1 and Work No. 2 in accordance with the combined heat and power embedded design measures.
(2) No later than the date that is 18 months after the date of final commissioning, the undertaker must submit to the relevant planning authority for its approval a report (“the CHP review”) updating the combined heat and power assessment.
(3) The CHP review submitted must—
(a)consider the opportunities that reasonably exist for the export of heat from Work No. 3, 3A and 3B at the time of submission of the CHP review; and
(b)include a list of actions (if any) that the undertaker is reasonably and practicably able to take (without material additional cost to the undertaker) to increase the potential for the export of heat from Work No. 3, 3A and 3B.
(4) The undertaker must take such actions as are included, within the timescales specified, in the approved CHP review.
(5) The relevant planning authority must consult with the Environment Agency before approving any CHP review.
(6) On each date (or the first date thereafter which is a working day) during the operation of Work No. 1 that is five years after the date on which it last submitted the CHP review or a revised CHP review to the relevant planning authority, the undertaker must submit to the relevant planning authority for its approval a revised CHP review.
(7) Sub-paragraphs (3) to (5) apply in relation to a revised CHP review submitted under sub‑paragraph (6) in the same way as they apply in relation to the CHP review submitted under sub‑paragraph (7).
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: