Origin of waste

29.—(1) Not less than 17.5% of the waste processed at the authorised development per operational year must originate from within Waste Area 1 unless otherwise agreed by the relevant planning authority. Waste originating outside of Waste Area 1 and then transported to a waste loading point located in Waste Area 1 is not considered to have originated in Waste Area 1.

(2) Not less than 80% of the waste processed at the authorised development per operational year must originate from Waste Area 1 and Waste Area 2 unless otherwise agreed by the relevant planning authority. Subject to sub-paragraph (1), waste transported into Waste Area 2 to a waste loading point is considered to have originated in Waste Area 2.

(3) No more than 20% of the waste processed at the authorised development per operational year must originate from outside of Waste Area 1 and Waste Area 2 unless otherwise agreed by the relevant planning authority. Waste sent direct to the authorised development from a location that is not located in either Waste Area 1 or Waste Area 2 will be deemed to originate from outside of Waste Area 2.

(4) The maximum tonnage of waste received from any one waste planning authority’s administrative area within Waste Area 2 must not exceed 312,800 tonnes in any operational year unless otherwise agreed by the relevant planning authority.

(5) From the date of final commissioning of the authorised development until the authorised development has been decommissioned in accordance with requirement 28 (unless otherwise agreed by the relevant planning authority), the undertaker must maintain a written record, retained at the authorised development, of the quantities and origin of the waste treated by the authorised development for each operational year.

(6) From the date of final commissioning until the authorised development has been decommissioned in accordance with requirement 28 (unless otherwise agreed by the relevant planning authority), on or prior to 1 February each year, the undertaker must provide to the relevant planning authority a report for the preceding operational year (the “Waste Catchment Report”). The Waste Catchment Report must identify—

(a)the waste throughput of the authorised development including the total tonnage of waste processed at the authorised development for the operational year;

(b)waste catchment including as far as it is reasonably practicable to audit, the waste area for each waste loading point for waste processed at the authorised development for the operational year, separately totalling tonnages received from waste area 1, waste area 2 and outside of waste area 2; and

(c)the total annual tonnage processed at the authorised development from each waste planning authority for the operational year.

(7) The relevant planning authority can request an interim Waste Catchment Report at any time for the preceding 12 month period. The undertaker must submit an interim Waste Catchment Report to the relevant planning authority within 6 weeks of receiving the request. The interim Waste Catchment Report must cover the 12 month period ending on the last day of the month the written request was made by the relevant planning authority to the undertaker unless otherwise agreed by the relevant planning authority.

(8) In this paragraph—

operational year” means the period from 1 January to 31 December, inclusive;

throughput” means the tonnage of waste received at the authorised development;

waste area 1” means a 75 kilometre radius from the point that has grid reference N307892.6931 and E545496.9373 and shown on the waste area plan;

waste area 2” means the area shown on the waste area plan; and

waste loading point” means the location where the waste is loaded onto a vehicle prior to being sent directly to the authorised development.

(9) In sub-paragraph (6)(b)waste area” means the areas or locations for each waste loading point, disaggregated to the smallest administrative area practicable, including but not limited to county, unitary, district, borough or postcode area.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources