<dc:identifier>http://www.legislation.gov.uk/uksi/2024/393/article/1</dc:identifier>
<dc:title>The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024</dc:title>
<dc:language>en</dc:language>
<dc:subject scheme="SIheading">INFRASTRUCTURE PLANNING</dc:subject>
<dc:publisher>Statute Law Database</dc:publisher>
<dc:modified>2024-08-30</dc:modified>
<dc:contributor>Expert Participation</dc:contributor>
<dct:valid>2024-06-12</dct:valid>
<dc:description>This Order authorises National Grid to undertake works to the national electricity transmission system between the existing substation at Monk Fryston to the existing substation at Osbaldwick. The proposed development is required to provide sufficient transmission capacity to enable the connection of new electricity generation projects in the region, and to carry out all associated works.</dc:description>
<ukm:SecondaryMetadata>
<ukm:DocumentClassification>
<ukm:DocumentCategory Value="secondary"/>
<ukm:DocumentMainType Value="UnitedKingdomStatutoryInstrument"/>
<ukm:DocumentStatus Value="revised"/>
<ukm:DocumentMinorType Value="order"/>
...</ukm:DocumentClassification>
<ukm:Year Value="2024"/>
<ukm:Number Value="393"/>
<ukm:Made Date="2024-03-14"/>
<ukm:ComingIntoForce>
<ukm:DateTime Date="2024-04-05"/>
...</ukm:ComingIntoForce>
<ukm:ISBN Value="9780348259490"/>
...</ukm:SecondaryMetadata>
<ukm:Alternatives>
<ukm:Alternative URI="http://www.legislation.gov.uk/uksi/2024/393/pdfs/uksi_20240393_en.pdf" Date="2024-03-20" Size="834753" Print="true"/>
...</ukm:Alternatives>
<ukm:Statistics>
<ukm:TotalParagraphs Value="278"/>
<ukm:BodyParagraphs Value="54"/>
<ukm:ScheduleParagraphs Value="224"/>
<ukm:AttachmentParagraphs Value="0"/>
<ukm:TotalImages Value="0"/>
...</ukm:Statistics>