23.Compulsory acquisition of land – incorporation of the mineral code
24.Time limit for exercise of authority to acquire land and rights compulsorily
27.Extinguishment of private rights and restrictive covenants relating to apparatus removed from land subject to temporary possession
39.Temporary use of land for maintaining the authorised development
PART 6 MISCELLANEOUS AND GENERAL
SCHEDULES
STREETS, CYCLE TRACKS OR PUBLIC RIGHTS OF WAY TO BE TEMPORARILY CLOSED
MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
2.(1) Without limitation on the scope of paragraph 1, the...
4.For section 7 of the 1965 Act (measure of compensation)...
6.The following provisions of the 1965 Act (which state the...
8.Section 20 of the 1965 Act (protection for interests of...
9.Section 22 of the 1965 Act (protection of acquiring authority’s...
LAND IN WHICH ONLY NEW RIGHTS AND RESTRICTIVE COVENANTS ETC. MAY BE ACQUIRED
PART 1 PROTECTION FOR ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
PART 2 PROTECTION FOR OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
PART 4 FOR THE PROTECTION OF RAILWAY INTERESTS
26.The provisions of this Part of this Schedule have effect,...
27.In this Part of this Schedule— “asset protection agreement” means...
28.(1) Where under this Part of this Schedule Network Rail...
29.(1) Subject to sub-paragraph (2) the undertaker must not exercise...
30.(1) The undertaker must before commencing construction of any specified...
32.The undertaker must— (a) at all times afford reasonable facilities...
33.Network Rail must at all times afford reasonable facilities to...
34.(1) If any permanent or temporary alterations or additions to...
35.The undertaker must repay to Network Rail all reasonable fees,...
36.(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
38.The undertaker must not provide any illumination or illuminated sign...
39.Any additional expenses which Network Rail may reasonably incur in...
40.(1) The undertaker must pay to Network Rail all reasonable...
43.The undertaker and Network Rail may, subject in the case...
44.Nothing in this Order, or in any enactment incorporated with...
45.The undertaker must give written notice to Network Rail if...
PART 5 FOR THE PROTECTION OF NORTHERN POWERGRID
47.For the protection of Northern Powergrid the following provisions have...
49.This Part of this Schedule does not apply to apparatus...
50.Regardless of any provision in this Order or anything shown...
52.(1) Where, in accordance with the provisions of this Part...
53.(1) Not less than 48 days before starting the execution...
54.(1) Subject to the following provisions of this paragraph, the...
55.(1) Subject to sub-paragraphs (2) and (3), if by reason...
56.Nothing in this Part of this Schedule affects the provisions...
57.Where in consequence of the proposed construction of any of...
58.If in consequence of an agreement reached in accordance with...
59.The plans submitted to Northern Powergrid by the undertaker pursuant...
60.Where practicable, the undertaker and Northern Powergrid will make reasonable...
PART 7 FOR THE PROTECTION OF NATIONAL GAS TRANSMISSION PLC AS GAS UNDERTAKER
PART 8 FOR THE PROTECTION OF NORTHERN GAS NETWORK’S APPARATUS