The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024

Site specific mitigation scheme

19.—(1) No part of Work No. 10 that affects the Travellers’ Encampment may commence until a scheme to mitigate the impacts of construction activities arising from those works, including noise, dust, vibration, and visual effects (including from lighting), has been submitted to and approved in writing by the relevant planning authority.

(2) The scheme referred to in sub-paragraph (1) must include the approach to liaison for the Travellers’ Encampment during the construction period.

(3) In the event that significant effects of notice or vibration are identified on receptors SEL16 and SEL17 as shown within the Noise and Vibration Figures (Document 5.4.14), the scheme referred to in sub-paragraph (1) must include mitigation measures to reduce the significant effects as far as practicable.

(4) The construction works for that part of Work No. 10 which affects the Travellers’ Encampment must be carried out in accordance with the approved scheme referred to in sub-paragraph (1) above, unless otherwise agreed with the relevant planning authority.