- Latest available (Revised)
- Original (As made)
This is the original version (as it was originally made).
13.—(1) The undertaker may, in connection with the carrying out of the authorised development, temporarily restrict, prevent use of or close each of the public rights of way specified in column (2) of Part 1 of Schedule 6 (public rights of way to be temporarily restricted) to the extent specified in column (3), by reference to the numbered points shown on the access and rights of way plans.
(2) The public rights of way specified in Part 1 of Schedule 6 (public rights of way to be temporarily restricted) must not be temporarily closed under this article unless an alternative public right of way is first provided by the undertaker to the reasonable satisfaction of the relevant local highway authority.
(3) The relevant diversion route provided under paragraph (2) will be subsequently maintained by the undertaker until the re-opening of the relevant public right of way specified in paragraph (1).
(4) Any person who suffers loss by the suspension of any private right of way under this article is entitled to compensation to be determined as if it were a dispute under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
(5) If a street authority which receives an application for confirmation that an alternative public right of way is satisfactory under paragraph (2) fails to notify the undertaker of its decision before the end of the period of 42 days beginning with the date on which the application was received by that street authority, it is deemed to have granted consent.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: