112. The provisions of this Part have effect unless otherwise agreed in writing between the undertaker and CF Fertilisers.
113. In this Part—
“construction” includes execution, placing, alteration and reconstruction and “construct” and “constructed” have corresponding meanings;
“CF Fertilisers” means CF Fertilisers UK Limited (company number 03455690), whose registered office is at Head Office Building, Ince, Chester, Cheshire, United Kingdom, CH2 4LB and any associated company of CF Fertilisers UK Limited which holds relevant property;
“relevant property” means—
any land, works, apparatus and equipment belonging to CF Fertilisers; and
any easement or other property interest held or used by CF Fertilisers or a tenant or licensee of CF Fertilisers for the purposes of such land, works, apparatus or equipment.
114. Regardless of any provision of this Order or anything shown on the land plans, the undertaker-
(a)must not extinguish any rights of access to the relevant property granted to CF Fertilisers otherwise than by agreement (both parties acting reasonably);
(b)must provide a minimum of two working days notification prior to entry to the relevant property; and
(c)must keep any existing roads used for access to the relevant property by CF Fertilisers clear from obstruction as far as reasonably practicable.
115. Nothing in this Part imposes any liability on the undertaker with respect to any damage, costs, expenses or loss attributable to the negligence of CF Fertilisers or its servants, contractors or agents or any liability on CF Fertilisers with respect of any damage, costs, expenses or loss attributable to the negligence of the undertaker or its servants, contractors or agents.
116. The undertaker must pay to CF Fertilisers all reasonable and proper costs, charges, damages and expenses not otherwise provided for in this Part of this Schedule (but always excluding any consequential loss or indirect loss) which may be reasonably incurred by CF Fertilisers in respect of any damage caused to or additional maintenance required to relevant property as a direct result of the construction of the authorised development.
117.—(1) Notwithstanding anything to the contrary in this Part of this Schedule, the undertaker shall not be liable for any consequential loss or indirect loss suffered by CF Fertilisers as a result of the construction of the authorised development and CF Fertilisers shall not be liable for any consequential loss or indirect loss suffered by the undertaker as a result of the construction of the authorised development.
(2) CF Fertilisers must-
(a)give the undertaker reasonable written notice of any such sums referred to in paragraph 116 as soon as reasonably possible after CF Fertilisers become aware of the same;
(b)not make any offers to settle claims or demands without the prior consent of the undertaker;
(c)take all reasonable steps to mitigate any liabilities; and
(d)keep the undertaker informed and have regard to the undertaker’s representations in relation to any such sums referred to in paragraph 116.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: