SCHEDULE 13Marine Licence 4: Dudgeon Extension Project Offshore Transmission – Work Nos 3B to 7B or 3C to 7C

PART 2Conditions

Cables and cable protection

Site Integrity Plan

14.—(1) Each programme, statement, plan, protocol or scheme required to be approved under condition 12 must be submitted for approval at least four months before the intended commencement of licensed activities, except where otherwise stated or unless otherwise agreed in writing by the MMO.

(2) The MMO must determine an application for approval made under conditions 12 and 13 within a period of four months commencing on the date the application is received by the MMO, unless otherwise agreed in writing with the undertaker.

(3) The licensed activities must be carried out in accordance with the plans, protocols, statements, schemes and details approved under conditions 12 and 13, unless otherwise agreed in writing by the MMO.