The Drax Power Station Bioenergy with Carbon Capture and Storage Extension Order 2024

Construction traffic management plan

15.—(1) No part of numbered works 1, 2, 3 and 8 of the authorised development is to commence, until a construction traffic management plan has, for that part, been submitted to and, after consultation with National Highways and the highway authority, approved by the relevant planning authority.

(2) The plan submitted and approved pursuant to sub-paragraph (1) must be substantially in accordance with the relevant part of the outline construction traffic management plan.

(3) Notices must be erected and maintained by the undertaker throughout the period of construction at every entrance to and exit from the construction site, indicating to drivers the approved routes for traffic entering and leaving the construction site.

(4) The plan must be implemented and maintained as approved throughout the construction of the authorised development.