Highway accesses during construction9

1

Construction of each of the accesses listed in Schedule 7 (access to works) must not commence until details of the siting, design and layout (including visibility splays and construction specification) of that access, and in respect of the accesses listed in Part 1 of Schedule 7 only, the means of reinstating the temporary means of access after construction, has been submitted to and, after consultation with the highway authority, approved by the relevant planning authority.

2

The highway accesses approved pursuant to sub-paragraph (1) must be constructed in accordance with the approved details.