The Network Rail (Cambridge Re-Signalling) Order 2024

  1. Introductory Text

  2. PART 1 PRELIMINARY

    1. 1.Citation and commencement

    2. 2.Interpretation

  3. PART 2 STREETS

    1. 3.Stopping up of streets

  4. PART 3 ACQUISITION AND POSSESSION OF LAND

    1. 4.Power to acquire land

    2. 5.Application of Part 1 of the 1965 Act

    3. 6.Application of the 1981 Act

    4. 7.Power to acquire new rights

    5. 8.Temporary use of land in connection with the development

    6. 9.Temporary use of land for oversailing and access

    7. 10.Disregard of certain interests and improvements

    8. 11.Extinction or suspension of private rights of way

    9. 12.Time limit for exercise of powers of acquisition

  5. PART 4 MISCELLANEOUS AND GENERAL

    1. 13.Statutory undertakers, etc.

    2. 14.Certification of plans, etc.

    3. 15.Service of notices

    4. 16.No double recovery

    5. 17.Arbitration

  6. Signature

  7. SCHEDULES

    1. SCHEDULE 1

      STREETS TO BE STOPPED UP

    2. SCHEDULE 2

      LAND IN WHICH ONLY NEW RIGHTS ETC., MAY BE ACQUIRED

    3. SCHEDULE 3

      LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

    4. SCHEDULE 4

      LAND WHICH MAY BE USED FOR OVERSAILING AND ACCESS

    5. SCHEDULE 5

      MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS

      1. Compensation enactments

        1. 1.The enactments for the time being in force with respect...

        2. 2.(1) Without limitation on the scope of paragraph 1, the...

        3. 3.(1) Without limitation on the scope of paragraph 1, the...

      2. Application of Part 1 of the 1965 Act

        1. 4.Part 1 (compulsory purchase under Acquisition of Land Act of...

        2. 5.(1) The modifications referred to in paragraph 4(a) are as...

    6. SCHEDULE 6

      APPARATUS OF STATUTORY UNDERTAKERS, ETC. IN STOPPED UP STREETS

      1. 1.Where a street it stopped up under article 3 (stopping...

      2. 2.Where a street is stopped up under article 3 any...

      3. 3.Subject to the following provisions of this Schedule, Network Rail...

      4. 4.If in the course of execution of relocation works under...

      5. 5.For the purposes of paragraph 4— (a) an extension of...

      6. 6.An amount which, apart from this paragraph, would be payable...

      7. 7.Paragraphs 3 to 6 do not apply where the authorised...

      8. 8.In this Schedule— “apparatus” has the same meaning as in...

  8. Explanatory Note