Search Legislation

The M3 Junction 9 Development Consent Order 2024

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening OptionsExpand opening options

Changes over time for: Paragraph 38

 Help about opening options

Alternative versions:

Status:

This version of this provision is prospective. Help about Status

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to The M3 Junction 9 Development Consent Order 2024. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Prospective

Timing of works and service of noticesE+W

38.—(1) Subject to sub-paragraph (2), any specified work, and all protective works required by the Agency under paragraph 37, must be constructed—

(a)without unreasonable delay in accordance with the plans approved under this Part of this Schedule; and

(b)to the reasonable satisfaction of the Agency,

and the Agency is entitled by its officer to watch and inspect the construction of such works.

(2) The undertaker must give to the Agency not less than 14 days’ notice in writing of its intention to commence construction of any specified work and notice in writing of its completion not later than 7 days after the date on which it is completed.

(3) If the Agency reasonably requires, the undertaker must construct all or part of the protective works so that they are in place prior to the construction of any specified work to which the protective works relate.

Commencement Information

I1Sch. 10 para. 38 in force at 9.10.2024 (as amended by S.I. 2024/1020, Sch.), see art. 1