SCHEDULE 2REQUIREMENTS
PART 2PROCEDURE FOR DISCHARGE OF REQUIREMENTS
Applications made under requirements
17.
(1)
Where an application has been made to the Secretary of State for any consent, agreement or approval required by a requirement (including agreement or approval in respect of part of a requirement) included in this Order, the Secretary of State must give notice to the undertaker of the decision on the application within a period of 8 weeks beginning with—
(a)
the day immediately following that on which the application is received by the Secretary of State;
(b)
the day immediately following that on which further information has been supplied by the undertaker under paragraph 18 (further information); or
(c)
such longer period as may be agreed between the parties.
(2)
(3)
Where—
(a)
an application has been made to the Secretary of State for any consent, agreement or approval required by a requirement included in this Order;
(b)
the Secretary of State does not determine such application within the period set out in sub-paragraph (1); and
(c)
the application is accompanied by a report referred to in paragraph 4 (details of consultation) stating that, in the view of a body required to be consulted by the undertaker under the requirement in question, the subject matter of the application is likely to give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement,
then the application is taken to have been refused by the Secretary of State at the end of that period.