
Print Options
PrintThe Whole
Instrument
PrintThe Whole
Schedule
PrintThis
Section
only
Changes over time for: Paragraph 18


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 03/08/2024.
Changes to legislation:
There are currently no known outstanding effects for the The Mallard Pass Solar Farm Order 2024, Paragraph 18.

Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Decommissioning and restorationE+W
18.—(1) Decommissioning works must commence no later than 60 years following the date of the final commissioning of the first phase of Work No. 1, as notified by the undertaker pursuant to requirement 3(4) (phasing of the authorised development and date of final commissioning).
(2) Prior to the commencement of any decommissioning works and prior to the end of the timeframes established pursuant to the decommissioning timing provisions in a detailed operational environmental management plan approved pursuant to requirement 12, for any part of the authorised development, the undertaker must submit to the relevant planning authority for that part (or both relevant planning authorities where that part falls within the administrative areas of both the District of South Kesteven and the County of Rutland) for approval, in consultation with the Environment Agency and Lincolnshire County Council, a decommissioning environmental management plan for that part.
(3) The plans submitted and approved under sub-paragraph (2) must be substantially in accordance with the relevant part of the outline decommissioning environmental management plan.
(4) No decommissioning works must be carried out until the relevant planning authority or both relevant planning authorities (as applicable) has/have approved the plan submitted in relation to such works.
(5) The plan submitted to and approved pursuant to sub-paragraph (2) must be implemented as approved for the works required to decommission that phase of the authorised development.
(6) This requirement is without prejudice to any other consents or permissions which may be required to decommission any part of the authorised development.
Back to top