As built drawingsE+W

184.  As soon as reasonably practicable following the completion of the construction of the authorised development, the undertaker must provide to the Canal & River Trust as built drawings of any specified works in a form and scale to be agreed between the undertaker and the Canal & River Trust to show the position of those works in relation to the waterway.

Commencement Information

I1Sch. 15 para. 184 in force at 27.9.2024, see art. 1