PART 14FOR THE PROTECTION OF UNIPER UK LIMITED
186. For the protection of Uniper as referred to in this Part of this Schedule the following provisions will, unless otherwise agreed in writing between the undertaker and Uniper, have effect.
187. In this Part of this Schedule—
“acceptable credit provider” means a bank or financial institution with a credit rating that is not lower than—
(a)
“A-” if the rating is assigned by Standard & Poor’s Ratings Group or Fitch Ratings; and
(b)
“A3” if the rating is assigned by Moody’s Investors Services Inc.;
“acceptable insurance” means a third party liability insurance effected and maintained by the undertaker or its contractor with a limit of indemnity of not less than £50,000,000 (fifty million pounds) per occurrence or series of occurrences arising out of one event or such lower amount as approved by Uniper, whether arising pursuant to the undertaker or any person on its behalf, arranged with an internationally recognised insurer of repute operating in the London and worldwide insurance market underwriters whose security/credit rating meets the same requirements as an “acceptable credit provider” (including any replacement insurance pursuant to paragraph 195), such insurance to be maintained for the construction and operational period of that part or parts of the authorised development which constitute specified works and such policy must include (but without limitation)—
(a)
a waiver of subrogation and an indemnity to principal clause in favour of Uniper; and
(b)
contractors’ pollution liability for third party property damage and third party bodily damage arising from pollution, contamination or environmental harm with cover of £10,000,000 (ten million pounds) per event or £20,000,000 (twenty million pounds) in aggregate;
“acceptable security” means either—
(a)
a parent company guarantee from a parent company in favour of Uniper to cover the undertaker’s liability to Uniper to a cap of not less than £10,000,000 (ten million pounds) per asset per event up to a total liability cap of £25,000,000 (twenty-five million pounds) (in a form reasonably satisfactory to Uniper and where required by Uniper, accompanied by a legal opinion confirming the due capacity and authorisation of the parent company to enter into and be bound by the terms of such guarantee) including any replacement parent company pursuant to paragraph 195(6); or
(b)
a bank bond or letter of credit from an acceptable credit provider in favour of Uniper to cover the undertaker’s liability to Uniper for an amount of not less than £10,000,000 (ten million pounds) per asset per event up to a total liability cap of £25,000,000 (twenty-five million pounds) (in a form reasonably satisfactory to Uniper) which includes any replacement bank bond or letter of credit pursuant to paragraph 195(6);
“alternative apparatus” means alternative apparatus to the satisfaction of Uniper to enable Uniper to fulfil its functions in a manner no less efficient than previously;
“apparatus” means—
(a)
any fixed and moveable items, which forms, or may form, part of Uniper’s system, including cavities, chambers, pipelines, valves, ventilators, pumps, compressors, pumping or compression systems, control systems and any associated cables (including high voltage, low voltage and datacoms) and any equipment in which electrical conductors are used, supported, or otherwise form, or may form, part of the system, cathodic protection systems, roads, compounds and equipment owned by Uniper; or
(b)
any other equipment or apparatus belonging to or maintained by Uniper or apparatus and such other equipment or apparatus constructed that becomes operational for the purposes of Uniper’s functions including any structure in which equipment or apparatus is, or will be, lodged or which gives, or will give, access to apparatus; or
(c)
any replacement equipment or apparatus as required or determined by Uniper;
“applicable law” means any applicable legislation, statutes, directives, regulations (including safety regulations), judgments, decisions, decrees, orders and other legislative measures or decisions having the force of law, treaties, conventions and other agreements between states, or between states and the European Union or other supranational bodies, rules of common law, customary law and equity and all civil or other codes and all other laws of, or having effect in, any jurisdiction from time to time in each case to the extent the same is legally binding upon the relevant person;
“as-built records” means each as-built record or document prepared by the undertaker or delivered to the undertaker by its subcontractors or any other person carrying out the specified works;
“authorised development” has the same meaning as in article 2 of this Order and includes any associated development authorised by this Order and for the purposes of this Part of this Schedule includes the use and maintenance of the authorised works and construction of any works authorised by this Part of this Schedule;
“commence” has the same meaning as in article 2 of this Order and “commencement” will be construed to have the same meaning save that for the purposes of this Part of this Schedule the terms “commence” and “commencement” include operations consisting of ecological or archaeological investigations, investigations for the purpose of assessing and monitoring ground conditions and levels (including drilling and making trial or bore holes), remedial work in respect of any pollution, contamination or other adverse ground conditions, erection of any temporary means of enclosure, receipt and erection of construction plant and equipment, diversion and laying of underground apparatus (including cables) and site clearance (including removal of vegetation) or any other activities being undertaken under, over, across, along or upon the apparatus or alternative apparatus in land;
“confidential information” means information exchanged during the negotiation or performance of this Part of this Schedule, which is identified in writing by the furnishing party as being confidential at the time of disclosure to the other party;
“deed of consent” means a deed of consent, crossing or proximity agreement, deed of easement, deed of variation or new deed of grant agreed between the parties;
“emergency works” has the meaning given to it in section 52 of the 1991 Act;
“good industry practice” means exercising the degree of skill, diligence, prudence, foresight and care reasonably expected of a skilled and experienced solar developer, which includes obtaining all necessary permits and compliance with any safety rules;
“functions” includes powers and duties;
“in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over, across, along or upon such land;
“including” or “include” are to be construed without limitation, and such general words are not to be given a restrictive meaning by reason of the fact that they are followed by particular examples intended to be embraced by the general words and references to “such as” or “for example” must be construed accordingly;
“insolvency related event” means, in respect of any person, any step, process, application, filing in court, order, proceeding, notice or appointment is taken or made by or in respect of such person in relation to the Banking Act 2009 special resolution regime or for a moratorium, composition, compromise or arrangement with creditors, administration, liquidation (other than for the purposes of amalgamation or reconstruction), dissolution, receivership (administrative or otherwise), distress (or the taking control of goods procedure set out in the Tribunals, Courts and Enforcement Act 2007) or execution in any jurisdiction or such person becomes insolvent or is unable or is deemed unable to pay its debts, suspends making payments on its debts, as they fall due in accordance with the law of any application jurisdiction;
“maintain” and “maintenance” include the ability and right to do any of the following in relation to any apparatus or alternative apparatus of Uniper including retain, lay, construct, use, maintain, repair, protect, access, alter, inspect, renew, replace, enlarge, decommission or remove the apparatus or alternative apparatus;
“parent company” means—
(a)
a parent company of the undertaker acceptable to and which must have been approved by Uniper acting reasonably; or
(b)
where a parent company is subject to an insolvency related event, a replacement parent company approved by Uniper acting reasonably;
“plan” or “plans” include all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and mitigation measures (including but not limited to integrity reports), earthing philosophies, proposed land and road crossings and other documents that are reasonably necessary properly and sufficiently to describe and assess the works to be executed;
“representative” means Uniper’s directors, officers, employees, agents, consultants and advisers;
“specified works” means any of the authorised development or activities undertaken in association with the authorised development which—
(a)
will or may be situated over, under, across, along, upon or within 15 metres measured in any direction of any apparatus, excluding any high pressure pipelines to which paragraph (b) below applies;
(b)
will or may be situated over, under, across, along, upon or within 50 metres measured in any direction of any high pressure pipeline; or
(c)
may in any way adversely affect any apparatus the removal of which has not been required by the undertaker under paragraph 192(2) or otherwise; and
“Uniper” means Uniper UK Limited incorporated in England with company number 2796628 and whose registered office is at Compton House 2300 The Crescent, Birmingham Business Park, Birmingham, England, B37 7YE and for the purposes of this Part of this Schedule is a “statutory undertaker”.
188. Except for paragraphs 189 (apparatus of Uniper in streets subject to temporary prohibition or restriction of use and public rights of way), 192 (retained apparatus), 193 (removal or replacement of apparatus), 194 (expenses) and 195 (indemnity) of this Part of this Schedule which will apply in respect of the exercise of all or any powers under the Order affecting the rights and apparatus of Uniper, the other provisions of this Part of this Schedule do not apply to apparatus in respect of which the relations between the undertaker and Uniper are regulated by the provisions of Part 3 of the 1991 Act.
Apparatus of Uniper in streets subject to temporary prohibition or restriction of use and public rights of way
189. Regardless of temporary prohibition or restriction of use or diversion of any street or public right of way under the powers of article 11 (temporary prohibition or restriction of use of streets and public rights of way), Uniper will be at liberty at all times to take all necessary access across any such street or public right of way and to execute and do all such works and things in, upon or under any such street or public right of way as it would have been entitled to do immediately before such temporary prohibition or restriction of use or diversion in respect of any apparatus which at the time of the prohibition or restriction of use or diversion was in that street or public right of way.
Protective works to buildings
190. The undertaker, in the case of the powers conferred by article 18 (protective works to buildings), must exercise those powers in accordance with paragraph 192 (retained apparatus) so as not to obstruct or render less convenient the access to any apparatus or alternative apparatus.
Acquisition of land
191.—(1) Regardless of the temporary prohibition or restriction of use of streets under the powers conferred by article 11 (temporary prohibition or restriction of use of streets and public rights of way), Uniper is at liberty at all times to take all necessary access across any such street and to execute and do all such works and things in, upon or under any such street as may be reasonably necessary or desirable to enable it to maintain any apparatus which at the time of the prohibition or restriction was in that street.
(2) Regardless of any provision in this Order or anything shown on the land plans, the undertaker must not acquire any apparatus otherwise than by agreement.
Retained apparatus
192.—(1) Not less than 56 days before the commencement of any specified works the undertaker must submit to Uniper at the address stated in paragraph 200, a plan in respect of those works.
(2) The plan to be submitted to Uniper under sub-paragraph (1) must include all comprehensive risk assessments (including any quantitative risk assessments) and any method statement describing—
(a)the exact position of the works;
(b)the level at which these are proposed to be constructed or renewed;
(c)the manner of their construction or renewal including details of excavation, positioning of plant etc;
(d)the position of all apparatus;
(e)by way of detailed drawings, every alteration proposed to be made to or close to any such apparatus;
(f)any changes to the land drainage systems, temporary crossing designs, traffic management plans, health and safety management plans, emergency response plans, planned changes or rerouting of any assets and their corresponding design codes, earth schedules and earthing risk assessments;
(g)any recommendations and/or mitigation measures to avoid interference with, or loss or damage to the apparatus (including damage caused by passing over the apparatus by heavy construction machinery) and related remedies should such mitigation measures fail;
(h)any intended maintenance regimes; and
(i)a programme of the works, including any proposed start dates and the anticipated duration of the works.
(3) The undertaker may not commence any works to which sub-paragraphs (1) and (2) apply until Uniper has given written approval of the plan so submitted and the undertaker and Uniper have used reasonable endeavours to carry out a joint site walk in the period 4 weeks before commencement of the works.
(4) The fact that any work or thing has been executed or done by the undertaker in accordance with a plan approved or deemed to be approved by Uniper, or to its satisfaction, or in accordance with any directions or award of an arbitrator, does not relieve the undertaker from any liability under this Part of this Schedule.
(5) Any approval of Uniper required under sub-paragraph (3)—
(a)may be given subject to reasonable conditions for any purpose mentioned in sub- paragraphs (6) or (10); and
(b)must not be unreasonably withheld or delayed.
(6) In relation to any work to which sub-paragraphs (1) or (2) apply, the undertaker will provide any additional information or documentation as reasonably requested by Uniper and Uniper may require modifications to be made to the plans as may be reasonably necessary for the purpose of securing its apparatus against interference or risk of damage or for the purpose of providing or securing proper and convenient means of access to any apparatus.
(7) Works to which this paragraph applies must only be executed in accordance with the plan, submitted under sub-paragraphs (1) and (2) or as relevant sub-paragraphs (5) and (6), as approved or as amended from time to time by agreement between the undertaker and Uniper and in accordance with all conditions imposed under sub-paragraph (5)(a) by Uniper for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and Uniper (or its representative) will be entitled to attend any meetings related to the specified works and watch, monitor and inspect the execution of those works.
(8) If, during the carrying out of the authorised development, any aspect of the works pose a risk of interference with or loss or damage to the apparatus, the undertaker will immediately notify Uniper, inwriting and submit a revised plan in respect of the affected works to Uniper for approval, and the provisions of this paragraph will apply to, and in respect of, the revised plan.
(9) If Uniper (or its representative) identifies a potential risk of interference with or loss or damage to the apparatus while watching, monitoring or inspecting the specified works, then Uniper (or its representative) may request suspension of such works, and the undertaker will then submit a revised plan in respect of the affected works to Uniper for approval, and the provisions of this paragraph will apply to, and in respect of, the revised plan, and a failure or delay of Uniper (or its representative) in exercising this right, or the undertaker’s failure to suspend the specified works upon request by Uniper (or its representative), will not relieve the undertaker of its responsibility for any interference with, loss of, or damage to the apparatus.
(10) Where Uniper requires any protective works to be carried out by itself or by the undertaker (whether of a temporary or permanent nature) such protective works, inclusive of any measures or schemes required and approved as part of the plan approved pursuant to this paragraph, must be carried out to Uniper’s satisfaction (acting reasonably) prior to the commencement.
(11) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of the authorised development, a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph will apply to and in respect of the new plan;
(12) The undertaker will not be required to comply with sub-paragraph (1) where it needs to carry out emergency works, provided that—
(a)in respect of danger to persons it must give to Uniper notice as soon as is reasonably practicable by calling Uniper’s emergency telephone line on 0800 389 4795 or such other telephone number notified by Uniper to the undertaker in writing; and
(b)in respect of danger to property it shall notify Uniper in accordance with point (a), before any emergency works are commenced by or on behalf of the undertaker,
and, in each case, as soon as is reasonably practicable give to Uniper a plan of those works and must—
(a)comply with sub-paragraphs (6) to (10) insofar as is reasonably practicable in the circumstances; and
(b)comply with sub-paragraph (13) at all times.
(13) At all times when carrying out any works authorised under the Order the undertaker must comply with, and use reasonable endeavours to procure compliance by any party acting on its behalf with, all applicable law and good industry practice. The undertaker must procure that any party carrying out any works on the land on its behalf has knowledge of the apparatus, its location (including as illustrated by a site map) and procure that the obligations contained in this Part of this Schedule are adhered to by such parties working on the land on its behalf.
(14) The undertaker must prepare and keep up to date a complete set of red-lined as-built records of the execution of the specified works, showing the exact as-built locations, sizes and details of such works as executed and the undertaker must submit the as-built records to Uniper no later than five working days after the completion of the specified works and Uniper may specify the number of copies of any as-built records acting reasonably.
Removal or replacement of apparatus
193.—(1) The undertaker is not permitted to remove, move or replace any apparatus in land without the prior written consent of Uniper, such consent not to be unreasonably withheld or delayed.
(2) If, in the exercise of the powers conferred by this Order, the undertaker has exercised its compulsory purchase powers to acquire any interest in or possesses temporarily any Order land in which any apparatus is placed and has the power to move, replace or remove that apparatus, it may not do so under this Part of this Schedule and any right of Uniper to maintain that apparatus in that land may not be extinguished until alternative apparatus has been constructed, and is in operation to the reasonable satisfaction of Uniper in accordance with sub-paragraphs (3) to (7) inclusive.
(3) If, for the purpose of executing any specified works in, on, under or over any land held, appropriated or used under this Order pursuant to exercising its compulsory purchase powers the undertaker requires the replacement or removal of any apparatus placed in that land it must give to Uniper no less than 56 days advance written notice of that requirement, together with a plan of the work proposed, and where applicable, the proposed replacement apparatus or the position of any alternative apparatus to be provided or constructed and in that case provided that where—
(a)the undertaker requires the replacement of any apparatus placed in that land, it must be replaced with identical apparatus, provided that if identical apparatus is not available, it may not be replaced with any apparatus that is less advanced than the apparatus being replaced and must either be—
(i)replaced with apparatus on a similar or equivalent basis (i.e. like-for-like basis); or
(ii)where it cannot be replaced on a similar or equivalent basis, then it must be replaced with enhanced apparatus no less advanced than the apparatus being replaced; and
(b)the undertaker requires the removal of any apparatus placed in that land (or if in consequence of the exercise of any of the powers conferred by this Order Uniper reasonably needs to remove any of its apparatus), Uniper must, subject to sub-paragraph (5), secure any necessary consents for the alternative apparatus and afford to Uniper to its satisfaction the necessary facilities and rights for the construction of alternative apparatus in other land of or land secured by Uniper and subsequently for the maintenance of that apparatus.
(4) Prior to any removal or any replacement of the apparatus pursuant to this paragraph, the parties must agree the value attributable to such apparatus or alternative apparatus and, prior to any replacement or removal, if such value cannot be agreed between the parties, such value will be determined in accordance with paragraph 199 (arbitration).
(5) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of or land secured by the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (3), in the land in which the alternative apparatus or part of such apparatus is to be constructed, the undertaker must take all steps required in the circumstances to assist Uniper to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed.
(6) Any alternative apparatus to be constructed in land of or land secured by the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between the undertaker and Uniper.
(7) Uniper must, after the alternative apparatus to be provided or constructed has been agreed, and subject to a written agreement having been entered into between the parties and the grant to Uniper of any such facilities and rights as are referred to in sub-paragraph (3) or (5), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this Part of this Schedule.
Expenses
194.—(1) Subject to the following provisions of this paragraph, the undertaker must pay to Uniper within 30 days of receipt of an invoice, all charges, costs and expenses incurred, or reasonably anticipated to be incurred, by Uniper in, or in connection with, the inspection, removal, relaying or replacing, alteration, repair, remediation or restoration of or protection of any apparatus or alternative apparatus or the construction of any new or alternative apparatus which may be required in consequence of the execution of any powers conferred on the undertaker, pursuant to the Order (including in the execution of any authorised development as is referred to in this Part of this Schedule) including without limitation—
(a)in connection with the cost of the carrying out of any assessment of Uniper’s apparatus under P.S.R 1996 and G.S.M.R reasonably necessary as a consequence of the authorised development;
(b)implementing any mitigation measures required as a result of any assessment referred to in point (a) reasonably necessary as a consequence of the authorised development;
(c)the approval of plans;
(d)the carrying out of protective works, plus a capitalised sum to cover the cost of maintaining and renewing permanent protective works; and
(e)the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to in this Part of this Schedule.
(2) For the purposes of calculating the sums payable pursuant to sub-paragraph 1 above, in the case of the replacement or removal of apparatus, the following applies—
(a)Where apparatus is removed under the provisions of this Part of this Schedule and which will not be re-used as part of the apparatus or alternative apparatus, there will be excluded from any sum payable under sub-paragraph (1) the value of the apparatus being removed; and
(b)subject to paragraph 193(3)(a), when replacing existing apparatus, there will be deducted from any sum payable under sub-paragraph (1) the value of that apparatus being removed under the provisions of this Part of this Schedule and which is not re-used as part of the apparatus or alternative apparatus, except that the value of any apparatus or alternative apparatus used to replace the apparatus being removed will be included in the sum payable under sub-paragraph (1), such value being agreed between the parties (or as determined in accordance with paragraph 199 (arbitration)) prior to any removal or replacement of the apparatus,
provided that, in each case, all charges, costs and expenses reasonably incurred, or reasonably anticipated to be incurred, by Uniper in, or in connection with the works required for the removal or replacement of such apparatus will be included in the sum payable under sub-paragraph (1).
(3) If, in accordance with sub-paragraph (2), any existing apparatus is replaced with enhanced apparatus where the undertaker’s consent has not been obtained by Uniper (or where disputed in accordance with paragraph 199 (arbitration), decided not to be necessary), then, if the construction expenses for this replacement surpass the construction expenses that would have been paid for similar or equivalent apparatus then any excess costs will be borne by Uniper, except that where it is not possible in the circumstances to obtain similar or equivalent apparatus, full costs will be payable by the undertaker.
(4) Any amount which apart from this sub-paragraph would be payable to Uniper in respect of works by virtue of sub-paragraph (1) will, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on Uniper any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.
Indemnity
195.—(1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any of the authorised development or in consequence of the construction, use, maintenance or failure of any of the authorised development by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by them) in the course of carrying out such works, including without limitation works carried out by the undertaker under this Part of this Schedule or any subsidence resulting from any of these works, any loss or damage is caused to any apparatus, alternative apparatus or property of Uniper, or there is any interruption in any services provided, or in the supply of any goods, or in the use of the apparatus or alternative apparatus (as applicable) by Uniper, the undertaker must—
(a)bear and pay the costs reasonably and properly incurred by Uniper in making good such loss or damage or in restoring the supply or its use;
(b)make compensation to Uniper for any other expenses, loss, damages, penalty or costs incurred by Uniper, by reason or in consequence of any such loss, damage or interruption; and
(c)indemnify Uniper for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from Uniper, by reason or in consequence of any such damage or interruption or Uniper becoming liable to any third party (an “indemnity claim”).
(2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to—
(a)any damage or interruption to the extent that it is attributable to the act, neglect or default of Uniper or its representatives; or
(b)any indirect or consequential loss of any third party (including but not limited to loss of use, revenue, profit, contract, production, increased cost of working or business interruption) arising from any such damage or interruption which is not reasonably foreseeable.
(3) Uniper must give the undertaker reasonable notice of an indemnity claim and no settlement or compromise is to be made that is prejudicial to the undertaker without the consent of the undertaker (not to be unreasonably withheld) which, if it withholds such consent, it will assume the sole conduct of the indemnity claim, provided that if the undertaker does not assume the sole conduct of the indemnity claim within 30 days of the indemnified claim being notified to it, Uniper, or a person designated by Uniper, may conduct the indemnity claim in such manner as it may deem appropriate and the undertaker will indemnify Uniper for any costs and expenses incurred in connection with defending any such indemnity claim.
(4) The undertaker will give assistance to Uniper, as requested, in connection with an indemnity claim (including circumstances where Uniper reasonably believes may give rise to an action, claim or demand by a third party).
(5) The undertaker undertakes not to commence construction (and not to permit the commencement of such construction) of the authorised development on any land owned by Uniper or in respect of which Uniper has an easement, wayleave or lease for its apparatus or any other interest or to carry out any works within 15 metres of Uniper’s apparatus (except in respect of any high pressure pipelines) or within 50 metres of Uniper’s high pressure pipelines until the following conditions are satisfied—
(a)unless and until Uniper is satisfied acting reasonably (but subject to all necessary regulatory constraints) that the undertaker has first provided the acceptable security (and provided evidence that it will maintain such acceptable security for the construction period of the authorised development from the proposed date of commencement of construction the authorised development) and Uniper has confirmed the same to the undertaker in writing; and
(b)unless and until Uniper is satisfied acting reasonably (but subject to all necessary regulatory constraints) that the undertaker has procured acceptable insurance (and provided evidence to Uniper that it will maintain such acceptable insurance for the construction period of the authorised development from the proposed date of commencement of construction of the authorised development) and Uniper has confirmed the same in writing to the undertaker.
(6) The undertaker agrees that if, at any time, the acceptable security or acceptable insurance expires or terminates, ceases to fulfil the criteria of acceptable security or acceptable insurance, ceases to be in full force and effect or becomes invalid or unenforceable for the purpose of this Part of this Schedule or an insolvency-related event occurs in respect of the undertaker, then the relevant security or insurance will no longer constitute acceptable security or acceptable insurance and will promptly be replaced by the undertaker with alternative acceptable security or acceptable insurance as approved by the undertaker.
(7) In the event that the undertaker fails to comply with sub-paragraph (4), nothing in this Part of this Schedule will prevent Uniper from seeking injunctive relief (or any other equitable remedy) in any court of competent jurisdiction.
(8) Uniper must use its reasonable endeavours to mitigate and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph applies where it is within Uniper’s reasonable ability and control to do so and which expressly excludes any obligation to mitigate liability arising from third parties which is outside of Uniper’s control and if reasonably requested to do so by the undertaker Uniper must provide an explanation of how the claim has been minimised, where relevant.
Co-operation
196.—(1) Where, in consequence of the proposed construction of any of the authorised development, Uniper makes requirements for the protection or alteration of apparatus under paragraphs 192(6) or 192(8), the undertaker must use its best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe, efficient and economic operation of Uniper’s apparatus and Uniper must use its best endeavours to co-operate with the undertaker for that purpose.
(2) For the avoidance of doubt whenever Uniper’s consent, agreement or approval to is required in relation to plans, documents or other information submitted by Uniper or the taking of action by Uniper, it must not be unreasonably withheld or delayed.
Confidentiality
197.—(1) Each party must treat any confidential information as private and confidential. The party in receipt of any confidential information from the other party may not use it for a purpose other than for the performance of its obligations under this Part of this Schedule and must not disclose confidential information received from the other party to any person, provided that a party may disclose confidential information to any of its directors, other officers, employees, contractors, customers, affiliates, insurers, funders, advisers or consultants to the extent that disclosure is reasonably necessary for the purposes of this Part of this Schedule.
(2) Sub-paragraph (1) does not apply to confidential information—
(a)which is at the date of commencement, or at any time after that date becomes, publicly known other than by breach of sub-paragraph (1);
(b)which was known by the receiving party before disclosure by the other party to the receiving party, provided that such confidential information was lawfully obtained; or
(c)to the extent disclosure of the confidential information is required by laws, the instructions of a competent governmental authority or such competent authority acting on behalf of such governmental authority, or the rules of a relevant and recognised stock exchange.
Access
198. If in consequence of the agreement reached in accordance with paragraph 191(1) of this Part of this Schedule or otherwise as granted by this Order the access to any apparatus (including appropriate working areas required to reasonably and safely undertake necessary works by Uniper (or representative) in respect of the apparatus) is materially obstructed, the undertaker must provide such alternative rights and means of access to such apparatus as will enable Uniper (or its representative) to maintain or use the apparatus no less effectively than was possible before such obstruction. For the avoidance of doubt, Uniper (or its representative) will be entitled to access its apparatus in the land at all times.
Arbitration
199. Any difference or dispute arising between the undertaker and Uniper under this Part of this Schedule must be determined by arbitration in accordance with article 42 (arbitration).
Notices
200. Any notice, statement, request, plan or any other written communication (including the plan to be provided at paragraph 192 to be given or made in respect of this Part of this Schedule by the undertaker must be given or made in writing FAO Lead Pipeline Engineer, Uniper Pipelines Team, Pipelines Office, Uniper Killingholme Power Station, Chase Hill Road, Killingholme, North Lincolnshire, DN40 3LU or such other address as Uniper may have notified to the undertaker from time to time.