xmlns:atom="http://www.w3.org/2005/Atom"

PART 5ACQUISITION AND POSSESSION OF LAND

Temporary possession of land

Temporary use of land by National Grid

25.—(1) National Grid may, in connection with the carrying out of the authorised development—

(a)enter on and take temporary possession of—

(i)so much of the land specified in column (1) of Schedule 10 (land of which only temporary possession may be taken) to exercise the powers described in the Book of Reference for the purpose specified in relation to that land in column (2) of that Schedule relating to the part of the authorised development specified in column (3) of that Schedule; and

(ii)any other Order land in respect of which no notice of entry has been served under section 11 of the 1965 Act (other than in connection with the acquisition of rights only) and no declaration has been made under section 4 of the 1981 Act;

(b)remove any electric line, electrical plant, buildings, structures, pylons, apparatus, equipment, vegetation or any other thing from that land;

(c)construct temporary or permanent works (including the provision of means of access and buildings or structures on that land); and

(d)construct any works specified in relation to that land in column (2) of Schedule 10 or any other mitigation works.

(2) Not less than 14 days before entering on and taking temporary possession of land under this article, National Grid must serve notice of the intended entry on the owners and occupiers of the land.

(3) National Grid may not, without the agreement of the owners of the land, remain in possession of any land under this article—

(a)in the case of land referred to in sub-paragraph (1)(a)(i), after the end of the period of one year beginning with the date of completion of the part of the authorised development specified in relation to that land in column (3) of Schedule 10, or

(b)in the case of land referred to in sub-paragraph (1)(a)(ii), after the end of the period of one year beginning with the date of completion of the work for which temporary possession of the land was taken unless National Grid has, by the end of that period, served a notice of entry under section 11 of the 1965 Act or made a declaration under section 4 of the 1981 Act in relation to that land.

(4) National Grid must provide the owners of any land of which temporary possession has been taken under this article with written notice of the date of completion of the works for which temporary possession was taken within 28 days of the completion of those works.

(5) Before giving up possession of land of which temporary possession has been taken under sub-paragraph (1)(a)(i), unless otherwise agreed with the owners of the land, National Grid must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land, but National Grid is not required to—

(a)replace a building, structure, apparatus, equipment, electric line, electrical plant or pylon removed under this article;

(b)restore the land on which any works or mitigation have been carried out under sub-paragraph (1)(d) including insofar as the element of works shown in column (4) of Schedule 10 is concerned;

(c)remove any foundations below 1.5 metres which had been placed in that land to support pylons and electric lines constructed upon those foundations;

(d)remove any permanent work including pylons, electric lines, underground cables, or other permanent services, constructed or installed on, over, under or in that land as part of the authorised development;

(e)remove any ground-strengthening works (being either works listed in Schedule 10 of this Order or other works to provide safe and stable ground conditions) which have been placed in that land to facilitate construction of the authorised development;

(f)remove or reposition any apparatus belonging to statutory undertakers;

(g)remove any drainage works; or

(h)restore ground levels adjusted as part of the authorised development.

(6) Before giving up possession of land of which temporary possession has been taken under sub-paragraph (1)(a)(ii), unless otherwise agreed by the owners of the land, National Grid must either acquire the land or the interest on, over, or in the land in accordance with the provisions of sub-paragraph (3)(b) or remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but National Grid is not required to—

(a)replace a building, structure, apparatus, equipment, electric line, electrical plant or pylon removed under this article;

(b)restore the land on which any mitigation works have been carried out under sub-paragraph (1)(d);

(c)remove any foundations below 1.5 metres which had been placed in that land to support pylons and electric lines constructed upon those foundations;

(d)remove any permanent work including pylons, electric lines, underground cables, or other permanent services, constructed or installed on, over, under or in that land as part of the authorised development;

(e)remove any ground-strengthening works (being works to provide safe and stable ground conditions) which have been placed in that land to facilitate construction of the authorised development;

(f)remove or reposition any apparatus belonging to statutory undertakers;

(g)remove any drainage works; or

(h)restore ground levels adjusted as part of the authorised development.

(7) National Grid must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.

(8) Any dispute as to a person’s entitlement to compensation under paragraph (7), or as to the amount of the compensation, must be determined under Part 1 of the 1961 Act.

(9) Nothing in this article affects any liability to pay compensation under section 152 of the 2008 Act (compensation in case where no right to claim in nuisance) or under any other enactment in respect of loss or damage arising from the carrying out of the authorised development, other than loss or damage for which compensation is payable under paragraph (7).

(10) Where National Grid takes possession of land under this article, National Grid is not required to acquire the land or any interest in it.

(11) Section 13 of the 1965 Act (refusal to give possession to acquiring authority) applies to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory acquisition provisions).

(12) Nothing in this article prevents National Grid from taking temporary possession more than once in relation to any land specified in sub-paragraph (1)(a).