7.—(1) No part of the authorised development may commence until a written landscape and ecological management plan has been submitted to and approved by the relevant planning authority for that part or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities, in consultation with the Environment Agency.
(2) The landscape and ecological management plan must be substantially in accordance with the outline landscape and ecological management plan.
(3) The landscape and ecological management plan must be implemented as approved.
(4) For the purposes of sub-paragraph (1), “commence” includes part 2(1)(h) (site clearance (including vegetation removal, demolition of existing buildings and structures)) of permitted preliminary works.