63.—(1) The deposit management organisation may, for each scheme year, charge any scheme producer that is registered with it under regulation 11 during all or part of that scheme year, a fee.
(2) The fee charged under paragraph (1) (the “registration fee”) may be used for the purposes of meeting any or all of the following costs—
(a)the NEA costs, and
(b)the costs incurred by the deposit management organisation in exercising its functions under or in connection with the Scheme.
(3) The amount of the registration fee payable by a scheme producer is the aggregate of the following amounts—
(a)the producer amount for containers made wholly or mainly from polyethylene terephthalate (PET) plastic (if any),
(b)the producer amount for containers made wholly or mainly from steel (if any), and
(c)the producer amount for containers made wholly or mainly from aluminium (if any).
(4) The producer amount for containers made wholly or mainly from each type of in-scope material must be calculated as follows (and may be £0)—
where—
“A” is the fee for the relevant scheme year for a container made wholly or mainly from the particular in-scope material (the “per container fee”), and
“B” is the total number of containers made wholly or mainly from that in-scope material which the deposit management organisation expects the relevant scheme producer to supply to scheme consumers in the relevant scheme year.
(5) The per container fee for a container made wholly or mainly from a particular in-scope material—
(a)must be the same for all registered scheme producers, and
(b)may be £0.
(6) The deposit management organisation must, for the purposes of determining the registration fee, have regard to the likely value, or if known the actual value, of each type of in-scope material which the deposit management organisation expects to be recycled from all of the refund items which are collected by, or returned, to the deposit management organisation in the relevant scheme year.
(7) The per container fee for one in-scope material must not subsidise any of the relevant costs from any other in-scope material.
(8) For the purposes of paragraph (7), “the relevant costs” for an in-scope material are the costs which the deposit management organisation expects to incur in the exercise of its functions under, or in connection with, the Scheme in relation to the collection, processing and recycling of refund items made wholly or mainly from that material.
(9) The deposit management organisation must—
(a)keep the registration fee under review;
(b)carry out a full review of the operation of the registration fee at least every 12 months, and
(c)publish the registration fee in such manner as it considers appropriate to bring it to the attention of scheme producers.
(10) Before determining, or re-determining, the registration fee, the deposit management organisation must consult—
(a)scheme producers, and
(b)such other persons (if any) as the deposit management organisation considers appropriate,
and have regard to the views expressed in responses to the consultation.
(11) The deposit management organisation may require the registration fee to be payable at times or intervals and by means specified by the deposit management organisation.
(12) The deposit management organisation may make different payment arrangements for different cases or circumstances and in particular—
(a)must ensure that any registration fee charged to a scheme producer in accordance with paragraph (1) does not include a fee in respect of a container from a container drink which is a registered low volume product during the scheme year concerned;
(b)may make arrangements for registration fees to be reduced, waived or refunded (whether in whole or in part).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: