7.—(1) The relevant notice, and the documents accompanying it, will be deemed to comprise the appellant’s representations in relation to the appeal.
(2) The local planning authority may elect to treat the questionnaire, and the documents sent with it, as its representations in relation to the appeal and, where it does so, it must notify the National Assembly and the appellant accordingly when it sends to the National Assembly, and copies to the appellant, the questionnaire in accordance with regulation 6.
(3) Where the local planning authority does not elect as described in paragraph (2), it must ensure that 2 copies of those further written representations are received by the National Assembly within 6 weeks of the starting date.
(4) An appellant who wishes to make any further representations to those in paragraph (1) must send 2 copies of those further representations to the National Assembly so as to be received within 6 weeks of the starting date.
(5) Any representations made to the National Assembly under paragraphs (3) and (4) must be dated with the date on which they are sent to the National Assembly.
(6) The National Assembly must, as soon as practicable after receipt, send to the appellant a copy of any representations sent to it by the local planning authority and must send to the local planning authority a copy of any representations sent to it by the appellant.
(7) The appellant and the local planning authority must send to the National Assembly 2 copies of any written comments they have on each other’s representations so as to be received within 9 weeks of the starting date and the National Assembly must, as soon as practicable after receipt, send a copy of those further comments to the other party.
(8) The National Assembly may disregard further information from the appellant and the local planning authority which is not received within 9 weeks of the starting date unless that further information has been requested by it.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.
Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: