http://www.legislation.gov.uk/wsi/2004/3054/article/16/made
The Scarweather Sands Offshore Wind Farm Order 2004
Compulsory purchase
Wind power
Road works
Motor industry
King's Printer of Acts of Parliament
2019-07-08
TRANSPORT AND WORKS, WALES
OFFSHORE INSTALLATIONS, WALES
ELECTRICITY, WALES
This Order provides for the construction and operation of an offshore wind farm and ancillary works on the bed of Swansea Bay off the coast between Porthcawl and Port Talbot and for the connection of those works via an onshore substation to the electricity distribution system.
PART IIWORKS
Protection of navigation and air traffic and control of noise
Execution by Secretary of State of works in default16
If, on the expiration of 30 days from the date when a notice under article 8(2)(a) or 10(1) is served upon the undertaker it has failed, without reasonable excuse, to comply with the requirements of the notice, the Secretary of State may execute the works specified in the notice; and any expenditure incurred by the Secretary of State in so doing will be recoverable from the undertaker.