Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
5.—(1) This paragraph shall apply where a contractor wishes to serve or serves an out of hours opt out notice before 1st October 2004.
(2) In this paragraph —
“OOH day” is the day specified by the Local Health Board for the commencement of the out of hours opt out in its decision under sub-paragraph (5);
“OOHB day” is the day six months after the date of service of the out of hours opt out notice; and
“OOHC day” is the day specified by the Local Health Board in its decision under sub-paragraph (11) or (13) (which must be nine months after the date of service of the out of hours opt out notice or before 2nd January 2005).
(3) A contractor which wishes to terminate its obligation to provide out of hours services which was included in the contract pursuant to regulation 30 shall notify the relevant Local Health Board in writing to that effect (“an out of hours opt out notice”).
(4) An out of hours opt out notice shall state the date on which the contractor would like the opt out to take effect, which must either be three or six months after the date of service of the out of hours opt out notice.
(5) As soon as is reasonably practicable and in any event within 28 days of receiving the out of hours opt out notice, the Local Health Board shall approve the notice and specify in accordance with sub-paragraphs (6) and (7) the date on which the out of hours opt out is to commence (“OOH day”) and the Local Health Board shall notify the contractor in writing of its decision as soon as possible, including reasons for its decision.
(6) Subject to sub-paragraph (7), OOH day shall be —
(a)the date specified in the out of hours opt out notice; or
(b)any other date before 2nd January 2005.
(7) A Local Health Board may not specify under sub-paragraph (5) a date earlier than the date specified in the out of hours opt out notice.
(8) A contractor may not withdraw an out of hours opt out notice once it has been approved by a Local Health Board under sub-paragraph (5) without the Local Health Board’s agreement.
(9) Following receipt of the out of hours opt out notice, the Local Health Board must use its reasonable endeavours to make arrangements for the contractor’s registered patients to receive out of hours services from an alternative provider from OOH day.
(10) The contractor’s duty to provide the out of hours services shall terminate on OOH day unless the Local Health Board —
(a)serves a notice under sub-paragraph (11) (extending OOH day to OOHB day or OOHC day); or
(b)makes an application under sub-paragraph (14) (seeking the approval of the Assembly to a decision to refuse an opt out or to delay the taking of effect of an opt out until after OOH day.
(11) If the Local Health Board is not successful in finding an alternative provider to take on the provision of the out hours services from OOH day, then it shall notify the contractor in writing of this fact no later than one month before OOH day, and —
(a)in a case where OOH day is three months after service of the out of hours opt out notice, the contractor shall continue to provide the out of hours services until OOHB day unless at least one month before OOHB day it receives a notice in writing from the Local Health Board under sub-paragraph (13) that despite using its reasonable endeavours, it has failed to find an alternative provider to take on the provision of the out of hours services from OOHB day;
(b)in a case where OOH day is after the day three months after the service of the out of hours opt out notice, the contractor shall continue to provide the out of hours services until OOHC day (which shall be specified by the Local Health Board in accordance with sub-paragraph (12) and included in its notice to the contractor under this sub-paragraph) unless at least one month before OOHC day it receives a notice from the Local Health Board under sub-paragraph (16) that it has made an application to the Assembly under sub-paragraph (14) seeking its approval to a decision to refuse an opt out or to delay the commencement of the opt out until after OOHC day.
(12) OOHC day shall be any day before 2nd January 2005 or the day nine months after the service of the out of hours opt out notice.
(13) Where in accordance with sub-paragraph (11)(a) the out of hours opt out is to commence on OOHB day and the Local Health Board, despite using its reasonable endeavours has failed to find an alternative provider to take on the provision of the out of hours services from that day, it shall notify the contractor in writing of this fact at least one month before OOHB day, in which case the contractor shall continue to provide the out of hours services until OOHC day (which shall be specified by the Local Health Board in accordance with sub-paragraph (12) and included in its notice to the contractor under this sub-paragraph) unless at least one month before OOHC day it receives a notice from the Local Health Board under sub-paragraph (16) that it has applied to the Assembly under sub-paragraph (14) seeking the approval of the Assembly to a decision to refuse an opt out or to postpone the commencement of an opt out until after OOHC day.
(14) The Local Health Board may, if it considers there are exceptional circumstances, make an application to the Assembly for approval of a decision to —
(a)refuse an opt out; or
(b)postpone the commencement of an opt out until after —
(i) OOHC day, or
(ii)OOH day where OOH day is 1st January 2005 and 1st January 2005 is nine months or more after the date of the out of hours opt out notice.
(15) Where OOH day is 1st January 2005 and 1st January 2005 is nine months or more after the date of the out of hours opt out notice, an application under sub-paragraph (14) shall be made at least one month before OOH day.
(16) As soon as practicable after making an application under sub-paragraph (14) to the Assembly, the Local Health Board shall notify the contractor in writing that it has made such an application.
(17) Sub-paragraphs (12) to (21) of paragraph 3 shall apply to an out of hours opt out as they apply to a permanent opt out and as if the reference to “C day” was a reference to OOHC day or OOH day where OOH day is 1st January 2005 and 1st January 2005 is nine months or more after the date of the out of hours opt out notice.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: