PART 4Determination
Time periods for decisions22.
(1)
(2)
The period specified or referred to in this paragraph is—
(a)
the period of eight weeks beginning with the date on which the application was received by the local planning authority;
(b)
except where the applicant has already given notice of appeal to the Welsh Ministers, such extended period as may be agreed in writing between the applicant and the authority; or
(c)
where any fee required in respect of an application has been paid by a cheque which is subsequently dishonoured, the appropriate period specified in sub-paragraph (a) or (b) above calculated disregarding the period between the date when the authority sent the applicant written notice of the dishonouring of the cheque and the date when the authority are satisfied they have received the full amount of the fee.
(3)
In this article “valid application” (“cais dilys”) means an application which consists of—
(a)
an application which complies with the requirements of article 4 or article 5, as the case may be;
(b)
where an application is made in respect of Crown land, the documents required by article 6;
(c)
in a case to which article 7 applies, the design and access statement or the access statement as the case may be;
(d)
in a case to which article 9 applies, the written declaration required by that article;
(e)
the certificate required by article 11;
(f)
(g)
any fee required to be paid in respect of the application and, for this purpose, lodging a cheque for the amount of the fee is to be taken as payment,
and a valid application must be taken to have been received when the application and such of the documents, particulars or evidence referred to above as are required to be included in or to accompany the application and any fee required have been lodged with the local planning authority.
(4)
Paragraph (3)(f) only applies if—
(a)
the application is for major development;
(b)
before the application is made the local planning authority publish, for the purposes of paragraph (3), a list of requirements on their website; and
(c)
the particulars or evidence that the authority require to be included in the application fall within that list.
(5)
A local planning authority must provide such information about applications made under article 4 or article 5 (including information as to the manner in which any such application has been dealt with) as the Welsh Ministers may by direction require. Any such direction may include provision as to the persons to be informed and the manner in which the information is to be provided.
(6)
Subject to paragraph (7), a local planning authority must not determine an application for planning permission, where any notice of, or information about, the application has been—
(a)
given by site display under article 10 or 12, before the end of the period of 21 days beginning with the date when the notice was first displayed by site display;
(b)
served on—
(i)
an owner of the land or a tenant under article 10, or
(ii)
an adjoining owner or occupier under article 12,
before the end of the period of 21 days beginning with the date when the notice was served on that person; or
(c)
published in a newspaper under article 10 or 12 or on a website under article 12, within the period of 14 days beginning with the date on which the notice or information was published,
(7)
Where, under paragraph (6), more than one of the prescribed periods applies, the local planning authority must not determine the application before the end of the later or latest of such periods.