PART 2Amendment of the Building Regulations 2010
Primary energy consumption rate and fabric performance values calculations7
After regulation 27 insert—
Primary energy consumption rate calculations27A
1
This regulation applies where a building (other than a dwelling) is erected and regulation 26A applies.
2
Not later than the day before the work starts, the person carrying out the work must give the local authority a notice which specifies—
a
the target primary energy consumption rate for the building;
b
the calculated primary energy consumption rate for the building as designed; and
c
a list of specifications to which the building is to be constructed.
3
Not later than five days after the work has been completed, the person carrying out the work must give the local authority—
a
a notice which specifies—
i
the target primary energy consumption rate for the building;
ii
the calculated primary energy consumption rate for the building as constructed; and
iii
whether the building has been constructed in accordance with the list of specifications referred to in paragraph 2(c), and if not a list of any changes to those specifications; or
b
a certificate of the sort referred to in paragraph (4) accompanied by the information referred to in sub-paragraph (a).
4
A local authority is authorised to accept, as evidence that the requirements of regulation 26A have been satisfied, a certificate to that effect by an energy assessor who is accredited to produce such certificates for that category of building.
5
In this regulation, “specifications” means specifications used for the calculation of the primary energy consumption rate.
Fabric performance values calculations27B
1
This regulation applies where a dwelling is erected and regulation 26B applies.
2
Not later than the day before the work starts, the person carrying out the work must give the local authority a notice which specifies—
a
the target fabric performance values for the dwelling;
b
the calculated fabric performance values for the dwelling as designed; and
c
a list of specifications to which the dwelling is to be constructed.
3
Not later than five days after the work has been completed, the person carrying out the work must give the local authority—
a
a notice which specifies—
i
the target fabric performance values for the dwelling;
ii
the calculated fabric performance values for the dwelling as constructed; and
iii
whether the dwelling has been constructed in accordance with the list of specifications referred to in paragraph 2(c), and if not a list of any changes to those specifications; or
b
a certificate of the sort referred to in paragraph (4) accompanied by the information referred to in sub-paragraph (a).
4
A local authority is authorised to accept, as evidence that the requirements of regulation 26B have been satisfied, a certificate to that effect by an energy assessor who is accredited to produce such certificates for that category of building.
5
In this regulation, “specifications” means specifications used for the calculation of the fabric performance values.