PART 2Amendment of the Building Regulations 2010

Primary energy consumption rate and fabric performance values calculations7

After regulation 27 insert—

Primary energy consumption rate calculations27A

1

This regulation applies where a building (other than a dwelling) is erected and regulation 26A applies.

2

Not later than the day before the work starts, the person carrying out the work must give the local authority a notice which specifies

a

the target primary energy consumption rate for the building;

b

the calculated primary energy consumption rate for the building as designed; and

c

a list of specifications to which the building is to be constructed.

3

Not later than five days after the work has been completed, the person carrying out the work must give the local authority

a

a notice which specifies

i

the target primary energy consumption rate for the building;

ii

the calculated primary energy consumption rate for the building as constructed; and

iii

whether the building has been constructed in accordance with the list of specifications referred to in paragraph 2(c), and if not a list of any changes to those specifications; or

b

a certificate of the sort referred to in paragraph (4) accompanied by the information referred to in sub-paragraph (a).

4

A local authority is authorised to accept, as evidence that the requirements of regulation 26A have been satisfied, a certificate to that effect by an energy assessor who is accredited to produce such certificates for that category of building.

5

In this regulation, “specifications” means specifications used for the calculation of the primary energy consumption rate.

Fabric performance values calculations27B

1

This regulation applies where a dwelling is erected and regulation 26B applies.

2

Not later than the day before the work starts, the person carrying out the work must give the local authority a notice which specifies

a

the target fabric performance values for the dwelling;

b

the calculated fabric performance values for the dwelling as designed; and

c

a list of specifications to which the dwelling is to be constructed.

3

Not later than five days after the work has been completed, the person carrying out the work must give the local authority

a

a notice which specifies

i

the target fabric performance values for the dwelling;

ii

the calculated fabric performance values for the dwelling as constructed; and

iii

whether the dwelling has been constructed in accordance with the list of specifications referred to in paragraph 2(c), and if not a list of any changes to those specifications; or

b

a certificate of the sort referred to in paragraph (4) accompanied by the information referred to in sub-paragraph (a).

4

A local authority is authorised to accept, as evidence that the requirements of regulation 26B have been satisfied, a certificate to that effect by an energy assessor who is accredited to produce such certificates for that category of building.

5

In this regulation, “specifications” means specifications used for the calculation of the fabric performance values.