PART 2 E+WPre-application

Pre-application consultation reportsE+W

11.—(1) Where an applicant submits an application to the Welsh Ministers in accordance with article 12, that application must be accompanied by a pre-application consultation report which gives particulars of—

(a)how the applicant complied with section 61Z of the 1990 Act;

(b)any response to the consultation received from persons consulted under section 61Z(3) or (4) of the 1990 Act; and

(c)the account taken of those responses.

(2) The pre-application consultation report must include—

(a)a copy of the notice referred to in article 8(1)(a)(i);

(b)a declaration that the notice referred to in article 8(1)(a)(i) was displayed in accordance with the requirements of that article;

(c)a list of the addresses of the persons who were given notice of the proposed application in accordance with article 8(1)(a)(ii) and a copy of the notice given to such persons;

(d)a copy of the publication referred to in article 8(1)(a)(iii);

(e)a declaration that the applicant has complied with the publication requirements in article 8(1)(b);

(f)copies of all notices given to community consultees, relevant persons and specialist consultees in accordance with articles 9(2) and 9(3);

(g)a summary of all issues raised by any person notified of the proposed application in accordance with section 61Z(3) of the 1990 Act and articles 8 and 9(2), including confirmation of whether the issues raised have been addressed and, if so, how; and

(h)copies of all responses received from specialist consultees with an explanation of the account taken of each response.