Registration requirements
4.—(1) For the purpose of section 2(2C) of the 1975 Act, the information that is to be registered with the NRBW by an undertaker of a large raised reservoir is that prescribed in Schedule 1, paragraphs 1 to 7.
(2) The information prescribed in Schedule 1 must be registered—
(a)before the end of the period of 28 days beginning with the day of the issue of a final certificate given in accordance with section 7 of the 1975 Act(1) in relation to—
(i)the construction of a new reservoir;
(ii)the alteration of an existing structure or area that prior to its alteration was not a large raised reservoir; or
(iii)the alteration of an area of a reservoir that prior to its alteration was not a large raised reservoir;
(b)within 6 months of registration under section 2(2C) of the 1975 Act,
(c)whichever is the sooner.
Section 7 was amended in relation to England and Wales by section 33 of, and paragraphs 8 and 11 of Schedule 4 to, the Flood and Water Management Act 2010 (c.29).