4.—(1) Subject to paragraph (2), the requirement for approval under paragraph 7(1) of Schedule 3 does not apply to construction work where the construction work does not require planning permission(1).
(2) The exception in paragraph (1) does not apply where the construction work involves the construction of a building or other structure covering an area of land of 100 square metres or more.
“Planning permission” is defined in paragraph 8(4) of Schedule 3.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.
Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: