SCHEDULE 6E+WRequirements for slurry storage systems

9.  If the walls of the slurry storage tank are not impermeable, the base of the tank must—E+W

(a)extend beyond the walls;

(b)be provided with channels designed and constructed so as to collect any slurry that escapes from the tank;

(c)have adequate provision for the drainage of the slurry from those channels to an effluent tank through a channel or pipe.