1. Introductory Text

  2. 1.Title, coming into force and code

  3. 2.Interpretation

  4. PART 1 APPLICATIONS

    1. 3.Applying for listed building consent

    2. 4.Heritage impact statement

    3. 5.Notice of application for listed building consent to owners of building

    4. 6.Certificate to be included with application for listed building consent

    5. 7.Acknowledgement of application for listed building consent

    6. 8.Advertisement of applications for listed building consent

    7. 9.Notification to the Amenity Societies and the Royal Commission on the Ancient and Historical Monuments of Wales

    8. 10.Reference of applications to the Welsh Ministers

    9. 11.Disapplication of requirement to notify the Welsh Ministers of applications for listed building consent

    10. 12.Decision on application

    11. 13.Notice of decision or referral to the Welsh Ministers

    12. 14.Notification of amenity societies etc. of decision

    13. 15.Application for variation or removal of conditions

  5. PART 2 APPEALS

    1. 16.Appeals

    2. 17.Variation of applications after notice of appeal

    3. 18.Decision on application after service of notice of appeal

  6. PART 3 SPECIAL CASES

    1. 19.Disapplication and modifications: applications by a planning authority for demolition of a listed building

    2. 20.Applications other than for demolition made by a planning authority

    3. 21.Application for listed building consent in respect of Crown land

    4. 22.Publicity for applications relating to urgent works on Crown land

  7. PART 4 Conservation Areas

    1. 23.Disapplication of the requirement for demolition in conservation areas to be authorised

    2. 24.Application of these Regulations to buildings in conservation areas

  8. PART 5 MISCELLANEOUS AND GENERAL

    1. 25.Advertisement of unopposed revocation or modification order

    2. 26.Interest rate on expenses for urgent works

    3. 27.Consequential amendments

    4. 28.Revocation

  9. Signature

    1. SCHEDULE 1

      Notification to Applicant on Receipt of Application

      1. 1.Your application dated ………………insert date was received on…………………………..insert date *[We...

      2. 2.If by ……………………….……………………. insert date 8 weeks beginning with the...

      3. 3.The right to, and procedure for, appeal is in sections...

      4. 4.You must submit any appeal on a form which you...

      5. 5.If you are appealing against a decision which refuses the...

    2. SCHEDULE 2

      Notification to Applicant on Refusal of Consent or Grant of Consent Subject to Conditions (to be included with notices of decision)

      1. 1.If you are aggrieved by the decision of the planning...

      2. 2.You must submit any appeal on a form which you...

      3. 3.The Welsh Ministers may allow a longer period for you...

      4. 4.If consent is refused, or is granted subject to conditions...

      5. 5.In the following paragraphs, “associated land” means land which includes,...

      6. 6.The conditions are that the owner of the building and...

      7. 7.There is more detail about the meaning of “usable in...

      8. 8.If the conditions in paragraph 6 are satisfied, the owner...

      9. 9.There is further detail about this right in sections 109...

    3. SCHEDULE 3

      Notification to Applicant on Refusal to Vary or Remove Conditions Attached to a Consent or on the Addition of New Conditions (to be included with the notices of decision)

      1. 1.You may appeal to the Welsh Ministers if you are...

      2. 2.The right to, and procedure for, appeal is in sections...

      3. 3.You must submit any appeal on a form which you...

      4. 4.The Welsh Ministers may allow a longer period for you...

    4. SCHEDULE 4

      Consequential amendments

      1. 1.The Local Authorities (Executive Arrangements) (Functions and Responsibilities) (Wales) Regulations 2007

      2. 2.The Transport and Works Applications (Listed Buildings, Conservation Areas and Ancient Monuments Procedure) Regulations 1992

      3. 3.In regulation 2, in the definition of “conservation area consent”...

      4. 4.In regulation 3— (a) at the end of the heading,...

      5. 5.After regulation 3 insert— Modification of procedures for listed building...

      6. 6.After Schedule 1 insert— SCHEDULE1A Modifications of the Listed Buildings...

      7. 7.The National Park Authorities (Wales) Order 1995

      8. 8.In Schedule 1 to the Local Government Reorganisation (Wales) (Consequential...

      9. 9.In the Schedule to the National Park Authorities (Wales) (Amendment)...

      10. 10.The Town and Country Planning (Electronic Communications) (Wales) (No 1) Order 2004

      11. 11.The Developments of National Significance (Wales) Regulations 2016

      12. 12.In Schedule 4— (a) for paragraph 2 in Part 2...

      13. 13.In Schedule 5— (a) for paragraph 2 of Part 2...

      14. 14.The Town and Country Planning (Referred Applications and Appeals Procedure) (Wales) Regulations 2017

      15. 15.In regulation 3(1)— (a) omit the definition of “the 2012...

      16. 16.Regulation 54 is omitted.

    5. SCHEDULE 5

      Revocation and withdrawal

      1. 1.The following statutory instruments are revoked— (a) the Planning (Listed...

      2. 2.The Planning (Listed Buildings and Conservation Areas) Regulations 1990 are...

      3. 3.The following Directions are withdrawn— (a) the Listed Building Applications...

  10. Explanatory Note