Sometimes the text of a provision is changed, but the change(s) only apply to a particular geographical area. In some limited cases where this happens, the editorial team create a version for each different geographical area. Multiple versions are only created in this way where the change in question is a substitution so that there are different versions of the text for the different extents. Insertions and repeals of text do not give rise to such multiple versions.
There are currently no known outstanding effects for the The Simple Pressure Vessels (Safety) Regulations 2016, Paragraph 12.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
12.—(1) For each individual type of vessel manufactured, the [F1approved] body must carry out the appropriate examinations and tests in order to verify the conformity of the vessel with the type described in the [F2Type] examination certificate and with the corresponding requirements of these Regulations.
(2) The manufacturer must present the vessels in the form of uniform batches and must take all necessary measures in order that the manufacturing process ensures the uniformity of each batch produced.
(3) When a batch is examined, the [F1approved] body must ensure that the vessels have been manufactured and checked in accordance with the technical documentation, and must perform a hydrostatic test or a pneumatic test of equivalent effect on each vessel in the batch at a pressure Ph equal to 1.5 times the vessel's design pressure in order to check its strength; the pneumatic test must be subject to acceptance of the test safety procedures by the [F3Secretary of State].
(4) In order to examine the weld quality, the [F1approved] body must carry out tests on test-pieces taken from, at the choice of the manufacturer, either a production test-piece or from a vessel. The tests must be carried out on longitudinal welds; however, where differing weld techniques are used for longitudinal and circumferential welds, the tests must be repeated on the circumferential welds.
(5) For the vessels subject to the experimental methods referred to in paragraph 17 (experimental method) of Schedule 1, these tests on test-pieces must be replaced by a hydrostatic test on five vessels taken at random from each batch in order to check that they conform to the essential safety requirements set out in that paragraph.
(6) In the case of accepted batches, the [F1approved] body must affix its identification number, or cause that number to be affixed, to each vessel and must draw up a written certificate of conformity relating to the tests carried out. All vessels in the batch may be placed on the market except for those which have not successfully undergone a hydrostatic test or a pneumatic test.
(7) If a batch is rejected, the [F1approved] body must take appropriate measures to prevent the placing on the market of that batch. In the event of frequent rejection of batches, the [F1approved] body may suspend the statistical verification.
(8) The manufacturer must be able to supply on request by the relevant authorities the [F1approved] body's certificates of conformity referred to in sub-paragraph (6).
(9) The [F1approved] body must supply the Secretary of State and, on request, other [F1approved] bodies, F4... with a copy of the inspection report issued by it.
(10) The manufacturer must, under the responsibility of the [F1approved] body, affix the [F1approved] body's identification number during the manufacturing process.
(11) In this paragraph, a “batch” of vessels must consist of no more than 3,000 vessels of the model of the same type.
Extent Information
E1This version of this provision extends to England and Wales and Scotland only; a separate version has been created for Northern Ireland only
Textual Amendments
F1Words in Sch. 2 substituted (E.W.S.) (31.12.2020) by The Product Safety and Metrology etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/696), reg. 1, Sch. 21 para. 40(c) (with Sch. 21 para. 37) (as amended by S.I. 2020/676, regs. 1(1), 2); 2020 c. 1, Sch. 5 para. 1(1)
F2Word in Sch. 2 substituted (E.W.S.) (31.12.2020) by The Product Safety and Metrology etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/696), reg. 1, Sch. 21 para. 40(e) (with Sch. 21 para. 37) (as amended by S.I. 2020/676, regs. 1(1), 2); 2020 c. 1, Sch. 5 para. 1(1)
F3Words in Sch. 2 para. 12(3) substituted (E.W.S.) (31.12.2020) by The Product Safety and Metrology etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/696), reg. 1, Sch. 21 para. 40(j) (with Sch. 21 para. 37) (as amended by S.I. 2020/676, regs. 1(1), 2); 2020 c. 1, Sch. 5 para. 1(1)
F4Words in Sch. 2 para. 12(9) omitted (E.W.S.) (31.12.2020) by virtue of The Product Safety and Metrology etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/696), reg. 1, Sch. 21 para. 40(k) (with Sch. 21 para. 37) (as amended by S.I. 2020/676, regs. 1(1), 2); 2020 c. 1, Sch. 5 para. 1(1)
12.—(1) For each individual type of vessel manufactured, the notified body must carry out the appropriate examinations and tests in order to verify the conformity of the vessel with the type described in the EU-type examination certificate and with the corresponding requirements of these Regulations.
(2) The manufacturer must present the vessels in the form of uniform batches and must take all necessary measures in order that the manufacturing process ensures the uniformity of each batch produced.
(3) When a batch is examined, the notified body must ensure that the vessels have been manufactured and checked in accordance with the technical documentation, and must perform a hydrostatic test or a pneumatic test of equivalent effect on each vessel in the batch at a pressure Ph equal to 1.5 times the vessel's design pressure in order to check its strength; the pneumatic test must be subject to acceptance of the test safety procedures by the [F5relevant state] in which the test is performed.
(4) In order to examine the weld quality, the notified body must carry out tests on test-pieces taken from, at the choice of the manufacturer, either a production test-piece or from a vessel. The tests must be carried out on longitudinal welds; however, where differing weld techniques are used for longitudinal and circumferential welds, the tests must be repeated on the circumferential welds.
(5) For the vessels subject to the experimental methods referred to in paragraph 17 (experimental method) of Schedule 1, these tests on test-pieces must be replaced by a hydrostatic test on five vessels taken at random from each batch in order to check that they conform to the essential safety requirements set out in that paragraph.
(6) In the case of accepted batches, the notified body must affix its identification number, or cause that number to be affixed, to each vessel and must draw up a written certificate of conformity relating to the tests carried out. All vessels in the batch may be placed on the market except for those which have not successfully undergone a hydrostatic test or a pneumatic test.
(7) If a batch is rejected, the notified body must take appropriate measures to prevent the placing on the market of that batch. In the event of frequent rejection of batches, the notified body may suspend the statistical verification.
(8) The manufacturer must be able to supply on request by the relevant authorities the notified body's certificates of conformity referred to in sub-paragraph (6).
(9) The notified body must supply the Secretary of State and, on request, other notified bodies, other [F6relevant states] and the Commission, with a copy of the inspection report issued by it.
(10) The manufacturer must, under the responsibility of the notified body, affix the notified body's identification number during the manufacturing process.
(11) In this paragraph, a “batch” of vessels must consist of no more than 3,000 vessels of the model of the same type.
Extent Information
E2This version of this provision extends to Northern Ireland only; a separate version has been created for England and Wales and Scotland only
Textual Amendments
F5Words in Sch. 2 para. 12(3) substituted (N.I.) (31.12.2020) by The Pressure Vessels (Amendment) (Northern Ireland) (EU Exit) Regulations 2020 (S.I. 2020/678), reg. 1(b), Sch. 1 para. 8(1)(b)
F6Words in Sch. 2 para. 12(9) substituted (N.I.) (31.12.2020) by The Pressure Vessels (Amendment) (Northern Ireland) (EU Exit) Regulations 2020 (S.I. 2020/678), reg. 1(b), Sch. 1 para. 8(1)(c)
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: