Search Legislation

The Scheme for Construction Contracts (Scotland) Regulations 1998

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

  1. Introductory Text

  2. 1.Citation, commencement and extent

  3. 2.Interpretation

  4. 3.The Scheme for Construction Contracts (Scotland)

  5. 4.Where– (a) the parties to a construction contract are unable...

  6. 5.The provisions in the Schedule to these Regulations shall be...

  7. Signature

    1. Expand +/Collapse -

      SCHEDULE

      THE SCHEME FOR CONSTRUCTION CONTRACTS (SCOTLAND)

      1. Expand +/Collapse -

        PART I ADJUDICATION

        1. 1.Notice of intention to seek adjudication

        2. 2.(1) Following the giving of a notice of adjudication and...

        3. 3.The request referred to in paragraphs 2, 5 and 6...

        4. 4.Any person requested or selected to act as adjudicator in...

        5. 5.(1) The nominating body referred to in paragraphs 2(1)(b) and...

        6. 6.(1) Where an adjudicator who is named in the contract...

        7. 7.(1) Where an adjudicator has been selected in accordance with...

        8. 8.(1) The adjudicator may, with the consent of all the...

        9. 9.(1) An adjudicator may resign at any time on giving...

        10. 10.Where any party to the dispute objects to the appointment...

        11. 11.(1) The parties to a dispute may at any time...

        12. 12.Powers of the adjudicator

        13. 13.The adjudicator may take the initiative in ascertaining the facts...

        14. 14.The parties shall comply with any request or direction of...

        15. 15.If, without showing sufficient cause, a party fails to comply...

        16. 16.(1) Subject to any agreement between the parties to the...

        17. 17.The adjudicator shall consider any relevant information submitted to him...

        18. 18.The adjudicator and any party to the dispute shall not...

        19. 19.(1) The adjudicator shall reach his decision not later than–...

        20. 20.Adjudicator’s decision

        21. 21.In the absence of any directions by the adjudicator relating...

        22. 22.If requested by one of the parties to the dispute,...

        23. 23.Effects of the decision

        24. 24.Where a party or the adjudicator wishes to register the...

        25. 25.(1) The adjudicator shall be entitled to the payment of...

        26. 26.The adjudicator shall not be liable for anything done or...

      2. Expand +/Collapse -

        PART II PAYMENT

        1. 1.Entitlement to and amount of stage payments

        2. 2.(1) The amount of any payment by way of instalments...

        3. 3.Dates for payment

        4. 4.Any payment of a kind mentioned in paragraph 2 above...

        5. 5.The final payment payable under a relevant construction contract, namely...

        6. 6.Payment of the contract price under a construction contract (not...

        7. 7.Any other payment under a construction contract shall become due...

        8. 8.Final date for payment

        9. 9.Notice specifying amount of payment

        10. 10.Notice of intention to withhold payment

        11. 11.Prohibition of conditional payment provisions

        12. 12.Interpretation

  8. Explanatory Note

Back to top

Options/Help