Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
Valid from 01/12/2022
(1)Subsection (2) applies if—
(a)the landlord under a standard contract makes a possession claim on the ground in section 170 or 191 (contract-holder's notice) or section 186 (landlord's notice in connection with end of fixed term), and
(b)the court is satisfied that the ground is made out.
(2)The court must make an order for possession of the dwelling (subject to any available defence based on the contract-holder's Convention rights).
(3)Subsection (4) applies if—
(a)the landlord under a standard contract makes a possession claim on the ground in section 178 or 199 (landlord's notice), and
(b)the court is satisfied that the ground is made out.
(4)The court must make an order for possession of the dwelling unless section 217 (retaliatory evictions) applies (and subject to any available defence based on the contract-holder's Convention rights).
(5)This section is subject to section 218 (review by the county court).
(1)This section applies if the landlord under a standard contract makes a possession claim on the ground in section 181 or 187 (serious rent arrears).
(2)If the court is satisfied that the contract-holder—
(a)was seriously in arrears with his or her rent on the day on which the landlord gave the contract-holder a possession notice, and
(b)is seriously in arrears with his or her rent on the day on which the court hears the possession claim,
it must make an order for possession of the dwelling (subject to any available defence based on the contract-holder's Convention rights).
(3)Section 181(2) or (as the case may be) section 187(2) applies for determining whether a contract-holder is seriously in arrears with his or her rent.
(4)This section is subject to section 218 (review by the county court).
(1)This section applies if—
(a)a landlord under a standard contract makes a possession claim on the ground in section 178 or section 199 (landlord's notice), and
(b)the court considers that the claim is a retaliatory claim.
(2)The court may refuse to make an order for possession.
(3)A possession claim is a retaliatory claim if—
(a)the contract-holder has enforced or relied on the landlord's obligations under section 91 or 92, and
(b)the court is satisfied that the landlord has made the possession claim to avoid complying with those obligations.
(4)The Welsh Ministers may by regulations amend this section for the purpose of providing for further descriptions of retaliatory claim.
(1)This section applies if a landlord under a standard contract makes a possession claim in the county court on a ground in a section to which subsection (2) applies, and—
(a)the landlord is a community landlord, or
(b)the landlord's decision to make a possession claim on that ground is subject to judicial review.
(2)This subsection applies to the following sections—
(a)section 170 (contract-holder's notice: periodic standard contracts),
(b)section 178 (landlord's notice: periodic standard contracts),
(c)section 181 (serious rent arrears: periodic standard contracts),
(d)section 186 (landlord's notice in connection with end of fixed term),
(e)section 187 (serious rent arrears: fixed term standard contracts),
(f)section 191 (contract-holder's notice: fixed term standard contracts), and
(g)section 199 (landlord's notice: fixed term standard contracts).
(3)The contract-holder may make an application in the possession proceedings for a review by the county court of the landlord's decision to make the claim.
(4)The contract-holder may make an application under this section regardless of whether he or she requested a review by the landlord under section 202 (introductory standard contracts and prohibited conduct standard contracts).
(5)The contract-holder may not make an application under this section on the ground that the possession claim was a retaliatory claim (within the meaning of section 217).
(6)The county court may confirm or quash the decision to make the claim.
(7)In considering whether to confirm or quash the decision, the county court must apply the principles applied by the High Court on an application for judicial review.
(8)If the county court quashes the decision it may—
(a)set aside the possession notice or (as the case may be) the landlord's notice and dismiss the possession proceedings;
(b)make any order the High Court could make when making a quashing order on an application for judicial review.
(9)The contract-holder may not make an application under subsection (3) after an order for possession has been made in respect of the dwelling.
(1)This section applies if the court makes an order for possession of a dwelling under section 215 or 216.
(2)The court may not postpone the giving up of possession to a date later than 14 days after the making of the order, unless it appears to the court that exceptional hardship would be caused if the giving up of possession were not postponed to a later date.
(3)The giving up of possession may not in any event be postponed to a date later than six weeks after the making of the order.
(4)The giving up of possession may be postponed by the order for possession, or by suspending or staying execution of the order for possession.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.
Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search. A point in time version is only available in English.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: