Commission Regulation (EU) 2016/1447Dangos y teitl llawn

Commission Regulation (EU) 2016/1447 of 26 August 2016 establishing a network code on requirements for grid connection of high voltage direct current systems and direct current-connected power park modules (Text with EEA relevance)

 Help about what version

Pa Fersiwn

 Help about advanced features

Nodweddion Uwch

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

Mae hon yn eitem o ddeddfwriaeth sy’n deillio o’r UE

Mae unrhyw newidiadau sydd wedi cael eu gwneud yn barod gan y tîm yn ymddangos yn y cynnwys a chyfeirir atynt gydag anodiadau.Ar ôl y diwrnod ymadael bydd tair fersiwn o’r ddeddfwriaeth yma i’w gwirio at ddibenion gwahanol. Y fersiwn legislation.gov.uk yw’r fersiwn sy’n weithredol yn y Deyrnas Unedig. Y Fersiwn UE sydd ar EUR-lex ar hyn o bryd yw’r fersiwn sy’n weithredol yn yr UE h.y. efallai y bydd arnoch angen y fersiwn hon os byddwch yn gweithredu busnes yn yr UE. EUR-Lex Y fersiwn yn yr archif ar y we yw’r fersiwn swyddogol o’r ddeddfwriaeth fel yr oedd ar y diwrnod ymadael cyn cael ei chyhoeddi ar legislation.gov.uk ac unrhyw newidiadau ac effeithiau a weithredwyd yn y Deyrnas Unedig wedyn. Mae’r archif ar y we hefyd yn cynnwys cyfraith achos a ffurfiau mewn ieithoedd eraill o EUR-Lex. The EU Exit Web Archive legislation_originated_from_EU_p3

Changes over time for: Commission Regulation (EU) 2016/1447 (Annexes only)

 Help about opening options

Changes to legislation:

Commission Regulation (EU) 2016/1447 is up to date with all changes known to be in force on or before 25 August 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to :

  • Regulation revoked by S.I. 2019/533 reg. 5(c) (This amendment not applied to legislation.gov.uk. Reg. 5 revoked on the day before IP completion day by S.I. 2019/1104, regs. 1(2), 2)
  • Art. 2 words omitted by S.I. 2024/706 reg. 42

ANNEX IU.K.Frequency ranges referred to in Article 11

Frequency rangeTime period for operation
[F147.0] Hz-[F247.5] Hz60 seconds
[F247.5] Hz-[F348.5] HzTo be specified by each relevant TSO, but longer than established times for generation and demand according to Regulation (EU) 2016/631 and Regulation (EU) 2016/1388 respectively, and longer than for DC-connected PPMs according to Article 39
[F348.5] Hz-[F449.0] HzTo be specified by each relevant TSO, but longer than established times for generation and demand according to Regulation (EU) 2016/631 and Regulation (EU) 2016/1388 respectively, and longer than for DC-connected PPMs according to Article 39
[F449.0] Hz-[F551.0] HzUnlimited
[F551.0] Hz-[F651.5] HzTo be specified by each relevant TSO, but longer than established times for generation and demand according to Regulation (EU) 2016/631 and Regulation (EU) 2016/1388 respectively, and longer than for DC-connected PPMs according to Article 39
[F651.5] Hz-[F752.0] HzTo be specified by each relevant TSO, but longer than for DC-connected PPMs according to Article 39

Table 1: Minimum time periods an HVDC system shall be able to operate for different frequencies deviating from a nominal value without disconnecting from the network.

ANNEX IIU.K.Requirements applying to frequency sensitive mode, limited frequency sensitive mode overfrequency and limited frequency sensitive mode underfrequency

A.Frequency sensitive modeU.K.

1.When operating in frequency sensitive mode (FSM):U.K.

(a)

the HVDC system shall be capable of responding to frequency deviations in each connected AC network by adjusting the active power transmission as indicated in Figure 1 and in accordance with the parameters specified by each TSO within the ranges shown in Table 2. This specification shall be subject to notification to the regulatory authority. The modalities of that notification shall be determined in accordance with the applicable F8... regulatory framework;

(b)

the adjustment of active power frequency response shall be limited by the minimum HVDC active power transmission capacity and maximum HVDC active power transmission capacity of the HVDC system (in each direction);

Figure 1: Active power frequency response capability of an HVDC system in FSM illustrating the case of zero deadband and insensitivity with a positive active power setpoint (import mode). ΔΡ is the change in active power output from the HVDC system. fn is the target frequency in the AC network where the FSM service is provided and Δf is the frequency deviation in the AC network where the FSM service is provided.

ParametersRanges
Frequency response deadband0-±500 mHz
Droop s 1 (upward regulation)Minimum [F90.1] %
Droop s 2 (downward regulation)Minimum [F90.1] %
Frequency response insensitivityMaximum 30 mHz

Table 2: Parameters for active power frequency response in FSM

(c)

the HVDC system shall be capable, following an instruction from the relevant TSO, of adjusting the droops for upward and downward regulation, the frequency response deadband and the operational range of variation within the active power range available for FSM, set out in Figure 1 and more generally within the limits set by points (a) and (b). These values shall be subject to notification to the regulatory authority. The modalities of that notification shall be determined in accordance with the applicable F10... regulatory framework;

(d)

as a result of a frequency step change, the HVDC system shall be capable of adjusting active power to the active power frequency response defined in Figure 1, in such a way that the response is:

(i)

as fast as inherently technically feasible; and

(ii)

at or above the solid line according to Figure 2 in accordance with the parameters specified by each relevant TSO within the ranges according to Table 3:

  • the HVDC system shall be able to adjust active power output ΔΡ up to the limit of the active power range requested by the relevant TSO in accordance with the times t1 and t2 according to the ranges in Table 3, where t1 is the initial delay and t2 is the time for full activation. The values of t1 and t2 shall be specified by the relevant TSO, subject to notification to the regulatory authority. The modalities of that notification shall be determined in accordance with the applicable F11... regulatory framework;

  • if the initial delay of activation is greater than [F120.5] second, the HVDC system owner shall reasonably justify it to the relevant TSO.

Figure 2: Active power frequency response capability of an HVDC system. ΔΡ is the change in active power triggered by the step change in frequency.

ParametersTime
Maximum admissible initial delay t 1[F130.5] seconds
Maximum admissible time for full activation t 2, unless longer activation times are specified by the relevant TSO30 seconds

Table 3: Parameters for full activation of active power frequency response resulting from frequency step change.

(e)

for HVDC systems linking various control areas or synchronous areas, in frequency sensitive mode operation the HVDC system shall be capable of adjusting full active power frequency response at any time and for a continuous time period;

(f)

as long as a frequency deviation continues active power control shall not have any adverse impact on the active power frequency response.

B.Limited frequency sensitive mode overfrequencyU.K.

1.

In addition to the requirements of Article 11 the following shall apply with regard to limited frequency sensitive mode — overfrequency (LFSM-O):

(a)

the HVDC system shall be capable of adjusting active power frequency response to the AC network or networks, during both import and export, according to Figure 3 at a frequency threshold f1 between and including [F1450.2] Hz and [F1550.5] Hz with a droop S3 adjustable from [F160.1] % upwards;

(b)

the HVDC system shall be capable of adjusting active power down to its minimum HVDC active power transmission capacity;

(c)

the HVDC system shall be capable of adjusting active power frequency response as fast as inherently technically feasible, with an initial delay and time for full activation determined by the relevant TSO and notified to the regulatory authority in accordance with the applicable F17... regulatory framework;

(d)

the HVDC system shall be capable of stable operation during LFSM-O operation. When LFSM-O is active, hierarchy of control functions shall be organised in accordance with Article 35.

2.

The frequency threshold and droop settings referred to in point (a) of paragraph 1 shall be determined by the relevant TSO and be notified to the regulatory authority in accordance with the applicable F18... regulatory framework.

Figure 3: Active power frequency response capability of HVDC systems in LFSM-O. ΔΡ is the change in active power output from the HVDC system and, depending on the operational conditions, either a decrease of import power or an increase of export power. fn is the nominal frequency of the AC network or networks the HVDC system is connected to and Δf is the frequency change in the AC network or networks the HVDC is connected to. At overfrequencies where f is above f1 the HVDC system shall reduce active power according to the droop setting.

C.Limited frequency sensitive mode underfrequencyU.K.

1.

In addition to the requirements of Article 11, the following shall apply with regard to limited frequency sensitive mode — underfrequency (LFSM-U):

(a)

the HVDC system shall be capable of adjusting active power frequency response to the AC network or networks, during both import and export, according to Figure 4 at a frequency threshold f2 between and including [F1949.8] Hz and [F2049.5] Hz with a droop S4 adjustable from [F210.1] % upwards;

(b)

in the LFSM-U mode the HVDC system shall be capable of adjusting active power up to its maximum HVDC active power transmission capacity;

(c)

the active power frequency response shall be activated as fast as inherently technically feasible, with an initial delay and time for full activation determined by the relevant TSO and notified to regulatory authority in accordance with the applicable F22... regulatory framework;

(d)

the HVDC system shall be capable of stable operation during LFSM-U operation. When LFSM-U is active, hierarchy of control functions shall be organised in accordance with Article 35.

2.

The frequency threshold and droop settings referred to in point (a) of paragraph 1 shall be determined by the relevant TSO and be notified to the regulatory authority in accordance with the applicable F23... regulatory framework.

Figure 4: Active power frequency response capability of HVDC systems in LFSM-U. ΔΡ is the change in active power output from the HVDC system, depending on the operation condition a decrease of import power or an increase of export power. fn is the nominal frequency in the AC network or networks the HVDC system is connected and Δf is the frequency change in the AC network or networks the HVDC is connected. At underfrequencies where f is below f2, the HVDC system has to increase active power output according to the droop s4 .

ANNEX IIIU.K.Voltage ranges referred to in Article 18

Synchronous AreaVoltage RangeTime period for operation
F24. . .F24. . .F24. . .
F24. . .F24. . .
F25. . .F25. . .F25. . .
F25. . .F25. . .
Great Britain[F260.90] pu-[F271.10] puUnlimited
F28. . .F28. . .F28. . .
F29. . .F29. . .F29. . .
F29. . .F29. . .

Table 4: Minimum time periods an HVDC system shall be capable of operating for voltages deviating from the reference 1 pu value at the connection points without disconnecting from the network. This table applies in case of pu voltage base values at or above 110 kV and up to (not including) 300 kV.

Synchronous AreaVoltage RangeTime period for operation
F30. . .F30. . .F30. . .
F30. . .F30. . .
F30. . .F30. . .
F31. . .F31. . .F31. . .
F31. . .F31. . .
Great Britain[F320.90] pu-[F331.05] puUnlimited
[F331.05] pu-[F341.10] pu15 minutes
F35. . .F35. . .F35. . .
F36. . .F36. . .F36. . .
F36. . .F36. . .

Table 5: Minimum time periods an HVDC system shall be capable of operating for voltages deviating from the reference 1 pu value at the connection points without disconnecting from the network. This table applies in case of pu voltage base values from 300 kV to 400 kV (included).

ANNEX IVU.K.Requirements for U-Q/Pmax-profile referred to in Article 20

F37

Figure 5: The diagram represents boundaries of a U-Q/Pmax-profile with U being the voltage at the connection points expressed by the ratio of its actual value to its reference 1 pu value in per unit, and Q/Pmax the ratio of the reactive power to the maximum HVDC active power transmission capacity. The position, size and shape of the inner envelope are indicative and shapes other than rectangular may be used within the inner envelope. For profile shapes other than rectangular, the voltage range represents the highest and lowest voltage points in this shape. Such a profile would not give rise to the full reactive power range being available across the range of steady-state voltages.

Textual Amendments

F37Annex 4 Figure 5: decimal point substituted for comma in each value in scales for X- and Y-axis of graph (31.12.2020) by virtue of The Electricity and Gas (Internal Markets and Network Codes) (Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1006), reg. 1(2), Sch. 3 para. 38(2)

Synchronous AreaMaximum range of Q/PmaxMaximum range of steady-state Voltage level in PU
F38. . .F38. . .F38. . .
F39. . .F39. . .F39. . .
Great Britain[F400.95][F410.225]
F42. . .F42. . .F42. . .
F43. . .F43. . .F43. . .

Table 6: Parameters for the Inner Envelope in the Figure.

ANNEX VU.K.Voltage-against-time-profile referred to in Article 25

Figure 6: Fault-ride-through profile of an HVDC converter station. The diagram represents the lower limit of a voltage-against-time profile at the connection point, expressed by the ratio of its actual value and its reference 1 pu value in per unit before, during and after a fault. Uret is the retained voltage at the connection point during a fault, tclear is the instant when the fault has been cleared, Urec1 and trec1 specify a point of lower limits of voltage recovery following fault clearance. Ublock is the blocking voltage at the connection point. The time values referred to are measured from tfault.

Voltage parameters [pu]Time parameters [seconds]
Uret[F440.00]-[F450.30]tclear[F460.14]-[F470.25]
Urec1[F470.25]-[F480.85]trec1[F491.5]-[F502.5]
Urec2[F480.85]-[F510.90]trec2Trec1-[F5210.0]

Table 7: Parameters for Figure 6 for the fault-ride-through capability of an HVDC converter station.

Textual Amendments

ANNEX VIU.K.Frequency ranges and time periods referred to in Article 39(2)(a)

Frequency rangeTime period for operation
[F5347.0] Hz-[F5447.5] Hz20 seconds
[F5447.5] Hz-[F5549.0] Hz90 minutes
[F5549.0] Hz-[F5651.0] HzUnlimited
[F5651.0] Hz-[F5751.5] Hz90 minutes
[F5751.5] Hz-[F5852.0] Hz15 minutes

Table 8: Minimum time periods for the 50 Hz nominal system for which a PPM shall be capable of operating for different frequencies deviating from a nominal value without disconnecting from the network.

ANNEX VIIU.K.Voltage ranges and time periods referred to in Article 40

Voltage RangeTime period for operation
[F590.85] pu-[F600.90] pu60 minutes
[F600.90] pu-[F611.10] puUnlimited
[F611.10] pu-[F621.118] puUnlimited, unless specified otherwise by the relevant system operator, in coordination with the relevant TSO.
[F621.118] pu-[F631.15] puTo be specified by the relevant system operator, in coordination with the relevant TSO.

Table 9: Minimum time periods for which a DC-connected power park module shall be capable of operating for different voltages deviating from a reference 1 pu value without disconnecting from the network where the voltage base for pu values is from 110 kV to (not including) 300 kV.

Voltage RangeTime period for operation
[F640.85] pu-[F650.90] pu60 minutes
[F650.90] pu-[F661.05] puUnlimited
[F661.05] pu-[F671.15] puTo be specified by the relevant system operator, in coordination with the relevant TSO. Various sub-ranges of voltage withstand capability can be specified.

Table 10: Minimum time periods for which a DC-connected power park module shall be capable of operating for different voltages deviating from a reference 1 pu value without disconnecting from the network where the voltage base for pu values is from 300 kV to 400 kV (included).

F68Figure 7: U-Q/Pmax-profile of a DC-connected power park module at the connection point. The diagram represents boundaries of a U-Q/Pmax-profile of the voltage at the connection point[s], expressed by the ratio of its actual value to its reference 1 pu value in per unit, against the ratio of the reactive power (Q) to the maximum capacity (Pmax). The position, size and shape of the inner envelope are indicative and other than rectangular may be used within the inner envelope. For profile shapes other than rectangular, the voltage range represents the highest and lowest voltage points. Such a profile would not give rise to the full reactive power range being available across the range of steady-state voltages.

Textual Amendments

F68 Annex 7 Figure 7: decimal point substituted for comma in each value in scales for X- and Y-axis of graph (31.12.2020) by virtue of The Electricity and Gas (Internal Markets and Network Codes) (Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1006), reg. 1(2), Sch. 3 para 40(4)

Range of width of Q/Pmax profileRange of steady-state Voltage level in pu
0-[F690.95][F700.1]-[F710.225]

Table 11: Maximum and minimum range of both Q/Pmax and steady-state voltage for a DC-connected PPM

ANNEX VIIIU.K.Reactive power and voltage requirements referred to in Article 48

Voltage rangeTime period for operation
[F720.85] pu-[F730.90] pu60 minutes
[F730.90] pu-[F741.10] puUnlimited
[F741.10] pu-[F751.12] puUnlimited, unless specified otherwise by the relevant system operator, in coordination with the relevant TSO.
[F751.12] pu-[F761.15] puTo be specified by the relevant system operator, in coordination with the relevant TSO.

Table 12: Minimum time periods for which a remote-end HVDC converter station shall be capable of operating for different voltages deviating from a reference 1 pu value without disconnecting from the network where the voltage base for pu values is from 110 kV to (not including) 300 kV.

Voltage rangeTime period for operation
[F770.85] pu-[F780.90] pu60 minutes
[F780.90] pu-[F791.05] puUnlimited
[F791.05] pu-[F801.15] puTo be specified by the relevant system operator, in coordination with the relevant TSO. Various sub-ranges of voltage withstand capability may be specified.

Table 13: Minimum time periods for which a remote-end HVDC converter station shall be capable of operating for different voltages deviating from a reference 1 pu value without disconnecting from the network where the voltage base for pu values is from 300 kV to 400 kV (included).

Maximum range of Q/PmaxMaximum range of steady-state voltage level in PU
[F810.95][F820.225]

Table 14: Maximum range of both Q/Pmax and steady-state voltage for a remote-end HVDC converter station.

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i mabwysiadwyd gan yr UE): Mae'r wreiddiol version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel adopted version that was used for the EU Official Journal
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

Mae’r llinell amser yma yn dangos y fersiynau gwahanol a gymerwyd o EUR-Lex yn ogystal ag unrhyw fersiynau dilynol a grëwyd ar ôl y diwrnod ymadael o ganlyniad i newidiadau a wnaed gan ddeddfwriaeth y Deyrnas Unedig.

Cymerir dyddiadau fersiynau’r UE o ddyddiadau’r dogfennau ar EUR-Lex ac efallai na fyddant yn cyfateb â’r adeg pan ddaeth y newidiadau i rym ar gyfer y ddogfen.

Ar gyfer unrhyw fersiynau a grëwyd ar ôl y diwrnod ymadael o ganlyniad i newidiadau a wnaed gan ddeddfwriaeth y Deyrnas Unedig, bydd y dyddiad yn cyd-fynd â’r dyddiad cynharaf y daeth y newid (e.e. ychwanegiad, diddymiad neu gyfnewidiad) a weithredwyd i rym. Am ragor o wybodaeth gweler ein canllaw i ddeddfwriaeth ddiwygiedig ar Ddeall Deddfwriaeth.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel adopted fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill