- Y Diweddaraf sydd Ar Gael (Diwygiedig)
- Gwreiddiol (a wnaed Fel)
There are currently no known outstanding effects for the The Air Quality Standards Regulations 2010.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Regulation 7(1)
General
1. Ambient air quality must be assessed at sampling points located in accordance with this Schedule, except at locations set out in paragraph 2.U.K.
2. Compliance with limit values directed at the protection of human health does not need to be assessed at the following locations—U.K.
(a)any location situated within areas where members of the public do not have access and there is no fixed habitation;
(b)on factory premises or at industrial locations to which all relevant provisions concerning health and safety at work apply;
(c)on the carriageway of roads and on the central reservations of roads except where there is normally pedestrian access to the central reservation.
3. Insofar as they are relevant, the principles set out in this Schedule also apply to indicative measurement and modelling.U.K.
Sampling points for the protection of human health
1. Sampling points directed at the protection of human health must be sited to provide data on—U.K.
(a)the areas within zones where the highest concentrations occur to which the population is likely to be directly or indirectly exposed for a period which is significant in relation to the averaging period of any limit value; and
(b)levels in other areas within the zones which are representative of the exposure of the general population.
2. Sampling points must in general be sited to avoid measuring very small micro-environments in their immediate vicinity. Where feasible, the Secretary of State must locate sampling points so as to be representative of air quality in a street segment of no less than 100m in length at traffic-orientated sites or an area of at least 250mx 250m at industrial sites.U.K.
3. Sampling points in urban background locations must be located so that their pollution level is influenced by the combined contribution from all sources upwind of the station. The pollution level should not be dominated by a single source unless such a situation is typical for a larger urban area. Those sampling points must, as a general rule, be representative for several square kilometres.U.K.
4. Where the objective is to assess rural background levels, the sampling point must not be influenced by agglomerations or industrial sites in its vicinity, i.e. closer than five kilometres.U.K.
5. Where contributions from industrial sources are to be assessed, at least one sampling point must be installed downwind of the source in the nearest residential area. Where the background concentration is not known, an additional sampling point must be situated within the main wind direction.U.K.
6. Sampling points must also, where possible, be representative of similar locations not in their immediate vicinity.U.K.
7. Account must be taken of the need to locate sampling points on islands, where that is necessary for the protection of human health.U.K.
Protection of ecosystems and vegetation
8. Sampling points targeted at the protection of ecosystems or vegetation must be sited more than 20 km away from agglomerations or more than 5 km away from other built-up areas, industrial installations or motorways or major roads with traffic counts of more than 50,000 vehicles per day. The Secretary of State must locate sampling points so as to be representative of air quality in a surrounding area of at least 1000 km². A sampling point may be sited at a lesser distance or to be representative of air quality in a less extended area, taking account of geographical conditions or opportunities to protect particularly vulnerable areas. Account must be taken of the need to assess air quality on islands.U.K.
1. Insofar as is practicable, sampling points must be situated in accordance with the following criteria—
[F1(a)the flow around the inlet sampling probe must be unrestricted (free in an arc of at least 270° or, for sampling points at the building line, 180°) without any obstructions affecting the airflow in the vicinity of the inlet (that is to say some metres away from buildings, balconies, trees and other obstacles and at least 0.5 m from the nearest building in the case of sampling points representing air quality at the building line);
(b)the inlet sampling point must be between 1.5 m (the breathing zone) and 4 m above the ground unless the station is representative of a large area and higher siting is appropriate. Any derogations must be fully documented;]
(c)the inlet probe must not be positioned in the immediate vicinity of sources in order to avoid the direct intake of emissions unmixed with ambient air;
(d)the sampler's exhaust outlet must be positioned so that recirculation of exhaust air to the sampler inlet is avoided;
(e)in relation to the location of traffic-orientated samplers, sampling points must be at least 25 m from the edge of major junctions and no more than 10 m from the kerbside. [F2A “major junction” is a junction which interrupts the traffic flow and causes different emissions (due to vehicles stopping and starting) from the rest of the road.]
Textual Amendments
F1Sch. 1 Pt. 3 para. 1(a)(b) substituted (31.12.2016) by The Air Quality Standards (Amendment) Regulations 2016 (S.I. 2016/1184), regs. 1(1), 3(a)
F2Words in Sch. 1 Pt. 3 para. 1(e) inserted (31.12.2016) by The Air Quality Standards (Amendment) Regulations 2016 (S.I. 2016/1184), regs. 1(1), 3(b)
2. The following factors may also be taken into account—U.K.
(a)interfering sources;
(b)security;
(c)access;
(d)availability of electrical power and telephone communications;
(e)visibility of the site in relation to its surroundings;
(f)safety of public and operators;
(g)the desirability of co-locating sampling points for different pollutants;
(h)planning requirements.
[F33. Any deviation from the criteria listed in this Part must be documented in accordance with Part 4.]U.K.
Textual Amendments
F3Sch. 1 para. 3 inserted (31.12.2016) by The Air Quality Standards (Amendment) Regulations 2016 (S.I. 2016/1184), regs. 1(1), 3(c)
Textual Amendments
F4Sch. 1 Pt. 4 inserted (31.12.2016) by The Air Quality Standards (Amendment) Regulations 2016 (S.I. 2016/1184), regs. 1(1), 4
1. The Secretary of State must for all zones and agglomerations fully document the site-selection procedures and record information to support the network design and choice of location for all monitoring sites.U.K.
2. The documentation must include compass-point photographs of the area surrounding monitoring sites and detailed maps.U.K.
3. Where supplementary methods are used within a zone or agglomeration, the documentation must include details of these methods and information on how the criteria listed in Article 7(3) of Directive 2008/50/EC are met.U.K.
4. The documentation must be updated as necessary and reviewed at least every 5 years, to ensure that selection criteria, network design and monitoring site locations remain valid and optimal over time.]U.K.
Regulation 17(1) and (2)
Averaging period | Limit value |
---|---|
One hour | 350 μg/m3 not to be exceeded more than 24 times a calendar year |
One day | 125 μg/m3 not to be exceeded more than 3 times a calendar year |
Averaging period | Limit value |
---|---|
One hour | 200 μg/m3 not to be exceeded more than 18 times a calendar year |
Calendar year | 40 μg/m3 |
Averaging period | Limit value |
---|---|
Calendar year | 5 µg/m3 |
Averaging period | Limit value |
---|---|
Calendar year | 0.5 µg/m3 |
Averaging period | Limit value |
---|---|
One day | 50 µg/m3, not to be exceeded more than 35 times a calendar year |
Calendar year | 40 µg/m3 |
Averaging Period | Limit Value | Date by which limit value is to be met |
---|---|---|
Calendar year | 20 μg/m3 | 1st January 2020] |
Textual Amendments
F5Words in Sch. 2 substituted (10.12.2020) by The Environment (Miscellaneous Amendments) (EU Exit) Regulations 2020 (S.I. 2020/1313), regs. 1(2), 2
1 The maximum daily eight hour mean concentration of carbon monoxide must be selected by examining eight hour running averages, calculated from hourly data and updated each hour. Each eight hour average so calculated will be assigned to the day on which it ends, that is, the first calculation period for any one day will be from 17:00 on the previous day to 01:00 on that day, the last calculation period for any one day will be the period from 16:00 to 24:00 on that day. | |
Averaging period | Limit value |
---|---|
Maximum eight hour daily mean1 | 10 mg/m3 |
Regulation 18(1)
1 The maximum daily eight hour mean concentration shall be selected by examining eight hour running averages, calculated from hourly data and updated each hour. Each eight hour average so calculated shall be assigned to the day on which it ends, that is, the first calculation period for any one day will be the period from 17:00 on the previous day to 01:00 on that day. The last calculation period for any one day will be the period from 16:00 to 24:00 on the day. | ||
2 If the three or five year averages cannot be determined on the basis of a full and consecutive set of annual data, the minimum annual data required for checking compliance with the target values will be valid data for one year in relation to the target value for the protection of human health and valid data for three years in relation to the target value for the protection of vegetation. | ||
Objective | Averaging period | Target value |
---|---|---|
Protection of human health | Maximum daily eight hour mean1 | 120 μg/m3 not to be exceeded on more than 25 days per calendar year averaged over three years2 |
Protection of vegetation | May to July | AOT 40 (calculated from 1 h values) 18,000 μg/m3 ∙h averaged over five years2 |
Averaging period | Target value |
---|---|
Calendar year | 25 μg/m3 |
Pollutant | Target value for the total content in the PM10 fraction averaged over a calendar year | Date by which target value should be met |
---|---|---|
Arsenic | 6 ng/m3 | 31st December 2012 |
Cadmium | 5 ng/m3 | 31st December 2012 |
Nickel | 20 ng/m3 | 31st December 2012 |
Benzo(a)pyrene | 1 ng/m3 | 31st December 2012 |
Regulations 8(1) and 20(1)
Objective | Averaging period | Long term objective |
---|---|---|
Protection of human health | Maximum daily eight hour mean within a calendar year | 120 μg/m3 |
Protection of vegetation | May to July | AOT 40 (calculated from 1h values) 6000 μg/m3∙h |
Regulation 21
1 To be measured over three consecutive hours at locations representative of air quality over at least 100 km 2 or an entire zone, whichever is smaller. | |
Pollutant | Alert threshold 1 |
---|---|
Sulphur dioxide | 500 µg/m3 |
Nitrogen dioxide | 400 µg/m3 |
Purpose | Averaging period | threshold |
---|---|---|
Information | 1 hour | 180 µg/m3 |
Alert | 1 hour | 240 µg/m3 |
Regulation 22
Averaging period | Critical level |
---|---|
Calendar year | 30 µg/m3 NOx |
Averaging period | Critical level |
---|---|
Calendar year and winter (1st October to 31st March) | 20 µg/m3 |
Regulation 24
Exposure reduction target relative to the AEI in 2010 | Year by which the exposure reduction target should be met | |
---|---|---|
Initial concentration in µg/m3 | Reduction target in % | 2020 |
Less than or equal to 8.5 | 0 | |
More than 8.5 but less than 13 | 10 | |
13 to less than 18 | 15 | |
18 to less than 22 | 20 | |
22 or more | All appropriate measures to achieve 18 µg/m3 |
Where the AEI in the reference year is 8.5 µg/m3or less, the exposure reduction target must be zero. The reduction target must also be zero in cases where the AEI reaches the level of 8.5 µg/m3at any point of time during the period from 2010 to 2020 and is maintained at or below that level.
Regulation 26(3)
1. Location of excess pollution—U.K.
(a)region;
(b)city (map);
(c)measuring station (map, geographical co-ordinates)
2. General information—U.K.
(a)type of zone (city, industrial or rural area);
(b)estimate of the polluted area (km2) and of the population exposed to the pollution;
(c)useful climatic data;
(d)relevant data on topography; and
(e)sufficient information on the type of targets requiring protection in the zone.
3. Responsible authorities (names and addresses of persons responsible for the development and implementation of air quality plans).U.K.
4. Nature and assessment of pollution—U.K.
(a)concentrations observed over previous years (before the implementation of the improvement measures);
(b)concentrations measured since the beginning of the project; and
(c)techniques used for the assessment.
5. Origin of pollution—U.K.
(a)list of the main emission sources responsible for pollution (map);
(b)total quantity of emissions from these sources (tonnes per year); and
(c)information on pollution imported from other regions.
6. Analysis of the situation—U.K.
(a)details of those factors responsible for exceeding the limit value or target value (transport, including cross-border transport, formation of secondary pollutants in the atmosphere); and
(b)details of possible measures for improvement of air quality.
7. Details of those measures or projects for improvements which existed prior to 11th June 2008—U.K.
(a)local, regional, national and international measures; and
(b)observed effects of those measures.
8. Details of those measures or projects adopted with a view to reducing pollution following 11th June 2008—U.K.
(a)listing and description of all the measures set out in the project;
(b)timetable for implementation;
(c)estimate of the improvement of air quality planned and of the expected time required to attain these objectives.
9. Details of the measures or projects planned or being researched for the long term.U.K.
10. List of the publications, documents and work etc. used to supplement information required by this Schedule.U.K.
Regulation 29(2)
1. In cases where either the information threshold or the alert threshold for nitrogen dioxide, sulphur dioxide or ozone is exceeded the details set out in paragraphs 3 to 6, as a minimum, must be made available to the public.U.K.
2. In cases where either the information or alert thresholds are predicted to be exceeded, the information set out in paragraphs 3 to 6 must be provided where practicable.U.K.
3. Information on any incident where information or alert thresholds are exceeded—U.K.
(a)the location or area where thresholds are exceeded;
(b)the type of threshold exceeded (information or alert threshold);
(c)the time at which the threshold was exceeded and the duration of the incident; and
(d)in the case of ozone, the highest 1-hour and 8-hour mean concentration.
4. Forecast for the following afternoon, day and days—U.K.
(a)the geographical area in which it is expected that an information or alert threshold will be exceeded;
(b)the expected change in pollution, that is, improvement, stabilisation or deterioration, and the reasons for those changes.
5. Information on the type of population concerned, possible health effects and recommended conduct in particular—U.K.
(a)information on the population groups at risk;
(b)description of likely symptoms;
(c)recommended precautions to be taken by the population concerned; and
(d)where to find further information.
6. Information provided under this Schedule must also include—U.K.
(a)information on preventive action to reduce pollution or exposure to it;
(b)an indication of main source sectors; and
(c)recommendations for action to reduce emissions.
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys