SCHEDULE 1PROVISIONS TO BE INCLUDED IN A LICENCE

Grant of a storage permit

1.  If a storage permit is granted under a licence then, subject to regulation 12, paragraphs 2, 3 and 4 of this Schedule apply in respect of the storage site authorised under that storage permit.

Closure of storage site by the operator

2.—(1) The operator must close the storage site where the conditions mentioned in regulation 8(1)(k) are met.

(2) The operator may close the storage site if—

(a)the consent of the authority has been given following an application under sub-paragraph (3), and

(b)any conditions attached to that consent have been met.

(3) An application for the authority’s consent to the closure of the storage site must—

(a)be made in writing and sent to the Department of Energy and Climate Change, and

(b)contain the reasons why the operator proposes to close the storage site.

(4) However, a storage site may not be closed under sub-paragraph (1) or (2) until the terms of the post-closure plan have been determined under regulation 13(3).

Post-closure plan

3.—(1) Prior to the closure of the storage site in accordance with paragraph 1(1) or (2) of this Schedule, the operator must submit a proposed post-closure plan to the authority for approval.

(2) That proposal must be based on the provisional post-closure plan, subject to any modifications proposed by the operator.

(3) In deciding whether to propose any such modifications, the operator must take into account—

(a)an analysis of the relevant risks;

(b)current best practice; and

(c)any improvements in the available technology.

Post-closure obligations

4.—(1) After the storage site has been closed and until the licence is terminated, the operator must continue to—

(a)monitor the storage site in accordance with paragraph 2 of Schedule 2,

(b)comply with its reporting and notification obligations in accordance with paragraph 3 of Schedule 2 (with the exception of sub-paragraph (5)(b)), and

(c)comply with its obligations to take corrective measures in accordance with paragraph 6 of Schedule 2.

(2) However, for those purposes any reference to the monitoring plan or the corrective measures plan is to be read as a reference to the post-closure plan.

(3) The operator must seal the storage site and remove the injection facilities in accordance with its obligations under Part 4 of the Petroleum Act 1998.

Extraction of stored CO2

5.  The operator must not (and must not permit any other person to) extract stored CO2 from the storage site except with the prior written consent of the authority and in accordance with any conditions subject to which any such consent is given.

Regulation 8(2)

SCHEDULE 2PROVISIONS TO BE INCLUDED IN A STORAGE PERMIT

Acceptance and injection of CO2

1.—(1) In order to be injected into the storage site the CO2 stream must consist overwhelmingly of carbon dioxide, and must in particular satisfy the conditions in sub-paragraph (2).

(2) The stream—

(a)must contain no waste or other matter added for the purposes of disposal;

(b)may contain incidental or trace substances (to the extent permitted by any legislation applicable to those substances), but only if the concentrations of all such substances are below the levels that would—

(i)adversely affect the integrity of the storage site or the relevant transport infrastructure, or

(ii)pose a significant risk to the environment or human health.

(3) In sub-paragraph (2)—

(a)incidental substance” means a substance which has become associated with the CO2 either at its original source or as a result of the process of capture or injection; and

(b)trace substance” means a substance which has been added to the CO2 in order to assist in the monitoring and verifying of its migration after injection.

(4) Before accepting and injecting the stream the operator must ensure that the conditions in sub-paragraphs (1) and (2) can be met, by carrying out—

(a)an analysis of the composition of the stream, and in particular of any corrosive substances that may be present in it, and

(b)an assessment of the risk that the stream will fail to comply with those conditions.

(5) The operator must maintain a register, at a place and in a manner approved by the authority, of the quantities and properties of the CO2 streams that have been delivered to, and injected in, the storage site (including the composition of those streams).

Monitoring

2.—(1) The operator must carry out a programme of monitoring of the storage complex and injection facilities, for the purposes specified in sub-paragraph (3).

(2) Such monitoring must include (where possible) the monitoring of the CO2 plume, and (where appropriate) of the surrounding environment.

(3) The purposes are—

(a)the comparison of the actual and modelled behaviour of the CO2 (and the naturally-occurring formation water) in the storage site;

(b)the detection of any significant irregularities;

(c)the detection of any migration of CO2;

(d)the detection of any leakage of CO2;

(e)the detection of any significant adverse effects on the surrounding environment, and in particular on—

(i)drinking water,

(ii)human populations, and

(iii)users of the surrounding biosphere;

(f)the assessment of the effectiveness of any corrective measures taken;

(g)updating the assessment of the safety and integrity, both short- and long-term, of the storage complex (including the assessment of whether the stored CO2 will be completely and permanently contained).

(4) The monitoring must be based on the monitoring plan.

(5) The monitoring plan must be updated in accordance with Annex II to the Directive, and in any event within five years of the approval of the original plan, in order to take account of—

(a)changes to the assessed risk of leakage;

(b)changes to the assessed risks to the environment and human health;

(c)new scientific knowledge; and

(d)improvements in best available technology.

(6) The updated plan must be submitted for approval by the authority.

(7) The authority may—

(a)approve that plan, or

(b)require the operator to make such modifications to it as the authority (after consulting the operator) considers necessary,

and the updated monitoring plan is the plan as so approved or modified.

(8) Sub-paragraphs (5) to (7) apply to the further updating of an updated plan as they apply to the updating of the original plan.

Reporting, and notification of leakages and significant irregularities

3.—(1) The operator must send to the authority a report in respect of each reporting period, containing the information specified in sub-paragraph (5).

(2) The report must be sent to the authority no later than four weeks after the end of the relevant reporting period.

(3) Unless the authority determines otherwise under sub-paragraph (4), the reporting periods are the period of one year beginning with the commencement of injection, and each subsequent yearly period.

(4) At any time before the commencement of injection, or during a current reporting period, the authority may notify the operator that (beginning with the next reporting period) reporting periods are to be a period of less than one year that is specified in the notice.

(5) The information is—

(a)the results of the monitoring carried out under paragraph 2 of this Schedule (including details of the monitoring technology employed);

(b)the quantities, properties and composition of the CO2 streams registered by the operator under paragraph 1(5) of this Schedule;

(c)proof that the financial security required by paragraph 7 of this Schedule has come into effect and remains in force;

(d)any other information requested by the authority that the authority considers relevant for the purposes of assessing compliance with the conditions of the storage permit or for increasing knowledge of the behaviour of the CO2 stored at the storage site.

(6) If the operator becomes aware of any leakages or significant irregularities, the operator must immediately notify the authority.

(7) If the operator becomes aware of any leakages, or of any significant irregularities which imply the risk of leakage, the operator must immediately notify the person who is the regulator in relation to the storage site for the purposes of legislation implementing the ETS Directive.

Notification and implementation of changes

4.—(1) The operator must notify the authority of any change planned in the operation of the storage site, including any change concerning the operator.

(2) A notification under sub-paragraph (1) must specify the target date.

(3) Except where sub-paragraph (4) applies, such a notification must be made at least three months before the target date.

(4) If the change solely concerns the operator, the notification must be made at least four weeks before the target date.

(5) The change may not be implemented before the later of—

(a)the target date, or any date notified under regulation 11(4)(b); and

(b)the date notified by the authority in accordance with regulation 11(1)(b)(ii).

(6) The change may not be implemented if the authority makes a notification to that effect under regulation 11(2)(b).

(7) However, notwithstanding sub-paragraphs (5) and (6), the change may be implemented on or after the later of the dates mentioned in sub-paragraph (5)(a) if the authority has not before then made a notification under regulation 11(1)(b)(ii) or (2)(b).

Review, and modification or revocation of the permit

5.  The permit is to be reviewed, and where necessary modified or (as a last resort) revoked, by the authority in accordance with regulation 11.

Corrective measures

6.—(1) If the operator becomes aware of any leakages or significant irregularities, the operator must take the necessary corrective measures and measures for the protection of human health.

(2) The measures taken must include those set out in the corrective measures plan (but this is subject to regulation 10(3)).

Financial security

7.—(1) The operator must maintain financial security that—

(a)is of an amount (“the secured amount”) sufficient to ensure that the obligations specified in sub-paragraph (5) can be met,

(b)is in force before the commencement of injection, and

(c)remains in force until the licence is terminated.

(2) However, if the storage permit is revoked the security must remain in force—

(a)until a new storage permit is granted, or

(b)if the storage site is closed following such revocation, until the licence is terminated.

(3) Following each report made by the operator in accordance with paragraph 3(1) to (5) of this Schedule, the authority is to assess whether the secured amount is appropriate in the light of—

(a)the assessed risk of leakage, and

(b)the estimated costs of meeting the obligations specified in sub-paragraph (5).

(4) If, following that assessment, the authority decides that the secured amount is to be adjusted—

(a)the authority must notify the operator of the new amount that is required, and

(b)where the secured amount is less than that new amount, the operator must ensure that it is increased to the new amount within three months of receiving that notification.

(5) The obligations are—

(a)all obligations of the operator arising under the storage permit, including those arising in respect of the closure of the storage site and during the period between such closure and the termination of the licence;

(b)the obligation to pay the authority’s costs under regulation 10(4)(b) or 12(6); and

(c)any obligations of the operator arising in respect of the storage site under legislation implementing the ETS Directive.

(6) Where the storage permit is revoked—

(a)the obligations of the operator under this paragraph continue in effect until the licence is terminated, but

(b)the assessment by the authority under sub-paragraph (3) is to be made at such intervals as the authority may determine.

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill