The Community Infrastructure Levy Regulations 2010

Status:

Point in time view as at 06/04/2020.

Changes to legislation:

There are currently no known outstanding effects for the The Community Infrastructure Levy Regulations 2010, PART 2. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

PART 2E+WDEFINITION OF KEY TERMS

Meaning of “owner” and “material interest”E+W

4.—(1) For the purposes of section 208 of PA 2008 (liability) a person is not an owner of the relevant land unless the person owns a material interest in the relevant land.

(2) A material interest in the relevant land is a legal estate in that land which is—

(a)a freehold estate; or

(b)a leasehold estate, the term of which expires more than seven years after the day on which planning permission first permits the chargeable development.

Commencement Information

I1Reg. 4 in force at 6.4.2010, see reg. 1

Meaning of “planning permission”E+W

5.—(1) For the purposes of Part 11 of PA 2008, “planning permission” means—

(a)planning permission granted by a local planning authority under section 70, 73 or 73A of TCPA 1990(1);

(b)planning permission granted by the Secretary of State under the provisions mentioned in sub-paragraph (a) as applied by sections 76A(10), 77(4) and 79(4) of TCPA 1990(2) (including permission so granted by a person appointed by the Secretary of State in accordance with regulations made under Schedule 6 to TCPA 1990);

(c)planning permission granted or modified under section 177(1) of TCPA 1990(3) (grant or modification of planning permission on appeals against enforcement notices);

(d)modification of a planning permission under section 97 or 100 of TCPA 1990(4);

(e)planning permission granted by an order made under section 102 or 104 of TCPA 1990(5) (orders requiring discontinuance of use or alteration or removal of buildings or works);

(f)development consent granted by an order made under section 114(1)(a) of PA 2008; or

(g)a general consent.

(2) But planning permission does not include planning permission granted for a limited period.

(3) In paragraph (1)(g) “general consent” means—

(a)planning permission granted—

(i)by a development order made under section 59 of TCPA 1990,

(ii)by a local development order adopted under section 61A of TCPA 1990(6),

[F1(iia)by a neighbourhood development order made under section 61E [F2or 61Q (community right to build orders)] of TCPA 1990,]

(iii)by a simplified planning zone scheme within the meaning of sections 82 and 83(7) of TCPA 1990,

(iv)in accordance with section 90 of TCPA 1990(8) (development with government authorisation), or

(v)by an enterprise zone scheme adopted under Schedule 32 to the Local Government, Planning and Land Act 1980(9); or

(b)development authorised by an Act of Parliament or an order approved by both Houses of Parliament which designates specifically the nature of the development authorised and the land on which it may be carried out.

Textual Amendments

Commencement Information

I2Reg. 5 in force at 6.4.2010, see reg. 1

Meaning of “development”E+W

6.[F3(1) The following works are not to be treated as development for the purposes of section 208 of PA 2008 (liability)—

(a)anything done by way of, or for the purpose of, the creation of a building of a kind mentioned in paragraph (2);

(b)the carrying out of any work to, or in respect of, an existing building if, after the carrying out of that work, it is still a building of a kind mentioned in paragraph (2);

(c)the carrying out of any work to, or in respect of, an existing building for which planning permission is required only because of provision made under section 55(2A) of TCPA 1990; and

(d)the change of use of any building previously used as a single dwellinghouse to use as two or more separate dwellinghouses.]

(2) The kinds of buildings mentioned in paragraph (1)(a) and (b) are—

(a)a building into which people do not normally go;

(b)a building into which people go only intermittently for the purpose of inspecting or maintaining fixed plant or machinery.

Textual Amendments

Commencement Information

I3Reg. 6 in force at 6.4.2010, see reg. 1

Commencement of developmentE+W

7.—(1) This regulation has effect for determining when development is to be treated as commencing for the purposes of Part 11 of PA 2008.

(2) Development is to be treated as commencing on the earliest date on which any material operation begins to be carried out on the relevant land.

(3) Paragraph (2) is subject to the following provisions of this regulation.

(4) Development is to be treated as commencing on the day planning permission is granted for that development if planning permission had previously been granted for that development for a limited period.

(5) Development for which planning permission is—

(a)granted under section 73A of TCPA (planning permission for development already carried out); or

(b)granted or modified under section 177(1) of TCPA 1990 (grant or modification of planning permission on appeals against enforcement notices),

is to be treated as commencing on the day planning permission for that development is granted or modified (as the case may be).

(6) In this regulation “material operation” has the same meaning as in section 56(4) of TCPA 1990(10) (time when development begun).

Commencement Information

I4Reg. 7 in force at 6.4.2010, see reg. 1

Time at which planning permission first permits developmentE+W

8.—(1) This regulation has effect for determining the time at which planning permission is treated as first permitting development for the purposes of Part 11 of PA 2008.

(2) Planning permission first permits development on the day that planning permission is granted for that development.

(3) Paragraph (2) is subject to the following provisions of this regulation.

[F4(3A) In the case of a phased planning permission, planning permission first permits a phase of the development—

(a)for any phase of an outline planning permission which is granted in outline—

(i)on the day of final approval of the last reserved matter associated with that phase; or

(ii)if earlier, and if agreed in writing by the collecting authority before commencement of any development under that permission, on the day final approval is given under any pre-commencement condition associated with that phase; and

(b)for any other phase—

(i)on the day final approval is given under any pre-commencement condition associated with that phase; or

(ii)where there are no pre-commencement conditions associated with that phase, on the day planning permission is granted.

(3B) In this regulation a “pre-commencement condition” is a condition imposed on a phased planning permission which requires further approval to be obtained before a phase can commence.]

(4) In the case of a grant of outline planning permission [F5which is not a phased planning permission], planning permission first permits development on the day of the final approval of the last reserved matter associated with the permission.

F6(5) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F6(6) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

[F7(7) In the case of a general consent, planning permission first permits development—

(a)on the day on which the collecting authority receives a notice of chargeable development submitted to it in accordance with regulation 64 in respect of that development; or

(b)if no notice of chargeable development is submitted in accordance with regulation 64, the day on which the last person is served with a notice of chargeable development in accordance with regulation 64A(3).]

Meaning of “chargeable development”E

9.—(1) The chargeable development is the development for which planning permission is granted.

(2) Paragraph (1) is subject to the following provisions of this regulation.

(3) Where planning permission is granted by way of a general consent, the chargeable development is the development identified in a notice of chargeable development submitted to the collecting authority in accordance with regulation 64 [F8, or prepared by the collecting authority in accordance with regulation 64A].

(4) In the case of a grant of [F9phased planning permission], each phase of the development is a separate chargeable development.

[F10(5) In Wales, where the effect of a planning permission granted under section 73 of TCPA 1990 is only to change a condition subject to which a previous planning permission was granted by extending the time within which development must be commenced, the chargeable development is the development for which permission was granted by the previous permission as if that development was commenced.

[F11(6) Where a planning permission is granted under section 73 of TCPA 1990, the chargeable development is the most recently commenced or re-commenced chargeable development.]

F11(7) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F11(8) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(9) For the purposes of [F12paragraph (6)], chargeable development is re-commenced where—

(a)the chargeable development (“the earlier development”) was commenced;

(b)work on the earlier development was halted and a different chargeable development (“the later development”) that was granted planning permission under section 73 of TCPA 1990 was commenced on the relevant land; and

(c)the later development was subsequently halted and the earlier development is continued.]

Extent Information

E1This version of this provision applies to England only; a separate version has been created for Wales only

Textual Amendments

Commencement Information

I6Reg. 9 in force at 6.4.2010, see reg. 1

Meaning of “chargeable development”W

9.—(1) The chargeable development is the development for which planning permission is granted.

(2) Paragraph (1) is subject to the following provisions of this regulation.

(3) Where planning permission is granted by way of a general consent, the chargeable development is the development identified in a notice of chargeable development submitted to the collecting authority in accordance with regulation 64 [F17, or prepared by the collecting authority in accordance with regulation 64A].

(4) In the case of a grant of [F18phased planning permission], each phase of the development is a separate chargeable development.

[F19(5) In Wales, where the effect of a planning permission granted under section 73 of TCPA 1990 is only to change a condition subject to which a previous planning permission was granted by extending the time within which development must be commenced, the chargeable development is the development for which permission was granted by the previous permission as if that development was commenced.

(6) Where the effect of a planning permission granted under section 73 of TCPA 1990 is to change a condition subject to which a previous planning permission was granted so that the amount of CIL payable calculated under regulation 40 (as modified by paragraph (8)) would not change, the chargeable development is the development for which planning permission was granted by the previous permission as if that development was commenced.

(7) Where the effect of the planning permission granted under section 73 of TCPA 1990 is to change a condition subject to which a previous planning permission was granted so that the amount of CIL payable under regulation 40 (as modified by paragraph (8)) would change, the chargeable development is the most recently commenced or re-commenced chargeable development.

(8) For the purposes of paragraphs (6) and (7), the liability to CIL under regulation 40 should be calculated in relation to an application made under section 73 of TCPA 1990 as if the date on which the planning permission granted under that application first permits development was the same as that for the application for planning permission to which the application under section 73 of TCPA 1990 relates.

(9) For the purposes of paragraph (7), chargeable development is re-commenced where—

(a)the chargeable development (“the earlier development”) was commenced;

(b)work on the earlier development was halted and a different chargeable development (“the later development”) that was granted planning permission under section 73 of TCPA 1990 was commenced on the relevant land; and

(c)the later development was subsequently halted and the earlier development is continued.]

Extent Information

E2This version of this provision applies to Wales only; a separate version has been created for England only

Textual Amendments

Commencement Information

I8Reg. 9 in force at 6.4.2010, see reg. 1

Meaning of “collecting authority”E+W

10.—(1) A charging authority is the collecting authority for CIL charged in its area.

(2) Paragraph (1) is subject to the following provisions of this regulation.

[F13(3) In relation to CIL charged by the Mayor—

(a)where the development subject to the levy, or any part of it, is situated in the area of a MDC, the MDC must collect that CIL and accordingly is the collecting authority for that CIL;

(b)where the development subject to the levy is in the area of more than one MDC, the MDC with the greatest proportion of the gross internal area of the development in its area must collect the that CIL and accordingly is the collecting authority for that CIL;

(c)in all other cases, the London borough council in whose area the development subject to the levy is situated must collect that CIL and accordingly is the collecting authority for that CIL.]

(4) In England a county council for an area for which there is more than one district council is the collecting authority for CIL charged in its area in respect of development for which it grants planning permission.

(5) A relevant consenting authority (P) may agree with a charging authority (C) that P shall be the collecting authority for CIL charged by C in respect of development for which P grants planning permission.

(6) In paragraph (5) “relevant consenting authority” means—

(a)the Homes and Communities Agency(11);

(b)an urban development corporation established by order of the Secretary of State under section 135(1) of the Local Government, Planning and Land Act 1980; F14...

(c)an enterprise zone authority designated under Schedule 32 to the [F15Local Government, Planning and Land Act 1980; or]

[F16(d)a Mayoral development corporation that is not a local planning authority for the purposes of section 206(5)(a) of PA 2008.]

(1)

Section 70 was amended by paragraph 14 of Schedule 7 to the Planning and Compensation Act 1991 (c. 34). Section 73 was amended by sections 42(2) and 51(3) of the Planning and Compulsory Purchase Act 2004 (c. 5). Section 73A was inserted by paragraph 16 of Schedule 7 to the Planning and Compensation Act 1991.

(2)

Section 76A was inserted by section 44 of the Planning and Compulsory Purchase Act 2004. Section 77 was amended by section 40(2)(d) of the Planning and Compulsory Purchase Act 2004, paragraph 18 of Schedule 7 to the Planning and Compensation Act 1991 and paragraph 2 of Schedule 10 to the Planning Act 2008 (c. 29). Section 79 was amended by section 18 of the Planning and Compensation Act 1991 and paragraph 4 of Schedule 10 to the Planning Act 2008.

(3)

Section 177(1) was amended by paragraph 24(1) of Schedule 7 to the Planning and Compensation Act 1991.

(4)

Section 97 was amended by paragraph 4 of Schedule 1 to the Planning and Compensation Act 1991. Section 100 was amended by paragraph 5 of Schedule 1 to the Planning and Compensation Act 1991.

(5)

Section 102 was amended by paragraph 6 of Schedule 1 and paragraph 21 of Schedule 7 to the Planning and Compensation Act 1991.

(6)

Section 61A was inserted by section 40(1) of the Planning and Compulsory Purchase Act 2004 and amended by the Planning Act 2008, sections 188 and 238 and Schedule 13.

(7)

Section 83 was amended by section 45 of the Planning and Compulsory Purchase Act 2004 and paragraph 2 of Schedule 5 to the Local Democracy, Economic Development and Construction Act 2009 (c. 20).

(8)

Section 90 was amended by paragraph 12 of Schedule 6 to the Planning and Compensation Act 1991, section 16(1) of the Transport and Works Act 1992 (c. 42) and paragraph 32(4) of Schedule 10 to the Environment Act 1995 (c. 25).

(10)

Relevant amendments to section 54 were made by paragraph 10 of Schedule 6 and paragraph 10(2) of Schedule 7 to the Planning and Compensation Act 1991 and section 40(2)(a) of the Planning and Compulsory Purchase Act 2004.

(11)

The Homes and Communities Agency was established by section 1 of the Housing and Regeneration Act 2008 (c. 17).

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill